PROCEDURE FOR WORKING OF TRACK MACHINES
RCSM BATCH NO. 1819090
COURSE CO-ORDINATOR
Shri. X. CHARLES Instructor / OPTG
GUIDE:
Shri. MANJUNATHAN Instructor / OPTG
Presented By:
• 1. N.PRAMOD SS/UAM/SA
• 2. K.B. RADHAKRISHNAN SS/IPL/TVC
• 3. GEORGE JOHN SS/AMPA/TVC
• 4. SADANAND MISRA SS/SGE/SA
• 5. U. GOVINDAN SM/KON/MDU
• 6. SHIV SHAMBHU KUMAR SM/TNPM/MAS
• 7. HEMANT KUMAR SM/MYY/TVC
• 8. BINOD KUMAR SM/PCKM/MAS
• 9. PREM PUJA SINGH SM/AB/MAS
INTRODUCTION
• Track Machines were introduced on Indian Railways during
early sixties. The use of the machines both for maintenance
as well as track laying increased with the introduction of heavy
track structures. For working of these machines instructions
had been issued by the railway board and Zonal Railways from
time to time.
B. Block Shunting
back/block authority
forward +T/465-E
C. During line T/465-E
block
• 11) After receiving the machines SM shall clear the section for
normal operation duly exchanging message supported by PN
with other end SM.
CONCLUSION
• It is a single authority to proceed for any number
of machines to enter the block section under line
block in group/convoy. It will reduce the time of
preparing individual authority, and hence
maximum utilization of block time. In this
authority no specific speed restriction to be
adhered in the block section for machine
movement which fetches the maximum block
time thus increase the productivity.