Syed Ahmed
November 16, 2017 Executive Director, DTCA
Technical Assistance for DTCA Capacity Building
Contents
Background
Components of RSTP
Implementation Status of RSTP Projects
2
Technical Assistance for DTCA Capacity Building
Background
3
Technical Assistance for DTCA Capacity Building
Background of DTCA
4
Technical Assistance for DTCA Capacity Building
Background of DTCA
Vision & Mission
Vision
To provide a planned modernized transportation system for
greater Dhaka area.
Mission
Ensure safe, reliable, faster and affordable Public Transport by
introducing integrated transport planning.
5
Technical Assistance for DTCA Capacity Building
6
Technical Assistance for DTCA Capacity Building
7
Technical Assistance for DTCA Capacity Building
Components of RSTP
8
Technical Assistance for DTCA Capacity Building
9
Technical Assistance for DTCA Capacity Building
10
Technical Assistance for DTCA Capacity Building
Kamalapur
Railway Station
11
Technical Assistance for DTCA Capacity Building
Jhilmil Narayanganj
12
Technical Assistance for DTCA Capacity Building
Abdullahpur Fatullah
Gubtoli Chashara
Rayerbazar Signboard
Sadarghat Demra
13
Technical Assistance for DTCA Capacity Building
Dhaka Bypass
Bhulta
Kanchpur
Narayanganj
Jhilmil
Western Bypass
14
Technical Assistance for DTCA Capacity Building
Kalakandi
Madanpur
Danga
Bypail
Gazipur
15
Technical Assistance for DTCA Capacity Building
Radial Roads
Proposed 8 radial roads:
1. Dhaka-Joydebpur-Mymensingh
2. Dhaka-Tongi-Ghorashal
3. Dhaka-Purbachal-Bhulta
4. Dhaka-Kachpur-Meghna
Bridge
5. Dhaka-Signboard-Narayanganj
6. Dhaka-Jhilmil-Ekuria
7. Dhaka-Amin Bazar-Savar
8. Dhaka-Ashulia-DEPZ
16
Technical Assistance for DTCA Capacity Building
Expressways
• Dhaka Elevated expressway
( Aiport – Mohakhali – Kamlapur – Saidabad – Jatrabari - Kutubkhali)
Implementing Agency: BBA
Transportation Hubs
• 21 transportation Hubs
• Primary interchanges and hubs:
• Dhaka International Airport
• Kamalapur Station
• Mohakhali Bus Terminal
• Jatrabari Bus Terminal
• Gabtoli Bus Terminal
• Gabtoli Circular Waterway
Station
• Shadarghat Terminal
18
Technical Assistance for DTCA Capacity Building
Gagipur
(Joydebpu
r)
Bhulta
Jhilmil
Existing Inter-district
19
Circular Waterway around Dhaka
Tongi Khal
• Integration of Landing Stations with Mass
Transit network (BRT/MRT) and with Turag
Public Transport System.
Balu
Buriganga Shitalakhya
Dhaleswari
20
(Paragraph22
7)
Technical Assistance for DTCA Capacity Building
21
Technical Assistance for DTCA Capacity Building
Implementation Status of
RSTP Projects
22
Technical Assistance for DTCA Capacity Building
MRT Line 6
Length : 20.1 kilometer (Elevated)
Number of Stations : 16 nos.
Passenger Capacity : 60,000/ hour (both directions)
Speed : 23~35 km/hour
100 km/hour (Maximum)
Travel Time : 37 minutes
Train Interval : 3. 5 minutes
Project Period : July 2012 – June, 2024
Estimated Cost in BDT : Total 21,985.07 (Crore)
GOB 5,390.48 (Crore)
JICA 16,594.59 (Crore)
23
MRTBuilding
Technical Assistance for DTCA Capacity Line - 6
Progress of MRT Line - 6
• Entire MRT Line-6 will be constructed under 8 Packages
• Agreement has been signed of Package No. 1, 2, 3, 4 and 8
• Tender Evaluation of Package No. 7 is going on
• Tender invited for Package No. 5 and 6 and last date: 15 November 2017
Implementation Challenges
• Construction of viaduct under Package No. 3 and 4 is going on along the
median, which is major cause of traffic congestion. Mitigation of traffic
congestion through diversion.
