Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Reason for
Fabrication is Not completed
failure
Mild steel plates were given on 3rd June, Stainless Steel liners supplied on 12th June But Fustners ( M12 Nuts and Bolts M16) were Not
why
supplied.
Why CAM failed to procure SS plate well in advance before releasing plan
Responsibility
Root Cause Action to procure SS plate was take late by cam
CAM
Reason for
Fabrication is Not completed
failure
There were 1060 drill holes with CSK. Mild steel plates were given on 3 rd June but Stainless Steel liners are not supplied on 13 th June .
Why
409 grade SS plate is not available at store
Why CAM failed to procure SS plate well in advance before releasing plan
Responsibility
Root Cause Action to procure SS plate was take late by cam
CAM
Item supplied on 25 May but Job started on 30 th May , Fitting completed on 4th June ( Qty 18, Welding completed on 5th June.
Why
Dressing completed on 7th June but job was not cleared by QA due to incomplete holes
Due to hole dia 90 mm was not cut at # 5 and at PO dia 22 hole was not mentioned to be done at fabrication so job is not
Why
passed.
Hole dia 90 mm to be cut at preparation and dia 22 to be done at Fabrication is not mentioned at PO.
Why
Responsibility
During detailing all gas cutting holes must be completed and all activity to be properly mentioned at
Root Cause
PO PED
Reason for
Fabrication was not completed
failure
Previously it was decided to buy shell upto 650 mm dia as KCP was unable to roll above 30mm thick. The thickness of shell is 36mm.
Why
Later on decision changed that shell to be rolled at shop. Shell fabrication completed on 3 rd June but failed to rectify ovality
Why KCP is not taking load and it is to be done at 250 Ton where 250 Ton is engaged with filler plate ( priority 5) which is higher priority
Responsibility
Root Cause Failed to take timely decision.
CAM
Reason for
Fabrication was not completed
failure
Job was B category so to complete side guard ( A category job ) and Conveyor Fitters were not engaged for 2 nd stage fitting.
why
Only 2 Gangs of fitters ( 4 nos) available at Group both gangs were engaged at above mentioned job . After completing fitting of
Why
conveyor fitting completed on 13th June.
Why One fitter has gone in long leave ( leave till 18, Due to son;s illness at Bagaluru so no fitter was available to restart Top Frame job.
Responsibility
Root Cause Resource constrain.
CAM
Reason for
Fabrication is Not completed
failure
why material was supplied on 13th but not as per drawing. ( there will be a 25* chamfer which is to be done at preparation not completed)
Why Marker failed to assess the chamfering so not marked on plate after CNC cutting.
Responsibility
Root Cause Mistake by PED.
PED
1 Detailing should be rechecked before releasing for item cutting 08.06.2019. PED
Reason for
Fabrication is Not completed
failure
Responsibility
Root Cause Focusing on higher priority jobs.
Prep
1 Time to complete RFD should be taken less to give focus on lower priority. 08.06.2019. PED
Reason for
Fabrication is Not completed
failure
Why Nesting available 26th April but PO is in MFG with 173 priority so not cut
Responsibility
Root Cause Focusing on higher priority jobs & RFD jobs.
Prep
1 Time to complete RFD should be taken less to give focus on lower priority. 08.06.2019. PED
Reason for
Fabrication is Not completed
failure
Material supplied till 11th June but till that time Material of Jamadoba Chute were supplied so all resources were depute to complete
why
Chute
Priority of Chutes are 3, 4 & 5. These are shut-down jobs. Materials of chutes supplied late ( SS plate on 12 june, which are to be
Why
drilled first ( 1287 Drill) which was a late supply .
Why To complete shut down jobs with higher priority lower priority were not focused
Responsibility
Root Cause Focusing on higher priority jobs & RFD jobs.
Prep
1 Time to complete RFD should be taken less to give focus on lower priority. 08.06.2019. PED
Reason for
Fabrication is Not completed
failure
Material supplied till 11th June but till that time Material of Jamadoba Chute were supplied so all resources were depute to complete
why
Chute
Priority of Chutes are 3, 4 & 5. These are shut-down jobs. Materials of chutes supplied late ( SS plate on 12 june, which are to be
Why
drilled first ( 1287 Drill) which was a late supply .
Why To complete shut down jobs with higher priority lower priority were not focused
Responsibility
Root Cause Focusing on higher priority jobs & RFD jobs.
Prep
1 Time to complete RFD should be taken less to give focus on lower priority. 08.06.2019. PED