Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
on
PWHT & HYDROTESTING
REAL QMD
1
Program objectives:
2
Program contents :
3
INDEX
Procedure 2 QM 00 ME 006
5
Purpose
6
Requirement Of Pre & Post Heating
7
Methods Of Pre Heating
8
Pre Heating In Case Of Interruption In Welding
• After welding is commenced, preheat shall be maintained till
PWHT is performed on P number 3, 4, 5A, 5B & 6 except all the
following conditions are satisfied
• For P-5B (Cr > 3%) & P-6, the weld is subjected to an
adequate intermediate heat treatment with a controlled rate of
cooling
9
• After cooling & before welding is resumed, visual
examination of the weld is performed to assure that no
crack have developed
• preheat to be applied, before welding resumes.
10
Post Heating
12
Surface Preparation :
13
Job knowledge of operator
14
PWHT (Post Weld Heat Treatment)
• This is the process of gradually and uniformly raising the
temperature of the weldment and base metal up to a certain
temperature, holding sufficient time at that temperature and
then gradually and uniformly cooling it to room temperature.
• Post weld heat treatment is required to be carried out on
weldment, as and when called for by Codes / Standard /
Specification. The purpose of PWHT may be either or all the
following reasons..
• To distribute the amount of Residual thermal stresses produced
during welding.
• To increase resistance to stress corrosion.
• To improve dimensional stability and ductility.
• To Temper the hard martensites as and when formed during
welding. 15
PWHT Temperature
16
Equipment for PWHT
18
Heating Elements
19
Heating Element position
21
PLACING OF HEATING BAND (COILING) & INSULATION
3T 3T T-Wall
Thickness
Fig-1
22
Thermocouples:
23
Thermocouple attachment shall be attached to the work
piece by Direct Wire Capacity Discharge method (Fig.2)
or by nut and bolt connection (Fig.3).
If the nut and bolt connection method is used (Fig.3),
the materials of nut-bolt shall be of compatible
composition with parent metal.
Tack Weld
6 mm
24
Number of Thermocouple's:
27
Thermal Insulation:
28
Verification :
32
CHAPTER-2: HYDRO TESTING
• References
• Purpose
• Equipment
• Pretest requirements
• System test pack
• Preparation of system for testing
• Test medium
• Testing procedure
• On revelation of leak
• Post test procedure
• Test records
33
References
34
Purpose
35
Equipments
36
Pre Test Requirements
38
System Test Pack
41
Test Medium
42
Testing Procedure
• Prior to filling the system with the test medium, the system
shall be inspected for fabrication completeness and
satisfactory test pack documents to be prepared and signed
by concerned QMD lead and disciplined engineer.
• After completion of flushing or purging, the area around the
system under test shall be cleared of unauthorised personnel.
• Liquid testing medium shall be introduced at the system low
point to avoid air pocket formation. Vents at high points shall
be left open and not closed until test medium flow from the
outlet
• Hydro test shall not commence till the test fluid temperature
is in equilibrium with pipe work system. Rate of pressure
increase shall be less than 5 bar/min.
43
• Pressurise the system to the specified test pressure and hold for
10 minutes to allow piping strain to equalise. Once achieved
inspect the complete system. Examinations for leakage shall be of
all joints and connections. The piping system exclusive of possible
localised instances at pump or valve packing shall show no visual
evidence of weeping or leaking. On completion of the check and if
no leaks are detected then leave the system for a further 30
minutes to complete the test.
• Testing at night shall be restricted to small systems only and at
ground level and there must be adequate illumination to detect
even the smallest leakage. There shall be no testing of systems in
pipe racks or elevated structures between sunset and sunrise.
• A system under test pressure shall never be left unattended. If a
test cannot be completed before the end of a work period, the
system shall be depressurised. The contractor shall be responsible
for all safety precautions and procedures during testing. 44
On Revelation of Leakage
45
Post Test Pressure