 Issues

 Awarded Housing Units


 Manpower and Equipment
Monitoring
 Project Accomplishment
 Updated Photos
PROJECT ACCOMPLISHMENT
AS OF AUGUST 28, 2018
No.of Units TARGET ACTUAL VARIANCE
I. HOUSING UNITS 332 26.50% 13.21% 13.29%
PER BLOCK:
BLOCK 2 LOT 17-33 (ECI) 17 74.04% 81.17% -7.138
BLOCK 2 LOT 1-12 (ECI) 12 45.77% 50.90% -5.13%
BLOCK 2 LOT 34-42 (ECI) 9 56.29% 62.32% -6.03%
BLOCK 1 LOT 1-6 (ECI) 6 53.52% 58.09% -4.57%
BLOCK 3 LOT 1-9 (ECI) 9 31.61% 34.15% -2.54%
BLOCK 3 LOT 10-18 (YNOT) 9 45.81% 45.34% 0.47%
BLOCK 16 LOT 1-16 (YNOT) 16 15.41% 16.15% -0.74%
BLOCK 13 LOT 10-27(CATIPAY) 18 12.52% 13.21% -0.69%
BLOCK 10 LOT 1-14 (NACUA) 14

II. LAND DEVELOPMENT


III. AMMENITIES
Manpower Monitoring (EMZALVE)
Daily Monitoring
Nov 12 Nov 13 Nov 14 Nov 15 Nov 16 Nov 17
Description
2018 2018 2018 2018 2018 2018
PM 0 0 0 0 0 0
Project Engr. 0 0 0 0 0 0
Foreman 1 1 1 1 1 1
Timekeeper 0 0 0 0 0 0
Warehouseman 1 1 1 1 1 1
Leadman 2 2 2 2 2 1
Electrician/Plumber 2 2 2 2 2 1
Welder 0 0 0 0 0 0
Mason 9 9 8 9 9 12
Carpenter/Installer 5 5 5 6 5 7
Painter 0 0 0 0 0 0
S. Skilled 3 3 3 3 3 3
Labor / Helper 14 13 12 15 13 19
Operator 2 2 2 2 2 2
TOTAL 41 40 38 43 40 47
Manpower Monitoring (RENATO YNOT)

Daily Monitoring
Nov 12 Nov 13 Nov 14 Nov 15 Nov 16 Nov 17
Description
2018 2018 2018 2018 2018 2018

Foreman 1 1 1 1 1 1
Mason 2 2 2 2 2 2
Welder 1 1 1 1 1 1
Labor 16 15 16 19 15 20
Carpenter 3 3 3 3 3 3
Installer 3 3 3 3 3 3
Steelman 1 1 1 1 1 1

TOTAL 27 26 27 30 24 31
Manpower Monitoring (ONE PIECE CONSTRUCTION)

Daily Monitoring

Nov 12 Nov 13 Nov 14 Nov 15 Nov 16 Nov 17


Description
2018 2018 2018 2018 2018 2018

Foreman 1 1 1 1 1 1
Leadman 1 1 1 1 1 1
Paintor 12 12 8 8 8 8
Mason 8 8 7 7 7 7
Welder 2 2 2 2 2 2
Labor 26 26 21 19 22 20
Carpenter 4 7 4 4 4 4
Installer 7 7 2 2 2 2
Steelman 3 3 3 3 3 3

TOTAL 64 67 49 47 50 48
Manpower Monitoring (JEFFREY H. NACUA BUILDERS)
Daily Monitoring

Nov 12 Nov 13 Nov 14 Nov 15 Nov 16 Nov 17


Description
2018 2018 2018 2018 2018 2018

Foreman 1 1 1 1 1 1
Mason 1 1 1 1 1 1
Welder 0 0 0 0 0 0
Labor 2 5 4 6 5 3
Paintor 0 6 5 7 6 4
Carpenter 1 2 2 2 2 2
Steelman 1 2 2 2 2 2

TOTAL 6 17 15 19 17 15
Equipment Monitoring

Nov 12 Nov 13 Nov 14 Nov 15 Nov 16 Nov 17


Description
2018 2018 2018 2018 2018 2018

MIXER (1CUM) 1 1 1 1 1 1

DUMPTRUCK 1 1 1 1 1

BACKHOE 2 2 3 3 3 3
WORLDWIDE CENTRAL PROPERITES, INC.
Coordination Meeting CMD, PMD, TPD, Purchasing & Accounting
30-Aug-18
Time: 2:00 PM to 7:00 PM
Venue: Conference Room

