Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
COMMISIONING OF
BOILER
WHAT IS THE DIFFERENCE OF
COMMISIONING & OPERATION
Commissioning-construction
&assembling stage
Operation-execution
Construction of Boiler
Four columns will be erected
Drum lifting (Critical activity)
Economiser coils-header
Reheater,superheater-hanger supports
Water walls
Parallel activities- RAPH, Milling system,
Fans
Agencies of power plant
commissioning
Customer - NLC
Supplier- BHEL
Consultant- Tata consultants
Duration to construct a
power plant
hammering
hanger supports
fails
Remedial action
Close the incoming steam valve
immediately.
Open the drains fully
Wait till hammering stops
Follow the procedure from beginning
2. Oil line flushing
What is the need for oil line flushing ?
Where is oil lines located in boilers ?
How the line is flushed ?
How many times flushing to be done ?
3. One series of ID/FD fans
made ready
ID fan commissioning procedure
FAN
electrical mechanical
instruments
Electrical faults
1. Locked rotor protection(LRP)-mechanical obstruction<2 secs
2. Differential protection- check for megar valve, 1 kv=1 mega
ohm, then 6.6kv=7 mega ohm. Check in each phase you
should get 7 mega ohm. If you get < 7 mega ohm either
moisture or oil ingress. If mega ohm is 0 then puncture in
insulation
3. Short circuit protection
4. Negative sequence protection
5. Earth fault protection
6. Thermal overload protection-heating characteristics, fan
cooling. greasing for lubrication of windings
Mechanical faults
1. Local latch
2. Fan bearing tempt. Contact
3. Oil pr. Protection contact etc
Instrument fault
1. PCD min. contact
2. Tempt. Contact
3. Pr. Switches contact
4. If false pick , then bypass or if it is
real then attend to the fault
FD fan
FD fan
commissioning-same
procedure
RAPH
SALIENT POINTS
Motor alone trial run for 8/12/24 hrs
Erection of hot/cold end baskets
Lignite firing
oil firing
Oil flushing
Flush oil lines with steam initially alone during
commissioning by keeping vents and drains
opened
If leak observed attend to it
Charge oil trace heating line with steam
Charge with oil gradually by starting oil
pumps from FOPH
Put oil under recirculation upto QCV near
burner station
Oil firing system
Erection of oil burners
Commissioning purge, atomizing, oil lines
Commissioning of limit switches in oil, steam
lines-check for its limit contact i.e open/close
contact
Commissioning of IR/UV scanners, with
cooling lines from SAF
Check for any chokes or foreign particles in
tip of oil gun by air blowing
Milling system
Motor (6.6 kv) alone to trial run
Mill wear plate checking for uniform alignment
Without fixing beater wheel , rotate manually and
check mechanical hardness
Commission lube oil system, with flow meters
Commission mill bearing tempt. Switches
Commission motor bearing tempt. switches
Charge ACW line
Inspect RSD – refractory healthiness, uniformity
After checking all fittings fix the wheel then close
the mill
Commissioning of SH/RH/ECO
Erection as per drawing
Check for any misalignment like sagging of headers
etc.
Check the critical hangers for their “cold” condition, if
not inspect the hanger
Provision of metal tempt. Thermocouples for
SH,RH,ECO,Drum both left/right sides
Fixing pr.guages,tempt. Gauges at local also contacts
for UCB indication
Drum to be inspected for cyclone separator fixing,
level switches,transmitters,hydrastep,local guage
glass
Chemical cleaning of boiler
Alkali boil out-it is cleaning of internals
for efficient heat transfer- removes
lubricants,oil,rust
Acid cleaning-scales, deposits removal
thermal flow test
Passivation-to avoid internal corrosion,
a anticorrosive coating is formed called
magnetite using hydrazine
Testing of boiler
Hydro test-1.5 times of working
pressure
Steam blow out-to check purity of
steam, removal of welding slag
Protection&interlock checking
Before boiler is lighted, P&I to be done
Start RAPH , follow defined procedure
Put ID/FD in “TEST” position with electrical help from annex, allow oil
pumps to run
Conduct pr, tempt. Switch contact from the field for both fans
Go to RH2 i/l to check furnace vacuum switches. LHS 2+, 1 – RHS
2-, 1+
+250mmwcl ,-300mmwcl for 2 sec or more
If pr is low then ID trips, if high then FD trips
Check mill protections, mill bearing tempt. Contact by putting mills in
“test” position
Check RAPH protections , GB/SB bearing tempt contact by c&I
Fill the boiler contour, check high level and low level
+330/-340 for 5 sec, boiler will trip( can be done while filling)
Inspections/checking
Commissioning of sampling points
Inspection of expansion joints, critical
hangers, peep hole doors, manhole
doors
Safety valve floating
Checking chemical valves
Synchronization, Load
raising,optimisation
Chemical valves
conden Feed drum Sat.steam Super
sate water heated
steam
sio2 .02 .02 .3 .02 .02