Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
TITRE PRESENTATION 1
TECHNO-ECONOMIC
ASPECTS OF POWER SYSTEMS
Ronnie Belmans
Stijn Cole
Dirk Van Hertem
2
OVERVIEW
• Lesson 1: Liberalization
• Lesson 2: Players, Functions and Tasks
• Lesson 3: Markets
• Lesson 4: Present generation park
• Lesson 5: Future generation park
• Lesson 6: Introduction to power systems
• Lesson 7: Power system analysis and control
• Lesson 8: Power system dynamics and security
• Lesson 9: Future grid technologies: FACTS and HVDC
• Lesson 10: Distributed generation
PRESENTATION TITLE 3
OUTLINE
INTRODUCTION TO POWER SYSTEMS
• Power systems
• Grid structure
• Grid elements
• New investments in the grid
• Tasks of the TSO
• Grid operation issues
THE GRID OF TODAY
• Transmission network
• To transport the electric
power from the point of
generation to the load centers
• All above a certain voltage
• (Subtransmission)
• Distribution network
• To distribute the electric
power among the consumers
• Below a certain voltage
STRUCTURE OF THE POWER GRID
WHAT’S THE DIFFERENCE?
• Transmission system
• Higher voltage (typical at least 110 kV and higher)
• Power injection by generation and import, large
consumers
• Interconnected internationally
• Meshed nature-Redundancy
• (Subtransmission system)
• Between transmission system and distribution system
• Connection of large industrial users and cities
• Open loop/partly meshed
• Distribution system
• 400 V to some ten of kV
• Industry, commercial and residential areas
• Radial
INDUSTRIAL NETWORK (HAASRODE)
P or S = U *
• Electric power P [MW] I
• Alternating current S [MVA]
• Two ways to increase the transported power
• Increase current I
• Larger conductor cross-section
• Increase voltage U
• More insulation
• Two ways to transport electricity
• Alternating current (AC)
• Direct current (DC)
PROBLEM FACED BY ELECTRICITY
PIONEERS
AC OR DC?
• Direct Current DC
• Generator built by W. von Siemens and Z.Gramme
• Low line voltage, and consequently limitation to size of the
system
• Alternating current AC
• Introduced by Nikola Tesla and Westinghouse
• Transformer invented by Tesla allows increasing the line voltage
• Allows transmitting large amounts of electricity over long
distances
TRANSFORMER
AC TRANSMISSION SYSTEM
• Frequency of 50 or 60Hz
• Current changes direction 100 or 120 times a sec
• Active AND reactive power in the same line
• 3 phase system
• Line voltages can be easily and economically
transformed up and down
• AC current does not use the whole conductor
• Skin effect
• AC conductors have larger diameters
than adequate DC
SWITCHYARD
DC TRANSMISSION SYSTEM
• Advantages of AC
• Cheaper transformation between voltages
• Easy to switch off
• Less equipment needed
• Known and reliable technology
• More economical in general
• Rotating field
• Advantages of DC
• Long distance transmission
• Higher investment costs offset by lower losses
• on 1000 km line, 5% for DC opposed to 20% for AC
• Undersea and underground transmission
• No reactive power problem
• Connection of separate power systems
COST OF TRANSMISSION LINE
FUNCTION OF VOLTAGE LEVEL
LINES AND CABLES
• Advantages
• Widely used in transmission over large distances
• Most economical (especially in rural areas)
• Well-known technology
• Environmental aspects
• Visual impact
• Vegetation
• Population
• Town planning
• Cultural heritage
• Natural site and landscape
OVERHEAD AC TRANSMISSION
NEW LINE
Conclusion
• Very difficult to
construct new lines in
industrialized countries
alternatives needed!
