Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
project management
Professional Diploma
in Procurement and Supply
Programme to project
management relationship
Programme management defined
• Managerial costs
costs linked to the management of relationships, involving contract
management, solving problems, visits, quality improvement and other
forms of development activities
Difficulties arising from
nominating subcontractors
• The main contractor may not feel the same sense of
responsibility for subcontractors that have been nominated
• The purchaser will generally take on a greater responsibility
for the co-ordination of work to be done by the nominated
subcontractor
• Main contractors will tend to limit liability for the work that is
to be performed by nominated subcontractors and so will
guard against any defaults in the time or quality of the work
provided
Exercising control over the use of
subcontractors
• To encourage main contractors for projects and programmes
to source subcontractors from SMEs, which will help promote
business opportunities to businesses in local communities
• To ensure that main contractors do not source from
subcontractors that may represent a risk to the supply chain
• To ensure that the number of subcontractors that work on site
is restricted, as the multiplicity of subcontractors can cause
difficulties in labour relations
Types of joint venture
• Vertical joint venture
the activities of the partners tend to follow on from each other in
sequence
• Horizontal joint venture
where the partners will generally carry out their work in parallel, so
that they work together to create the project or programme
• Homogeneous joint venture
where the partners will be operating in broadly the same industry
• Heterogeneous joint venture
where the partners will be operating in different industries and will
therefore have specialisations in different disciplines
Traditional supplier relationships
• The purchasing department will take the responsibility for order
placement with external suppliers and contractors but has little
direct contact with these to develop value-added outcomes
• Purchasing functions will be led by conformance to procedures
and processes, with the department administering the tendering
of contracts
• Selection of suppliers and contractors is done primarily on
pricing
• Relationships with suppliers and contractors will tend to be
adversarial, lacking trust and of an arm’s length nature and
relying on competitive pressure to drive improvements in value-
added outcomes
Common features of partnering
• Problem resolution
• Continuous improvement
• Supply chain network
• The behaviour of purchasers
• The behaviour of main contractors
• The behaviour of consultants
• The behaviour of subcontractors
Key principles of partnering
• Early involvement of key members of the project team
• Selection of suppliers on the basis of value, not lowest price
• Common processes, such as shared IT
• A commitment to measurement of performance as the
basis for continuous improvement
• Long-term relationships in the supply chain
• Modern commercial arrangements based on target cost or
target price with incentivisation through shared pain and
gain
Partnership success factors
• Team integration
How well integrated is the programme and project team?
Are there effective and coordinated links between the client and the supplier officers?
• Advisory support
Are appropriate technical advisors on hand at the key times to support clear strategic
and operational thinking?
Is the advisory support biased to the customer or the supplier viewpoint?
• Stakeholder engagement
Do the engaged stakeholders represent an appropriate spread of customers and end
users?
What are the rules of engagement and are those clearly understood by both parties?
• A middle phase
in which work gets under way and rapid progress is made as resources
are deployed productively
• An ending phase
in which progress slows
The project lifecycle
Time distribution of project effort
Project lifecycle for baking a cake
Alternatives to the ‘S’-shaped
lifecycle
Estimates of project cost
Maylor’s four-phase project lifecycle
Phase Key issues Fundamental questions
D1: Define the Project and organisational • What is to be done?
project strategy, goal definition • Why is it to be done?
D2: Design the Modelling and planning, • How will it be done?
project process estimating, resource • Who will be involved in each
analysis, conflict resolution part?
and justification • When can it start and finish?
D3: Deliver the Organisation, control, • How should the project be
project (do it!) leadership, decision making managed on a day-to-day
and problem solving basis?