• Utility relocation
• Security of foreign Experts and Consultants
24
Technical Assistance for DTCA Capacity Building
MRT Line 5
Total Length : 19.6 km
Route Alignment : Baliarpur-Modumoti-Amin bazar-Gabtoli-Technical-Mirpur 1, Mirpur 10,
Kochukheth-Banani-Gulshan 2-Badda-Vatara
Elevated Section : 6.0 km (Hemayetpur to Aminbazar and Notunbazar to Vatara)
Underground Sec : 13.6 km (Aminbazar to Notunbazar)
Number of Stations : 14 Nos.
25
MRTBuilding
Technical Assistance for DTCA Capacity Line - 5
Progress of MRT Line - 5
• Pre-feasibility of MRT Line-5 has been completed
• Feasibility Study will be completed within March 2018
• MRT Line-5 Project could be implemented through the Co-financing of ADB and JICA
• EOI Evaluation is going on to select Detail Design Consultant.
Implementation Challenges
• Acquisition of 80 acre of land area for the depot construction near Hemayetpur
• NOC from the Bangladesh Armey to fixup 1.3 km underground alignment through the
Dhaka Cantonment
• Uninterrupted Power supply for the operation
• MRT Act 2015 need to be congenial with the construction of underground metro rail
systems
26
Technical Assistance for DTCA Capacity Building
MRT Line 1
Total Length : 26.6 km
Route Alignment : Airport-Khilkhet-Kuril-Badda-Rampura-
Malibagh-Rajarbagh-Kamalapur and from
Kuril to Kanchan bridge.
Elevated Section : 10.2 km (Kuril to Kanchan bridge)
Underground Section : 16.4 km (Airport to Kamalapur)
Number of Stations : 17 Nos.
27
MRTBuilding
Technical Assistance for DTCA Capacity Line - 1
Progress of MRT Line - 1
• Pre-feasibility of MRT Line-5 has been completed
• Feasibility Study will be completed within March 2018
• Loan agreement was signed with JICA for the Detail Design of MRT Line - 1
• EOI Evaluation is going on to select Detail Design Consultant.
Implementation Challenges
• Acquisition of 100 acre of land area for the depot construction near Pitolganj, Rupganj
• NOC from the DNCC for the sub-soil investigation along the alignment
• Uninterrupted Power supply for the operation
• MRT Act 2015 need to be congenial with the construction of underground metro rail
systems
28
Technical Assistance for DTCA Capacity Building
BRT Line 3
BRT line 3 has two section:
29
Technical Assistance for DTCA Capacity Building
30
Technical Assistance for DTCA Capacity Building
31
Technical Assistance for DTCA Capacity Building
32
Technical Assistance for DTCA Capacity Building
33
Technical Assistance for DTCA Capacity Building
34
BRTBuilding
Technical Assistance for DTCA Capacity Line - 3
Progress of MRT Line - 1
• Construction of BRT Line – 3 (Northern part) is going on and the implementing agency
is RHD, BBA and LGED
• Detail Design of BRT Line – 3 (southern part) has been completed
Implementation Challenges
• Financing by the World Bank for the BRT Line – 3 (Southern Part), Phase – 1 (Airport to
Mohakhali)
35
Technical Assistance for DTCA Capacity Building
36
Technical Assistance for DTCA Capacity Building
Implementation Challenges
• Development of Business Model and formulation of Bus System Manager
• Requirement of Total 646 million UDS and for the Phase – 1 it requires 446 million USD.
37
Technical Assistance for DTCA Capacity Building
38
Technical Assistance for DTCA Capacity Building
Implementation Challenges
• Removal of illegal vendors and hockers from the Furbaria Intersection to
implement Dhaka Integrated Traffic Management Project.
39
Technical Assistance for DTCA Capacity Building
40
Technical Assistance for DTCA Capacity Building
Total Budget Required to implement RSTP
Implementation Period
Project Responsible
Cost Phase 1 Phase 2 Phase 3 Phase 4
Component Agency
2016-2020 2021-2025 2026-2030 2031-35
Expressway BBA, RHD 3,973 1,144 787 1,940 102
Primary Roads Inner Ring Road BWDB
1,449 212 1,237 0 0
RHD
Middle Ring
Road RHD 520 0 71 230 219
Others
RHD 1,406 1,708 79 239 11