Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1.2
1.1
1.0
0.9
0.8
Lower Control Limit
Earned Value Management
Planned Value
Earned Value
Actual Cost
Earned Value Management: Basic Elements
SV = EV - PV = 32 - 48 = - 16 {unfavorable}
SV% = SV / PV = -16 / 48 = -33% {unfavorable}
Some Derived Metrics; Variances
CV: Cost Variance (EV-AC)
A comparison of the budgeted cost of work performed with
actual cost. It shows whether a project is under or over
budget.
CV = EV - AC = 32 - 40 = -8 {unfavorable}
CV% = CV / EV = - 8 / 32 = -25% {unfavorable}
Some Derived Metrics; Variances
This shows the team whether the project will finish under
or over budget, by subtracting the EAC from the BAC.
Find, SV, % SV, CV, % CV, SPI, CPI, CSI, VAC, EACt, EAC, ETC and
also elaborate what these values mean to project manager?
Variances
Schedule Variance = EV-PV
49,000
- 55,000
SV = - 6,000
SPI: EV/PV
49,000/55,000 = 0.891
CPI: EV/AC
49,000/56000 = 0.875
EACt: (BAC/SPI)/(BAC/months)
(230,000/ .891)/(230,000/12)= 13.47 months
3. If all the work completed in Month 4 fails quality testing, and has to be
reworked in Month 5, meaning that none of Month 5’s tasks can be completed:
3a. What is the EV at 3b. What is the AC at 3c. What is the CPI at
the end of month 5 the end of month 5 the end of month 5
Assignment # 2 – C & D (group assignment)
2 D. Based on this Estimate, can you prepare WBS? Prepare one for the same 5
Marla house
2 E. Prepare AOA & PDM, calculate Total Duration of the project, identify all
paths and then identify Critical Path. Calculate ES, LS, EF, LF & floats only for
PDM