PUTATAN WATER

TREATMENT PLANT 2
Interconnection of the
PROCEDURE: New Permeate Pipe to
the Existing Pipe
KEYPLAN
SITE PREPARATION

a) Coordination with Maynilad prior to the date of execution.


b) Site Clearing
c) Surveyor will check the alignment of the pipes prior to start of any activity.
d) Exercise all valves connected to Ø1600mm pipe.
e) Mobilization for the materials, tools & equipment and manpower required for
the activity.
f) Prepare temporary sand bag channel from the existing tapping point going to
existing open pit below Sludge Building
REMOVAL OF Ø1600mm BLIND FLANGE

1. Close all valves connected to the existing Ø1600mm pipe and the existing
concrete reservoir.
2. Remove Ø1600mm blind flange by loosening bolts and nuts
DEWATERING WORKS

After removing the blind flange, the remaining water that is trapped inside the
existing Ø1600mm pipe shall be continuously drained.

A temporary channel made up of sand bags is constructed to control the flowing


water from the termination point or blind flange going to the existing open pit
below the proposed Sludge Silo location.
DEWATERING WORKS
INSTALLATION OF REDUCER & FLEXIBLE CONNECTOR

Using crane, to lift the 1600mm x 1000mm reducer and flexible connector to its
final location and held in place during installation.

Install the Ø1600 x 1000 reducer and Ø1000 flexible connector assembly by fixing
bolts, nuts and washers.

After the successful installation, open all the valves that were previously closed.
PIPE LAYOUT

NEW DN1000
PERMEATE PIPE

EXISTING DN1600 PIPE


W/ FLANGE AND
BULKHEAD/BLINDFLANGE

NOTE:
The interconnection of pipes
shall be done after successful
Hydro-testing, Flushing &
1000x700mm
FLEXIBLE CONNECTOR Disinfection of the permeate
1600x1000mm line.
REDUCER
TIME INTERRUPTION

The table below shows the sequence of operation and its estimated duration to be
undertaken during the 8-hour shutdown.

No Duration
OPERATION Period, Hrs.
. (hours)
Removal of 1600 mm and Blind Flange
1 including 3
draining of Water inside pipe
2 Installation of reducer and flexible connector 1
3 Tightening of DN1600 Flange 3
4 Tightening of DN1000 Flange 1
TOTAL 8 hours 1 2 3 4 5 6 7 8