D4: Develop Assessment of process and • How can the process be
the process outcomes of the project, continually improved?
evaluation, changes for the
future
Cumulative expenditure
Weiss and Wysocki’s lifecycle
PHASE ACTIVITIES
Definition • State problem • Obtain preliminary resources
• Identify goals • Identify assumptions and risks
• List objectives
Planning • Identify project activities • Identify which activities are
• Estimate time and cost critical
• Sequence activities • Write project proposal
Organising • Obtain resources • Organise project team
• Recruit project leader • Assign work packages
• Recruit project team
Controlling • Define management style • Review project schedule
• Establish control tools • Issue change orders
• Prepare sitreps
Closing • Gain client acceptance • Issue final report
• Install deliverables • Conduct review of the project
• Document the project
Elements of a project plan
ELEMENT DESCRIPTION
Overview A short summary of the project objectives and scope
Objectives This contains a more detailed statement of technical and profit goals
General approach Describes both the managerial and the technical approaches to the work
Contractual aspects This includes a list of all reporting requirements, customer-supplied
resources, liaison arrangements, review and cancellation procedures etc
Schedules This lists all tasks and milestones with estimated dates
Resources This includes the budget and the cost monitoring and control procedures
Personnel This defines the skills and expertise needed for the project
Risk management This covers both potential problems and potential lucky breaks, with
plans planned responses
Evaluation methods Standards should be established at the project’s inception against which
its eventual success or failure can be evaluated
Three levels of organisation
• The technical level
This is concerned with the performance of specific operations or tasks
associated with the performance of the project.
• Cost sharing
where the supplier stands to benefit from its own work. In such cases,
the buyer and supplier may agree on a fair basis for sharing the costs
(often 50: 50).
• Joint ventures
Costs of the project are met partly from public funds and partly from
other sources with overall control of the project being in private
sector hands.
Risks associated with PFI funding
mechanisms
• Design and construction risks
• Commissioning and operating risks
• Demand risks
• Final residual value risks
• Technology and obsolescence
• Regulation risks
• Project finance risks
• Contractor default risks
Types of cashflow
• Cash outflows might include the cost of capital equipment, any loan
interest payable, wages and salaries of new employees taken on as part of
the project, and tax payable on the profits arising.
• Cash inflows might include increased cash receipts from customers,
savings in operating costs arising from increased efficiency, and possibly
any reductions in tax bills.
• Net cashflows in any period are the cash inflows less cash outflows for that
period.
• There are also opportunity costs of capital. This means the benefit forgone
by investing in the chosen project rather than the next best alternative.
• Finally, there is the impact of depreciation. Depreciation is not a cashflow
– it is merely a ‘book entry’, reclassifying capital expenditure as operating
expenditure.
Cashflows for Project A
Net cashflow Cumulative
each year cashflow
£ £
Year 0 (200,000) (200,000)
Year 1 50,000 (150,000)
Year 2 50,000 (100,000)
Year 3 50,000 (50,000)
Year 4 50,000 0
Year 5 50,000 50,000
Cashflows for Project B
Net cashflow Cumulative
each year cashflow
£ £
Year 0 (200,000) (200,000)
Year 1 20,000 (180,000)
Year 2 20,000 (160,000)
Year 3 20,000 (140,000)
Year 4 80,000 (60,000)
Year 5 80,000 20,000
Year 6 80,000 100,000
Weaknesses of the ARR approach
• It takes no account of the project’s life
A 20 per cent return may seem more attractive than a 15 per cent
return, but a project offering 15 per cent for five years may be more
attractive than one that offers 20 per cent for only two years.
• Level 2
At an organisational level so that activities and individuals working on
the project are shown on the chart
• Level 3
At a micro or detailed level so that tasks are detailed with individuals
responsible for the work identified
Project selection
• The sacred cow
A project is suggested by a senior and powerful official in the organisation. Less senior managers
have no option but to implement it, no matter how poorly thought out it may be.
• Likelihood refers to the probability that the risk may occur, given its
nature and the current risk management practices in place
• A low likelihood indicates that the risk is unlikely to occur, given its nature and current
risk management practices in place.
• A medium likelihood of occurrence indicates that the risk has a moderate probability of
occurrence.
• A high likelihood of occurrence indicates that the risk is likely to occur, despite the risk
management practices in place.