OVERHEAD AC TRANSMISSION
ADDING/REPLACING CONDUCTORS
• Increased ampacity
• Without supplementary environmental impact
• Within existing right-of-way
• Equip second circuit
• No new towers needed cost effective
• Heavier conductors
• Tower and foundation modifications may be needed → very
high cost
• Classic
• Paper insulated, oil-filled
• XLPE
• New types
• Higher voltages
• Lower losses
• More expensive
AC CABLES
NEW TYPES
Source: ABB
CABLES
TASKS OF THE TSO
Production
~ ~ ~
Import/
Export
Grids
Consumer
FREQUENCY CONTROL
TASKS OF THE TSO
• Frequency control
• Primary frequency control
• Compensate for short-term unbalances at local level
• Stabilize frequency within acceptable range around set point
• Secondary and tertiary frequency control
• Control the load-generation balance at the programmed
export-import
• Contribute to bringing the frequency back to its set point
• Relieve the primary control reserve after an incident
• Scheduled (set point) frequency (time control)
• Laufenburg control centre in Switzerland
• To account for the Synchronous Time deviations
• 50.01 or 49.99 Hz for the whole day
TASKS OF THE TSO
• UCTE
• Established in 1951 as UCPTE, 9 control zones, currently 27
• 23 countries, 33 TSOs, 620 GW installed capacity, 295 TWh exchanges
• Full synchronous operation of its members in 1958
• absorbed many “smaller” initiatives along the way
• CENTREL, SUDEL, COMELEC
• 450 mln. people, annual electricity consumption 2500 TWh.
• Nordel
• F,SWE,NO,DK (part)
• UKTSOA
• UK
• ATSOI
• Ireland
• UPS/IPS
• Ex Commonwealth of Independent States
SYNCHRONOUS AREAS (1)
WHY CREATE SYNCHRONOUS AREAS
?
• Increase grid reliability and mutual support
• Improved system frequency control to minimize major
disturbances
• Mutual support in case of emergencies
• Sharing reserve capacities
• Facilitate functioning of the electricity market
• non-discriminatory domestic and cross-border access to the grid
• No need for synchronous area as such, also possible with dc
links
Source:
IAEW
SYNCHRONOUS AREAS (3)
OPERATIONAL HANDBOOK (UCTE)
“Stronger interconnections require common and
consistent understanding of grid operation and control
and security in terms of fixed technical standards and
procedures”
Source: DG COMP
FRANCO-BELGIAN BORDER 2001
• Benelux case
• Positive correlation between loop flows and wind in
Germany
• Up to 0.4
• Loop flows almost entirely through BE and NL
PHASE SHIFTER INVESTMENTS IN
THE BENELUX IN ORDER ALLOW
POWER FLOW CONTROL
1. Meeden (Nl)
1 2. Gronau (D)
3. Kinrooi (B)
4. Kinrooi (B)
2
5. Zandvliet (B)
5 6. Monceau (B)
3
6
HOW DANGEROUS CAN UNEXPECTED
FLOWS BE?
North PL CZ
RWE
1815
SEPS MVM
South +3903
SK H +3126
4669
F +3846
RTE - 504
GB
1525 A
- 426 APG
118
752
DC link 575
120 +677
CH
646
E +2614 ETRANS
REE +2560
3022
401
I ELES
SLO
ELES
P 1704 - 5380 481 - 452
HEP
North PL CZ
RWE
1815
505
South +3903
SK H +3126
4669
F +3846
RTE - 504
GB
1525 342
1189
- 426 A APG
118
752
DC link 575
120 +677
CH
646
E +2614 ETRANS 28
REE 846 +2560
3022
2875
401
I ELES
SLO
ELES
P 1704 - 5380 481 - 452
HEP
729
2320
North
PL CZ
D
SEPS MVM
South SK H
RWE PSE
F 4327
1307
RTE
A
APG
CH
ETRANS
E 1492 92
REE
I 147 ELES
SLO
ELES
P 437
HEP
TERNA
REN HR BiH
CUMULATIVE WIND POWER
INSTALLED CAPACITY
2005
WIND POWER INSTALLED IN
EUROPE BY END OF 2005
SHARE OF DAILY WIND POWER IN RESPECTIVE DAILY
PEAK DEMAND IN E.ON-GRID (GERMANY).
CONCLUSIONS