Sei sulla pagina 1di 35

Prince Sattam Bin Abdul Aziz University

College of Engineering
Project Management

Case Study :
Project Selection for Spent Nuclear Fuel Cleanup
Presented By :
Mahmood Kodimy
Fawzy Radwan
Monther al Qassab
Wassem Ramadan
Nasser Al-Dawood
Instructor: Dr. Yehya Rashid
1
Agenda:
 Brief summary of the case.

 Answering the following Questions :

o Why it takes 5 moths to explain the problem to the stakeholders.?

o Why do you think the stakeholders no longer trusted the


authorities?.
o What might have been the problem with options 1,2 and 4 ?
o How is option 3 a solution ?

2
Hanford Nuclear Fuel Site

 Reactors
 Cooling towers
 Nuclear fuel
3
Hanford Nuclear Fuel Site

 Located in Washington DC ,USA


 Near to Columbia Rever

4
Hanford Nuclear Fuel Site

In 1994
Westinghouse Hanford Co., on contract to the
Department of Energy’s Hanford Nuclear Fuel Site
, reorganized for “projectization” to help Hanford with facility
shutdown, and site cleanup.

 Removing a facility from service

 The major project in this overall task was


the site cleanup

5
Hanford Nuclear Fuel Site
Challenges
spent nuclear fuel (SNF) : Fuel that has been withdrawn
from a nuclear reactor and it has been irradiated in a nuclear
reactor and no longer useful ((Consumed))

6
Hanford Nuclear Fuel Site
Challenges

Made of unlined concrete

7
Hanford Nuclear Fuel Site
Challenges

2,100 metric tons of SNF are stored

SNF is principally metallic uranium


but also it include:
- 5 metric tons of Plutonium
- 1 ton of Radio active Fission
products .
Some of SNF is corroded and
became sludge .

The 40-year old basins

original 20-year design life


Major leaks in 1970s and 1993

Operating and attempting to maintain these “accidents waiting to happen”


cost $100,000 a day 8
Hanford Nuclear Fuel Site
Addressing the problem

 To determine Acceptable Options Hanford went To:


Site’s stakeholders:
- The media
- Activists regulators
- Oversight group
- Three Indian tribes
- Government Leader
- Congress
- Hanford Employees

It required five months of public discussion for the stakeholders to


understand the issues and regain their trust in Hanford

9
Hanford Nuclear Fuel Site
Options

Another two months were required to develop four


project options as follows:

1. Better Encapsulate the fuel and leave it in the basin

10
Hanford Nuclear Fuel Site
Options

Another two months were required to develop four


project options as follows:

2. Place the fuel in wet storage elsewhere at Hanford.

11
Hanford Nuclear Fuel Site
Options

Another two months were required to develop four


project options as follows:

3. Place the fuel in dry storage elsewhere at Hanford.

12
Hanford Nuclear Fuel Site
Options

Another two months were required to develop four


project options as follows:

4. Ship the fuel overseas for reprocessing

13
Hanford Nuclear Fuel Site

 After 3 month of evaluation:

- Option 3 was selected


- The project was completed December 1999,“ three years
ahead of the original schedule”.
- saving taxpayers $350 million.
- the cost of maintaining the fuel is expected to drop to only
$3,000 per day.

14
Hanford Nuclear Fuel Site

Question -1: Why did it take five months to explain


the problem to the stakeholders?

15
Hanford Nuclear Fuel Site

Question -1: Why did it take five months to explain


the problem to the stakeholders?

 stakeholders :
 Stakeholders: are persons who either care
about or have a vested interest in your project
(owners, employees, government …).

16
Hanford Nuclear Fuel Site

1)
 We are faced here a immense problem ,we are
talking about nuclear fuel, because that we need to
explain the problem carefully and clearly to the
stakeholders.

17
Hanford Nuclear Fuel Site

2)
 Because the stakeholders are many and from different
aspects of society:
(the media, activists, regulators, oversight groups, three Indian
tribes, government leaders, Congress, and Hanford employees),
and each one has their own way of thinking :
-some stakeholders simply did not believe the problem existed.
-Others probably were worried that the suggested solutions
would only worsen the situation.