An impact/likelihood grid
Normal distribution
A Monte Carlo simulation
Number of times the simulation Percentage of simulation runs where
result was less than or equal to the the result was less than or equal to
Total project duration Total Project Duration the Total Project Duration
11 5 1%
12 20 4%
13 75 15%
14 90 18%
15 125 25%
16 140 28%
17 165 33%
18 275 55%
19 440 88%
20 475 95%
21 490 98%
22 495 99%
23 500 100%
Benefits of a risk register
• Provide a useful tool for managing and reducing the risks
identified before and during the project
• Provide the project sponsor, Board or senior management
with a documented framework from which risk status can be
reported
• Ensure the communication of risk management issues to key
stakeholders
• Provide a mechanism for seeking and acting on feedback to
encourage the involvement of the key stakeholders
• Identify the mitigation actions required for implementation of
the risk management plan and associated costings
Risk register information
• Reference number a unique reference code for the risk
• Description the nature of the risk and how the risk will impact on the
organisation
• Probability this is the likelihood of the risk happening
• Impact a rating defining the effect that the risk will have on
the ability to achieve objectives
• Mitigation a description of the action to be taken to reduce the
probability of the risk occurring, or to reduce its impact
• Contingency where a risk is considered to be severe, consideration should
be given to a contingency plan
• Accountability the person that carries the responsibility for ensuring that
the risk is monitored and effectively managed
• Status a description of the current position for the risk
An example of a risk register
Mitigation actions
• Preventive actions
planned actions to reduce the likelihood that a risk will occur and/or
reduce the seriousness should it occur
• Contingency actions
planned actions to reduce the immediate seriousness of the risk when
it does occur
• Recovery actions
planned actions taken once a risk has occurred to allow you to move
on
Supply chain risk management
considerations
• There are many types of risk in the end-to-end supply chain
• Their characteristics in terms of probability and severity will
vary greatly
• Risk will be sensitive to the context of the company, its
markets and its position in the supply chain
• The permutations and combinations of risk are such that few
generalisations will apply
• Pinpointing all of the areas that a company may face is likely
to be a difficult task, but also a worthwhile one
Consequences of demand risk
• Demand exceeding supply could result in price
increases that will either have to be absorbed by the
organisation or passed on to customers
• The inability to meet demand may be perceived by
customers as a failure of commitment and may affect
both future business and reputation
• Demand that is consistently below projections will be
a major threat, as investments would have been
made on the projected figures throughout the
specific areas of the supply chain
Process risk areas
• Variation in manufacturing output
• Poor equipment utilisation
• Quality issues
• Warehouse operating issues
• Supply chain issues
• Transport issues
Activities in Project Alpha
ACTIVITY PRECEDING ACTIVITIES DURATION IN DAYS
A – 3
B – 3
C – 7
D A 1
E D, J 2
F B 2
G C 1
H E, F, G 1
J B 1
A skeleton network for Project
Alpha
Project Alpha: numbering the
nodes
Project Alpha: earliest start times
Project Alpha: latest finishing
times
‘Crashing’ activities
• Identify activities that may be ‘crashed’
• For each activity, establish cost of crashing
• Estimate activity duration with resources added
• Determine revised completion date and cost
• Recalculate critical path and costs
• Compare various options to determine most effective
solution
Buffers
Buffers are defined quantities of time applied to a project
schedule to protect the promised due date from variation.
• A feeding buffer
Protects non-critical tasks where they feed into critical tasks. This
improves the chance that the critical task can begin on time.
• A capacity buffer
Used in a multi-project environment to protect each project from
variation in resource use on other projects.
• A resource buffer
Protects against the possibility that a key resource will be in short supply
when needed.
Examples of indices
• Commodities indices, or commodity price indices
track the weighted average of selected commodity prices, and are
designed to be representative of a broad commodity asset class or a
subset of commodities (such as energy, metals or agriculture)
• Bottom up
The people that are involved in delivering the tasks, schedules and
work breakdown structure are consulted regarding costs and
timescales, and the data collated is then aggregated to compile the
total costs for a project.
Costing information
• Material costings
Material costs will be based on the specifications created for the project.
There will be estimates of the quantities of materials required together
with their pricing.
• Labour costings
The calculation of labour costs will consist of the multiplication of
estimated labour hours by the rates chargeable for different grades of
labour. In addition, other direct costs associated with the project that
involve people can be added to the budget, such as travel and subsistence
costs.
• Overhead rates
Separate variable and fixed overhead rates may be established and
apportioned to the cost of the activity.
Lifecycle costing
Lifetime costs of managing a
capital asset
Unnecessary cost
• Unnecessary costs of design
• Unnecessary cost of a component
• Unnecessary cost of a material
• Unnecessary cost of poor buildability
• Unnecessary lifecycle cost
Value engineering phases
1 Information phase
The team decides on the objectives and the scope of the study.
