MUMBAI METRO LINE 3

CONTRACT - UGC 05

DESIGN AND CONSTRUCTION OF UNDERGROUND


STATIONS AT DHARAVI, BKC, VIDYANAGRI &
SANTACRUZ WITH ASSOCIATED TUNNELS

DHARAVI CONSTRUCTION REVIEW – 26.06.18


PHYSICAL PROGRESS AT A GLANCE
Sr. No Work Description UOM Scope Finished Balance %Comp
1 General
i Tree Cutting Nos 5 5 0 100%
ii Tree Transplantation Nos 39 26 13 67%
2 Utility
i 2mx2m Storm Water Drain & Culvert Rmt 155 155 0 100%
ii Laying 450mm water line (Building Side) Rmt 332 332 0 100%
iii 1200 mm S.W.D at Building Side Rmt 300 300 0 100%
iv 900 mm dia Water Line (Nallah Side) Rmt 300 198 102 66%
3 Secant Piling & Caping Beam
i Secent Piling Station Box Nos 1079 837 242 78%
ii Secent Piling Entry Exit Nos 125 125 0%
iii Caping Beam Rmt 740 377 363 51%
4 Road Work - Nallah side
i Gabion wall Rmt 280 205 75 73%
ii GSB Rmt 300 150 150 50%
iii WMM Rmt 300 150 150 50%
iv DBM Rmt 300 0 300 0%
5 King post - Decking Nos 232 107 125 46%
i Phase-1 Diversion Nos 88 57 31 65%
ii Phase-2 Diversion Nos 144 52 92

CONTRACT: UGC 05 26.06.18


TRAFFICE DIVERSION ON WEST (GABION WALL SIDE)
Road Diversion
18 Jul18

CONTRACT: UGC 05 26.06.18


STATUS OF PILING AND PROGRAM

Grid 01-09 - 96 Nos Grid 09-15 -18 Nos


By 30th Jun 18 Grid 17-23 -56 Nos
By 23th Jul 18 By 10th Jul 18

End Wall two phases-31Nos


By 20th Jul 18

Status of Secant Pile : Completed 837 Nos. Balance : 242 Nos.

CONTRACT: UGC 05 26.06.18


INTERMIDIATE TRAFFICE DIVERSION PHASES FOR NORTH WALL PILING
Road Construction End Wall two phases-31Nos
By 23th Jul 18 By 31th Jul 18

1st Phase Decking 100 mtr


By 16th Aug 18

Ancillary Building Excavation


By 1st Jul 2018 8th Sep 18

CONTRACT: UGC 05 26.06.18


TRAFFICE DIVERSION ON WEST (GABION WALL SIDE)
South End Piling
By 18th Aug 18

Excavation Start 16 Aug 18

2nd Phase Decking


By 30th Sep 18

Traffic Diversion
By 15th Oct 18

CONTRACT: UGC 05 26.06.18


DHARAVI STATION

SECANT PILING-EAST WALL GABION CONSTRUCTION

CONTRACT: UGC 05 26.06.18


DHARAVI STATION

ROAD CONSTRUCTION – N. JUCTION ROAD CONSTRUCTION-Gr 11 to 17

CONTRACT: UGC 05 26.06.18


THANK YOU

CONTRACT: UGC 05 26.06.18