Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
A N G G OTA K E LO M P O K
Add a Footer 2
INTRODUCTION
In the construction of embankment on soft soil
POLYFELT TS has, during the construction stage, the
same function as described in the chapter on
“unpaved road" also, the stability of a so called 3-
layers system embankment / geotextile/subsoil- is
strongly influenced by two geotextile parameters:
b) Tensile strength
Add a Footer 3
It is well known,that consolidation time and
therefore construction time are strongly
influenced by the permeability of the
embankment foundation . When estimating the
consolidation time using conventional
consolidation theories (terzaghi theory) the
foundation is assumed to be ideally permeable .
this goal can be readily attained by using
POLYFELT TS as a separation layer, due to its
high vertical and horizontal permeability.
Add a Footer 4
INTRODUCTION
5
During base failure, the Very seldom occurs in
entire embankment sinks
down into subsoil. practice
consideration for the stability for the stability against sliding in the
base due to spreading pressure.
Add a Footer 6
There are restricted by
base failure • For these reason, tensile
• The factor of safety against toe strength of POLYFELT TS has
failure can be improved theoretically not been considered in the
by reinforcing the embankment
stability analysis described in
base.
section 5 of this chapter
• However, this improvement is
considerably restricted by the above
mentioned base failure, which still
has to be considered.
Add a Footer 7
EMBANKMENT
Add a Footer 8
AREAS OF
APPLICATION
Flood control dams
Railroad embankment
Causeways
Add a Footer 9
GEOTEXTILE FUNCTIONS
Add a Footer 10
10
DESAIGN PARAMETERS
Fill
Material
Fill
Embankment
geometry
Polyfelt TS Placement
rate
Foundation
Add a Footer 11
11
4. Seleksi Kriteria
Mempertimbangkan kepadatan di lokasi konstruksi dan kondisi batas
hidraulik di perhitungkan berdasarkan pemilihan jenis geotextil, seperti
berikut ini:
*)Isi material dari lapisan pertama.
Nonkohesif
Kohesif
4. Selection Criteria
Considering the traffic on the construction site and the
hydraulic boundary conditions on which the calculations are
based, the following geotextile type selection is recommended:
*)fill material of the first layer.
Fill material* Geotextile Selection
Noncohesive
Refer to Chapter on "Unpaved Roads" TS 800
Cohesive
5. Stability Analysis
• In the following analysis the stability of an embankment on a soft,
homogeneous soil layer with the thickness D is checked. The soil below the
soft layer is assumed to be stiff. Figure 1 demonstrates the embankment
geometry on which stability calculations are based.
• Soil parameters ɸ and Cu have to be reduced by an adequate factor of
safety before entering the calculations. For multi-layered soils, an average
value can be considered (2).
Figure 1: Embankment Geometry
H = height of embankment (m)
B = crest width (m)
Figure 2 shows the considered types of base failure (2) (3) from which
type “a” was chosen based on lowest stability. Diagram E-I provides
the required value for Kc as a function of the D/B ratio.
Figure 2: Types of Base Failure
For D/B ratio ≥ 9,663, Kc is constant with Kc=0,189;
this value correlates with the solution of Prandtl
with Kc= 1/((2+π)) = 0,194, which is applicable for
D/B ≥0,71.
Diagram E-I: Determination of Kc Considering Base Failure of
an Embankment.
Refer to Chapter on "Unpaved Roads" TS 800:
Depending on load and subsoil conditions, there are three possible variants of construction.
Variant 1 POLYFELT TS alone as a seperation and filter layer.
Variant 2 POLYFELT TS with a protective sand layer.
Variant 3 POLYFELT TS with a compacted sandy gravel layer.
Applications for the individual variants are given in Table R-1.
Noncohesive
2 1/2
granular soils
Cu required = kc . ɣ. h ≤ ( cu actual / Fs )
Dimana:
1
M = 2 . 𝜋 . (2 . m + I)
m = running variable
Tv = Cv . t/𝑙 2 (time factor)
Cv = consolidation coefficient for vertical flow (𝑚2 /𝑠)
T = time (sec)
I = length of greatest seepage path (m) (D unilateral, D / 2 in bilateral drainage
Diagram L-X, Consolidation of subsoil with POLYFELT TS
Figure 9: Embankment Height vs Time withhh Linear Load Increase
SETTLEMENT
For an estimate of the final settlement in the center of the embankment,
the assumption is made that soil stiffness underneath the soft layer is
sefficiently great to neglect settlement of these layers. Furthermore, the
stiffness modulus e is assumed to be constant throught the entire layer
thickness, d if several layers with different e values are present,
calculations can be approximated with an average value:
E = 𝜀 (Ei . di) / 𝜀 𝑑𝑖
The depth of influence of the applied load is limited to 2 . B. therefore, if
layer thickness D > 2. B, the ratio D / B should be stated as 2,0 in
diagram D-XI
The final settlement in the center of embankment is
obtained according to steinbtenner:
𝑠∞ = D . f . 𝛾 . h / E
Where:
D = thickness of soft layer (≤ 2 . B ) m
f = influence factor per diagram E-XI
𝛾 . h = applied load (Kn/𝑚2 )
E = stiffness modulus (Kn/𝑚2 )
𝛽 = 25° ; ∅ = 30°
Kc = 0,110
• Base failure is governing ( max Kc! )
Kc = 0,189
Curead = f8 x Kc x 𝛾 x h
= 1,1 x 0,189 x 19 x 6,0
= 23,7 Kn/m2
Therefore the base failure is the governing factor for each fill stage
• Required degree of consolidation Ui :
𝐶𝑢𝑖+𝑖−𝐶𝑢𝑖
- 𝑈𝑖 =
∆𝑐,𝑚𝑎𝑥,𝑖−𝐶𝑢𝑖+𝐶𝑢𝑎𝑐𝑡𝑢𝑎𝑙
- Cui = f8 x Kci x 𝛾 x hi (f8 = 1,1 )
𝐵𝑖
-∆𝑐𝑢𝑚𝑎𝑥𝑖 = 𝛾 𝑥 ℎ𝑖 𝑥 𝑥 tan 𝜑 ′
𝐵′
1
-𝐵𝑖 = 𝑖 (𝐵𝑖 + 𝐵′ )
2
49
Construction schedule :
- Fill to H1 = 2,5 m
- After 9 months, fill to H2 = 4,5 m
- After 8 more months, fill to H3 = 6 m
52
SPESIFICATION NOTES
In order to establish objective criteria, the relevant geotextile parameters have
to be specified according to standard test methods, as described in the
chapter on “Geotextile Testing”. However, in order to meet the special
geotextile requirements presented in this application chapter, it is necessary to
specify all relevant parameters as mentioned on the right. The values of the
selected polyfelt-grade can be drawn from the data sheet below
53