KHALDEH – DBAYEH

AND
DBAYEH - OKAIBE
EXPRESSWAYS
March 6 2018
By
Elie Helou – Council for Development and
Reconstruction
KHALDEH DBAYEH AND DBAYEH OKAIBE EXPRESSWAYS
Project Objective:

Connecting the
Northern &
Southern sections Coastal
Highway
of the M50 & to link
with the Pan Arab Known as
Highway
M50

By providing a
missing bypass to
the city of Beirut
& Pan Arab
By providing added Highway
capacity to bypass
the city Jounieh.
CURRENT TRAFFIC CONDITIONS
NORTHERN ENTRANCE TABARJA
NORTHERN
NORTHERN ENTRANCE
ENTRANCE

TABARJA - BEIRUT BOTH


BEIRUT BCD- DIRECTIONS
BCD TABARJA SOUTHERN
BEIRUT AM PM NIGHT ENTRANCE
ADT BOTH DIRECTIONS 290000 VPH
DISTANCE 24 KM
TRAVEL 70 MIN 90 MIN 18 MIN
TIME
SPEED 20 KM/HR 16 KM/HR 80 KM/HR
CURRENT TRAFFIC CONDITIONS
SOUTHERN ENTRANCE
TABARJA

NORTHERN
ENTRANCE

KHALDE - BEIRUT BOTH


BEIRUT BCD- DIRECTIONS
BCD KHALDE
AM PM NIGHT SOUTHERN
KHALDE
ADT BOTH DIRECTIONS 130000 VPH ENTRANCE
SOUTHERN DISTANCE 16 KM
ENTRANCE TRAVEL 40 MIN 35 MIN 12 MIN
TIME
SPEED 24 KM/HR 28 KM/HR 80 KM/HR
PEAK HOUR OR PEAK DAY
Very high level of congestion is recorded on major corridors
thought-out most hours of the day
DOWN THE ROAD
GBA MAIN ARTERIALS IN 2035
LOS “E” 1954
LOS “F” 2582

KHALDEH-DBAYEH
EXPRESSWAY
KHALDEH DBAYEH AND DBAYEH OKAIBE EXPRESSWAYS
Alignment & interchanges
KHALDEH-DBAYEH DBAYEH-OQAIBE
EXPRESSWAY EXPRESSWAY
20 KM 18 KM

‫محول البوار‬

‫محول صفرا‬

‫محول‬
)‫الميكانيك (الحدث‬
‫محول ضبية‬ ‫محول عوكر‬
‫محول‬
‫الكفاءات – الحدث‬
‫محول غزير‬
‫محول ذوق مصبح‬

‫محول ساحل علما‬

- Total length 38 km
- 20 interchanges
‫‪2027 ADT‬‬
‫‪50,000 VPH‬‬
‫محول خلدة‬

‫محول‬
‫الميكانيك (الحدث)‬
‫‪2027 ADT‬‬
‫‪50,000 VPH‬‬
‫‪2027 ADT‬‬
‫‪100,000 VPH‬‬
KHALDEH-DBAYEH EXPRESSWAY

• Elevated viaduct 20 km
• Dual 3-4 lanes in each direction
• Construction cost 775 MUSD
• Expropriation cost 850 MUSD
• Urban area
• Flat terrain
KHALDEH-DBAYEH EXPRESSWAY
Box Girder viaduct
DBAYEH OKAIBE EXPRESSWAYS
- Tunnels twin tubes x 3 lanes each, 8 km long
- Bridges twin structures x 3 lanes each, 5 km long
- At grade 5 km long
- Suburban, Mountainous terrain
- Construction Cost 825 MUSD
- Expropriation Cost 415 MUSD

DBAYEH-OQAIBE
EXPRESSWAY
18 KM
DBAYE – OKAIBE BRIDGES
Arch Bridge: Nahr El Kalb Bridge
Bridge structural Total Number of Total Length
type bridges (m)

Arch bridge 2 (Nahr-El-Kalb) 1000


Dbaye – Okaibe Bridges
Balanced Cantilever: 8

Total Number of
Bridge structural type Total Length (m)
bridges
Balanced Cantilever 8 2000
Dbaye – Okaibe Bridges
Precast I-Beams: 16 bridges

Total Number of
Bridge structural type Total Length (m)
bridges
Precast I-Girders 16 2324
Dbaye – Okaibe Bridges
Twin Tunnels

Tunnel Section Length = 8280 m


Longest Tunnel (Harissa Area) = 2800 m
KHALDEH DBAYEH AND DBAYEH OKAIBE EXPRESSWAYS

Possible sections based on connectivity to road network


KHALDEH DBAYEH AND DBAYEH OKAIBE EXPRESSWAYS
Current Status
Completed
• Khalde - Dbayeh and Dbayeh - Okaibe expressways preliminary engineering
designs
• Khaldeh – Dbayeh initial ESIA prepared in 2012
• Dbayeh - Okaibe expressway expropriation plan approved by way of decree
No. 2169 on 9/1/2018.

On-going
• Khaldeh – Dbayeh expressway decree at pre-final preparation stage
• Khalde - Dbayeh and Dbayeh - Okaibe expressways financial study is at 60 %
progress
• Khalde - Okaibe ESIA to start shortly
Next steps

To start the due diligence process for developing the expressway on a PPP basis
and decide on the following pressing issues:

1. Whether to execute the expressway as one project or split it into different


standalone sections
2. How to cover the project expropriation costs
KHALDEH DBAYEH AND DBAYEH OKAIBE EXPRESSWAYS

Thank you