Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Introduction
Advantages of rigid pavement
Materials
Types of rigid pavement
Types of joints
Sealing of joints
Construction procedure
Distresses in rigid pavement
Concrete pavements have been used for highways, airports, streets, local
roads, parking lots, industrial facilities, and other types of infrastructure.
“Concrete generally has a higher initial cost than asphalt but lasts longer
and has lower maintenance costs” (Hoel and Short 2006: 26).
Long life
Maintenance free performance
Good riding quality
Good abrasion resistance
Ability to withstand extremes of weather
Exclusion of water
Effect of oil spillage
Skid resistant
Cement
Ordinary Portland Cement (33 grade, 43 grade , 53 grade )
Portland Pozzolana Cement (33 grade)
Portland slag cement (33 grade)
Composite cement (blended with slag and fly ash)( 33 grade)
Admixtures
Fly ash : 25% by weight of CM with OPC
Ground granulated blast furnace slag : 50% by weight of CM with OPC
Silica fumes : 10% by weight of CM
Metakaoline : 20% by weight of CM
Fine aggregate
PHYSICAL CHARACTERISTICS :
Clay lumps ≤ 1 %
Coal and Lignite ≤ 1%
Material passing : Natural sand - ≤ 3 %
IS Sieve 75 Micron : Crushed stone sand - ≤ 15 %
: Blend of natural sand and crushed stone and ≤ 8 %
Soundness / Water absorption : Same as for Coarse Aggregates
Temperature reinforcement
TMT bars
Fibres
Reduce shrinkage cracking
Improve post cracking residual strength
Steel fiber or polymeric synthetic fiber
Preformed seals
Valcanized elastomeric compound using polychloroprene (Neoprene) as the
base polymer
Joint sealing
Hot sealants or cold sealants with chemical formulation like
polysulphide / silicone / polyurethane or other similar formulation may
be used for sealing.
Overheated and reheated material should be avoided
Quantity of sealing compound required for one operation of joint sealing work
shall only be heated.
Transverse joint
• Expansion joint
• Contraction joint
• Construction joint
Longitudinal joint
Early entry saw cut joint
Temporary seal (jute rope) shall be provided for blocking ingress or dirt,
stone pieces etc.
After the concrete slabs have been cured, before allowing for traffic, joints
shall be widened to 10 mm width and depth of 20 mm for sealing.
Joints can also be formed by pressing a mild steel T section into the fresh
concrete.
For accurate placing of dowels at the end of the day, strong bulkheads made of
steel with holes drilled along the centre line shall be used. If considered
convenient, two piece bulkheads may be used.
Dry cutting operation with specially designed blade , do not require water for
cooling
Up cutting rotation blade : to keep debris out of joint
Light weight device is used
Sealant shall be applied slightly to a lower level than slab with a tolerance of 3 ±
1 mm
The sub grade shall be of coarse grained material and have a minimum CBR
of 8%
The camber and super elevation shall be same as that of the concrete slab.
Side forms shall be of mild steel sections of depth equal to the thickness of
the pavement with provision for insertion of tie bars wherever essential.
At least three stake pickets for each 3m of form shall be provided with ample bracing
and support to prevent springing of the forms under the pressure of concrete.
Wooden forms shall be held by stakes set at intervals not exceeding 2m.
Wooden forms shall be capped along the inside upper edge with 30-50mm
angle iron, well recessed and kept flush with the face of the wooden forms.
All forms shall be cleaned and oiled each time they are used.
Forms shall be removed only after the concrete has set for at least 12
hours.
After removal of forms, the ends shall be cleaned and any honey combed
sub-base to act as a separation layer between the subbase and concrete slab.
• Separation member shall be transparent or white in colour and laid flat with
atleast 300 mm
• placing polythene membrane, the existing subbase shall be wetted with water.
• Aggregate stock piling may be done on the ground if it is, without vegetation, levelled,
compacted with good quality sub-base material and is well drained.
• Each separate size of coarse aggregate should be stacked separately and separated by
wooden or steel partition to avoid inter-mixing
• Moisten the fine grained aggregate aggregates to avoid them getting blown away.
Batching of Materials:
• All batching materials should be by weight.
• After determining the proportion of each ingredient the fine aggregate and
each proportioned coarse aggregate shall be weighed and approved and
placed into the hopper of the mixer along with the necessary quantity of
cement.
• Inadequate compaction induces presence of excess voids. Presence of 5% voids reduce the
strength from that of fully completed concrete by about 30% and presence of 10% voids will
• Work on gradients: The progress on gradient of placing, compacting and finishing of concrete should
proceed from the lower to the higher reaches. The concrete mix shall be stiffer than that used on level
reaches. In case of very steep gradient, or where fill up areas/ very weak subgrade is there,
reinforcement in single layer or in two layers in the PQC may be provided. Slump of concrete mix in
After final floating and finishing and before application of the liquid curing
membrane, the surface shall be textured by TINING or BRUSH TEXTURING
The pavement shall be given a broom finish with an approved clean steel or
fibre broom not less than 450mm wide.
Texturing (Brooming) shall be perpendicular to the centre line of the
pavement, and the texture shall be uniform in character and width, and not
more than 1.5 mm deep (This value is 1 ± 0.25mm as per IRCL15-2011)
Measurement of texture by using an sand patch method.
texturing brush
Curing compound has water retention efficiency of not less than 90%.
Map cracking
• Series of cracks that extends only on surface of slab.
• These type of cracks caused by excessive bleeding and plastic shrinkage
Polished aggregates
• In this surface mortar and texturing warn away
• To expose aggregates
scaling
the deterioration of the upper concrete slab surface, normally 3–13 mm (1/8-
1/2 inch), and may occur anywhere over the pavement.
Blowups-
It is an upward movement of pavement at transverse joint and cracks.
It is buckling failure due to compressive stress in concrete pavement
Corner breaks-
Triangular pieces at corner about (30cm)
Joint spalling-
Breaking, cripping fraying of slab
Faulting
Faulting is defined as “difference in elevation across a joint or crack ”.
Faulting is most likely for pavements with aggregate interlock joints, or at
mid-slab cracks in JPCP.
As traffic moves across the joint it imposes impact loads on the leave slab,
forcing loose materials from under the leave slab to under the approach
slab. This phenomenon is termed pumping