18
Hanford Nuclear Fuel Site

3)
 Is Take time to prepare for meetings with
stakeholders for Discussion and negotiation .

19
Hanford Nuclear Fuel Site

 NOTE:

Key stakeholders can make or break the


success of a project.

20
Hanford Nuclear Fuel Site

Question 2: Why do you think the stakeholders


no longer trusted the authorities ?

21
1- The basins located only 400 yards (366m) from
Washington State’s pristine Columbia River,

2- They had an original 20-year design life and


were in very poor condition.

3- They were experiencing major leaks in the


late 1970s and again in 1993.

4- Operating and attempting to maintain these


“accidents waiting to happen ”cost $100,000 a
day

22
Hanford Nuclear Fuel Site

23
Hanford Nuclear Fuel Site

Question 3: What might have been the problems with


options 1, 2, and 4?

24
Hanford Nuclear Fuel Site

Option one
 Encapsulate the fuel
 Definition
Encapsulate the fuel : enclose in shielded
a capsule or other small container horizontally in
tunnels at a depth of about 300 m

25
Hanford Nuclear Fuel Site

Option one
Advantage
By put extra shield Over the waste packages will be drip
shields to limit water contact ,This design allows a high
degree of flexibility for adjusting such things as waste
packages and package spacing.

Disadvantage

It just give more time not a solution of problem. so, the


stakeholder doesn't find this option as an alternative
solution

26
Hanford Nuclear Fuel Site

Option two
 Wet storage
Definition :
Storage of spent nuclear fuel in a pool of water or in canisters
filled with water

27
Hanford Nuclear Fuel Site

Option two
Advantage :
Doing some maintenance to reduce SNF from the Basins and provide for
up to 40 years of new wet storage in a new facility that meets current
design criteria. That's mean it would be accelerated reduce the SNF from
aging facilities near the Columbia River

Disadvantage :
it would require construction expense and continued
maintenance, would reduce but not prevent the continuation of
SNF degradation so, the stakeholder recognize that, we doing
the same thing over again and expecting a different result , but
the result will be the same of present problem
28
Hanford Nuclear Fuel Site

Option four
Ship the fuel overseas

Definition :
To transport the Snf to another location for
processing

29
Hanford Nuclear Fuel Site

Option four
 Advantage :
it converts uranium (the major constituent of SNF) into uranium
trioxide that is storable in dry form and for which future use
(constituent of power reactor fuel) might be found; converts
plutonium to a stable oxide for which a future use (constituent
of power reactor fuel) might be found
 Disadvantage :
uncertainties about the feasibility of shipping the degraded fuel
overseas. Also, costs of new shipping casks, and construction of a
new head-end facility at the processing plant

30
Hanford Nuclear Fuel Site

Question 4: How is option 3 a solution?

31
Hanford Nuclear Fuel Site

Question 4: How is option 3 a solution?

The option 3 was “place the fuel in dry storage at


Hanford” .
Why dry storage is the best…?

Dry storage managing is less expensive since it provides


all safety characteristics, doesn’t need electrical
systems (necessary only in vault storage), periodic
maintenance and a constant fuel monitoring,
increasing the system reliability for longer periods.
Another important characteristic is that the radiation
shield is made by thick concrete, cast iron, steel, lead
walls or a combination of them.

32
Hanford Nuclear Fuel Site
Summary

1- Dry storage is the most safer .


2- It can not react with the dry place while it is was
happening with wet place .
3- It does not need the expensive cooling and purification
systems as there are in wet storages "pools".
4- It has less risk in an accident than a spent fuel pool.
5- It is more difficult to crack or fail in an earthquake.

33
Hanford Nuclear Fuel Site

Conclusion

After all these considerations it can be concluded


that dry storage for spent nuclear fuel is more
advantageous for long time

34
Thank you
References:
1. PROJECT MANAGEMENT A Managerial Approach by Jack R. Meredith
2. Management of Spent Nuclear Fuel from the K Basins at Hanford Site,
Columbia ... By Richland County
3. Wikipedia

35

Potrebbero piacerti anche