Lucy Electric

Operation Training

By: Lucy Electric Service Team


RMU
Course Aim:
To deliver a basic operational understanding of and
with Lucy Electric

Course Structure:
- Introduction
- How to operation Aegis plus RMU
Ring Main Unit
Ring Main Unit

Schematic of RMU MEA units is 3 way (LVL)

Note! L: Load break switch


V: Vacuum circuit breaker
Ring Main Unit
Ring Main Unit

Operation Function

1. Load Break Switch (SW)

2. Vacuum Circuit Breaker (CB)


Ring Main Unit

Load Break Switch (SW)


Sequence for operation

1. OFF
2. Selector
3. ON
ON EARTH ON MAIN

OFF SELECTOR ON
Ring Main Unit

Load Break Switch (SW)


Sequence for operation
1. OFF (It’s mean open (circuit) single line between substation
and RMU and then get ready for next sequence)
- OFF MAIN
- OFF EARTH

OFF MAIN: User use handle to operate (Turn handle follow red arrow)
Ring Main Unit

Load Break Switch (SW)


OFF Main complete indicator

This function for open (circuit) single line between substation


and RMU’s busbar and then get ready for next sequence
Ring Main Unit

Load Break Switch (SW)


Sequence for operation
1. OFF (It’s mean open (circuit) single line between substation
and RMU and then get ready for next sequence)
- OFF MAIN
- OFF EARTH

OFF EARTH: User use handle to operate (Turn handle follow red arrow)
Ring Main Unit
Load Break Switch (SW)
OFF EARTH complete indicator

This function for open (circuit) single line between substation and
RMU’s earth and then get ready for next sequence
Ring Main Unit
Load Break Switch (SW)
Sequence for operation
2. Selector (What do you want to do?)
- Main
- Earth

Rotate selector knob (by hand) for selector to


Main or Earth
Ring Main Unit
Load Break Switch (SW)
Sequence for operation
3. ON to Main (It’s for connection from substation to RMU’s busbar (24KV))
- Selector Main
- On Main

ON MAIN: User use handle to operate (Turn handle follow red arrow)
Ring Main Unit
Load Break Switch (SW)
ON to Main complete indicator

This function for connection from


substation to RMU’s busbar (24KV)
Ring Main Unit
Load Break Switch (SW)
Sequence for operation
3. ON to Earth (It’s for connection from substation to earth (Maintenance))
Note! This function must be remove dropout fuse before operate
- Selector Earth
- On Earth
ON EARTH: User use handle to operate (Turn handle follow red arrow)

Maintenance mean user can take out for cable box and test cable cover
Ring Main Unit
Load Break Switch (SW)
ON to EARTH complete indicator
Maintenance user can take out
cable box and test cable cover

Note! This function must


be remove dropout fuse
before operate
Ring Main Unit

Vacuum Circuit Breaker (CB)


Sequence for operation

1. OFF
2. Selector
3. ON

ON EARTH ON MAIN

OFF SELECTOR ON
Ring Main Unit

Vacuum Circuit Breaker (CB)


Sequence for operation
1. OFF (It’s mean open (circuit) single line between RMU’s busbar
and Transformer (Load) and then get ready for next sequence)
- OFF MAIN
- OFF EARTH
OFF MAIN: User use hand to push trip button
Ring Main Unit

Vacuum Circuit Breaker (CB)


OFF Main complete indicator

This function for open (circuit) single line between substation


and RMU’s busbar and then get ready for next sequence
Ring Main Unit

Vacuum Circuit Breaker (CB)


Sequence for operation
1. OFF (It’s mean open (circuit) single line between RMU’s busbar
and Transformer (Load) and then get ready for next sequence)
- OFF MAIN
- OFF EARTH
OFF EARTH: User use hand to push trip button
Ring Main Unit
Vacuum Circuit Breaker (CB)
OFF EARTH complete indicator

This function for open (circuit) single line between RMU’s earth
and Transformer (Load) and then get ready for next sequence
Ring Main Unit
Vacuum Circuit Breaker (CB)
Sequence for operation
2. Selector (What do you want to do?)
- Main
- Earth

Selector MAIN Selector EARTH


Rotate selector (by handle) turn follow red
arrow for selector to Main or Earth
Ring Main Unit

Vacuum Circuit Breaker (CB)


Sequence for operation
3. ON Main (It mean charge spring (ON) for connection between
RMU’s busbar (24KV) and Transformer (Load))
- Selector Main
- ON Main
ON MAIN: User use handle to operate (Turn handle follow red arrow)
Ring Main Unit
Load Break Switch (SW)
ON Main complete indicator

This function for connection from RMU’s


busbar (24KV) to Transformer (Load)
Ring Main Unit
Load Break Switch (SW)
Sequence for operation
3. ON Earth (It’s for connection from Transformer (load) to earth (Maintenance))
Note! This function must be remove dropout fuse before operate
- Selector Earth
- ON Earth
ON EARTH: User use handle to operate (Turn handle follow red arrow)

Maintenance mean user can take out for cable box and test cable cover
Ring Main Unit
Load Break Switch (SW)
ON EARTH complete indicator
Maintenance user can take out
cable box and test cable cover

Note! This function must


be remove dropout fuse
before operate
Thank You