BEVERLY PROJECT
TIMELINE
PROJECT/ WORK ITEM IN-CHARGE STATUS NEXT STEP
Start Deadline

PVC doors for 17 units


1 Doors Purchasing delivered on site Last 2nd follow-up on wooden doors
week of August, 2018

Submersible pump for


Water Pumps and Overhead Installation of couplings and
2 1-Sep-18 TPD/CMD installation. Overhead tank
tank pumps
for quotation
3 STP including Civil works TPD for update
4 MECO (MOA) for update
5 MCWD for update

Block 2 lot 17 (Davies),


We instructed Emazlve to
almost done. Finalization for
6 Paint 3-Sep-18 CMD prepare Block 2 lot 18 for
evaluation and checking of
mock-up (Boysen)
actual quantities.

ISSUES/CONCERNS:
PROJECT UPDATE:

1. PROJECT SCHEDULE

2. PROGRESS MONITORING

3. PROGRESS PHOTOS
TAKE-OVER BY NACUA BUILDERS

ONGOING PRIMER
COATING

ONGOING BASE
PREPARATION

BLOCK 2 LOT 17-33 - ECI


TAKE-OVER BY ONE PIECE

ONGOING
HOUSEKEEPING

ONGOING MASONRY
AND ROOF FRAMING

BLOCK 2 LOT 1-12 - ECI


TAKE-OVER BY ONE PIECE

ONGOING BASE
PREPARATION AT
GROUND FLOOR

ONGOING CEILING
AND WAL FRAMING

BLOCK 1 LOT 1-6 - ECI


TAKE-OVER BY RENATO YNOT

ONGOING MASONRY
AND BASE
PREPARATION

ONGOING FRAMING
AND BOARD
INSTALLATION

BLOCK 2 LOT 34-42 -ECI


TAKE-OVER BY RENATO YNOT

ONGOING STAIR
FORMWORKS

CONCRETED 2ND
FLOOR BEARING
WALL

BLOCK 3 LOT 1-9 - ECI


ONGOING GROUND
BASE PREPARATION

ONGOING FRAMING
AND BOARD
INSTALLATION

BLOCK 3 LOT 10-18-YNOT


ONGOING STAIR
CONCRETE POURING

2ND FLOOR BEARING


WALL READY FOR
CONCRETE POURING
(STRUCTURAL)
BLOCK 16 LOT 1-16 - YNOT
ONGOING STAIR
FORMWORKS

ONGOING MASONRY
AND ROOF FRAMING

BLOCK13 LOT 10-27 - CATIPAY


CONCRETED
GROUND BEARING
WALL AND SLAB

ONGOING FORMWORKS
AT SECOND FLOOR

BLOCK13 LOT 1-9 - CATIPAY


ONGOING
STRUCTURAL
(GRADE BEAM)

ONGOING
FORMWORKS
(GROUND FLOOR)

BLOCK 10 LOT 1-14 - NACUA


1 2
SEE ACTUAL PHOTOS

2
1
3

CONCRETE
POURING
MANHOLE AND
4 RCP LAYING
PREPARATION
ALONG ROAD 10

3 4

EXCLUDING PRELIMINARIES
Previous This Period To Date
(August 18, 2018) (august 18-25, 2018) (as of August 25, 2018)

Target 47.36 % 2.08% 49.44% ROAD CONCRETE


SOIL BREAKING FOR
POURING ALONG
Actual 40.12% 1.18% 41.92% MANHOLE LAY-OUT
ROAD 9
Variance 2.87% -7.52%

LAND DEVELOPMENT
AWARDED HOUSING UNITS
EXCAVATED AREAS FOR RCP LAYING
RCP LAYING
DRAINAGE MANHOLE
SEWER JUNCTION BOX
SEWER LINE
SAND BEDDING
WATERLINE

LAND DEVELOPMENT
ROAD CONCRETE POURING
LEGEND :
ROAD PREPARATION
CONCRETED ROAD