2 Speculation phase
This phase is concerned with the generation of creative design ideas, usually through a
‘brainstorming’ process, leading to the formulation of alternative design solutions which fulfil the
value objectives.
3 Evaluation phase
The objective of the phase is to critically appraise the proposals of the previous phase.
4 Development phase
The favoured alternative solutions to emerge from the previous phase are then developed to a level
of detail sufficient to enable cost studies to be undertaken for each option.
5 Presentation phase
The presentation phase is concerned with the production of a report by the VE team, detailing the
conclusions of the VE study and presentation of the recommendations arising out of the review.
6 Implementation of value engineering proposals
the Project Manager should act on the proposals made, indicating where recommendations will be
incorporated into the design, and detailing cost and time implications.
Benefits of buying alliances
• Reduced acquisition costs
• Shared market intelligence and product knowledge
• Shared resources – people, time, management information
• Investing together in supplier development and R&D so enabling
improvements can be shared
• Increasing the suppliers’ interest as a greater value is placed on the
group
• Presenting a united front to suppliers
• Releasing time to concentrate on more strategic procurement
• Inter-member trading can be set up to cover for shortages;
inventory can be managed more effectively; supplier benefits from
greater market penetration
Many to many relationships
Consortium relationships
Difficulties with consortium
purchases
• The central purchasing organisation that creates the consortium-based
contracts through its sourcing and contract negotiations will need to
recover the costs of its personnel and overheads. The difficulty is that the
gains achieved through the consortium are automatically wiped out by the
mark-up added to cover these costs.
• It will rarely be the case that the consortium-based contract will be a
mandatory requirement for all of its members to buy into. As a result,
particularly with organisations that have devolved purchasing, there can
often be a lack of ‘buy-in’ to the contracted frameworks.
• There is often a lack of co-ordination between the members of the
consortium. A larger buyer can tend to take control and be the dominant
member.
Open book costing
Contractors or suppliers can provide data for the
following items:
• Labour costs
• Material costs
• Plant hire
• Overheads
• Subcontract costs
• Profit
A template for open book costing
Measures of progress
• Percentage completion of an activity in terms of cost and
time
• Planned progress against actual progress
• Work in progress
• Any impact on critical path
• Payment progress
• Overall work content
• Outstanding requirements (resources etc) planned or still
required
Time control systems
• Time budget
the overall project duration as fixed by specific constraints in the
contract strategy; the period which, once fixed, becomes a key
parameter for management of the project
• Time plan
a division of total time into interlinked time allowances for readily
identifiable activities with definable start and finish points; the overall
project programme
• Time checking
monitoring actual time spent on each activity against the allowance in
the time plan; reporting any variances as soon as identified for critical
activities
Benefits of reports
• Mutual understanding of project goals
• Awareness of the progress of parallel activities
• More realistic planning
• Understanding interrelationships between different tasks
• Early warning signals of problems and delays
• Reducing delays in communicating any changes deemed
necessary
• Faster management response to defective work
• Higher visibility to top management
• Keeping the client and other interested parties up to date
Types of control processes
• Cybernetic control
automatic detection and correction of deviations from plan
• Go/no-go controls
testing to see whether some condition has been met before allowing
progression to the next step
• Reworked
When a quality issue involves work that requires modifications to
return it to the agreed standard, then it should be classified as rework.
• Compromised
If the project team accepts work that is below the agreed standard,
then this will be classified as compromised.
Stages of a project
Project KPIs
GROUP INDICATORS
Time 1 Time for completion 4 Time predictability – design and
2 Time predictability – design construction
3 Time predictability – 5 Time to rectify defects
construction
Cost 1 Cost for completion 4 Cost predictability – design and
2 Cost predictability – design construction
3 Cost predictability – 5 Cost to rectify defects
construction
Quality 1 Defects 3 Quality defects at End of Defect
2 Quality defects at Available for Liability Period
Use
Client 1 Client Satisfaction with the 2 Client Satisfaction with Service
satisfaction Delivered Product
Health and 1 Reported Accidents 2 Lost Time Due to Accidents
safety
Three dimensions to an audit
• The efficiency of the project
This dimension assesses whether the project meets both the budget
and the schedule.