DBAYEH - OKAIBE
EXPRESSWAYS
March 6 2018
By
Elie Helou – Council for Development and
Reconstruction
KHALDEH DBAYEH AND DBAYEH OKAIBE EXPRESSWAYS
Project Objective:
Connecting the
Northern &
Southern sections Coastal
Highway
of the M50 & to link
with the Pan Arab Known as
Highway
M50
By providing a
missing bypass to
the city of Beirut
& Pan Arab
By providing added Highway
capacity to bypass
the city Jounieh.
CURRENT TRAFFIC CONDITIONS
NORTHERN ENTRANCE TABARJA
NORTHERN
NORTHERN ENTRANCE
ENTRANCE
NORTHERN
ENTRANCE
KHALDEH-DBAYEH
EXPRESSWAY
KHALDEH DBAYEH AND DBAYEH OKAIBE EXPRESSWAYS
Alignment & interchanges
KHALDEH-DBAYEH DBAYEH-OQAIBE
EXPRESSWAY EXPRESSWAY
20 KM 18 KM
محول البوار
محول صفرا
محول
)الميكانيك (الحدث
محول ضبية محول عوكر
محول
الكفاءات – الحدث
محول غزير
محول ذوق مصبح
- Total length 38 km
- 20 interchanges
2027 ADT
50,000 VPH
محول خلدة
محول
الميكانيك (الحدث)
2027 ADT
50,000 VPH
2027 ADT
100,000 VPH
KHALDEH-DBAYEH EXPRESSWAY
• Elevated viaduct 20 km
• Dual 3-4 lanes in each direction
• Construction cost 775 MUSD
• Expropriation cost 850 MUSD
• Urban area
• Flat terrain
KHALDEH-DBAYEH EXPRESSWAY
Box Girder viaduct
DBAYEH OKAIBE EXPRESSWAYS
- Tunnels twin tubes x 3 lanes each, 8 km long
- Bridges twin structures x 3 lanes each, 5 km long
- At grade 5 km long
- Suburban, Mountainous terrain
- Construction Cost 825 MUSD
- Expropriation Cost 415 MUSD
DBAYEH-OQAIBE
EXPRESSWAY
18 KM
DBAYE – OKAIBE BRIDGES
Arch Bridge: Nahr El Kalb Bridge
Bridge structural Total Number of Total Length
type bridges (m)
Total Number of
Bridge structural type Total Length (m)
bridges
Balanced Cantilever 8 2000
Dbaye – Okaibe Bridges
Precast I-Beams: 16 bridges
Total Number of
Bridge structural type Total Length (m)
bridges
Precast I-Girders 16 2324
Dbaye – Okaibe Bridges
Twin Tunnels
On-going
• Khaldeh – Dbayeh expressway decree at pre-final preparation stage
• Khalde - Dbayeh and Dbayeh - Okaibe expressways financial study is at 60 %
progress
• Khalde - Okaibe ESIA to start shortly
Next steps
To start the due diligence process for developing the expressway on a PPP basis
and decide on the following pressing issues: