UNIT PELAKSANA PROYEK PEMBANGKIT JBT 2

“METHOD STATEMENT FOR CONCRETE LINING IN TAILRACE TUNNEL”

RAMA ALPHA YURI MARGARETA – 9216531ZY


UNIT PELAKSANA PROYEK PEMBANGKIT JBT 2

General Description

Compilation Basis

Allocation of Resources

Construction Layout

Construction Method

www.pln.co.id 1
GENERAL
DESCRIPTION
UNIT PELAKSANA PROYEK PEMBANGKIT JBT 2

Referring to Official Letter No. 1540


“Submission of Construction Method
Statement for Concrete Lining in Tailrace
Tunnel” dated March 5, 2018

Guidance for construction of tailrace tunnel


concrete lining, mainly including installation
of reinforcement, installation of formwork,
and concrete placement

www.pln.co.id 2
COMPILATION
BASIS
UNIT PELAKSANA PROYEK PEMBANGKIT JBT 2

DETAIL DESIGN DRAWINGS

STANDARDS
ASTM C 33 : Concrete Aggregate
ACI 301 : Structural Concrete in Building
ASTM A 615 : Deformed and Plain Carbon-Steel
Bars for Concrete Reinforcement
ASTM A36M-08 : Carbon Structural Steel

CONSTRUCTION SCHEDULE

www.pln.co.id 3
ALLOCATION OF
RESOURCES
UNIT PELAKSANA PROYEK PEMBANGKIT JBT 2

MATERIAL EQUIPMENT
Steel bar D19
2 units
723.16 ton
@6 meter
Steel bar R8
10.57 ton

Concrete
12616 ton
1 unit

PVC Waterstop
LABOUR
1999 m

Highskilled
8persons
Manager Foreman Skilled
2persons 8persons 16persons
General
10persons

www.pln.co.id 4
CONSTRUCTION
LAYOUT
UNIT PELAKSANA PROYEK PEMBANGKIT JBT 2

www.pln.co.id 5
UNIT PELAKSANA PROYEK PEMBANGKIT JBT 2

Starting Ending Length Starting Ending Length


No. No.
Chainage Chainage (m) Chainage Chainage (m)
S1 PW0+009.45 PW0+021.45 12 S3 PW0+141.909 PW0+153.909 12

S2 PW0+021.45 PW0+031.406 9.956 S4 PW0+153.909 PW0+165.909 12

S5 PW0+165.909 PW0+177.909 12

C1 PW0+031.406 PW0+037.626 6.22 S6 PW0+177.909 PW0+189.909 12

C2 PW0+037.626 PW0+043.846 6.22 …

C3 PW0+043.846 PW0+050.066 6.22 …

… …

… S40 PW0+597.909 PW0+609.909 12

C16 PW0+124.706 PW0+130.926 6.22 S41 PW0+609.909 PW0+621.909 12

C17 PW0+130.926 PW0+137.146 6.22 S42 PW0+621.909 PW0+628.639 6.73

C18 PW0+137.146 PW0+141.909 4.763 S43 PW0+628.639 PW0+635.368 6.729

www.pln.co.id 6
UNIT PELAKSANA PROYEK PEMBANGKIT JBT 2

Starting Ending Length


No.
Chainage Chainage (m)
C19 PW0+635.368 PW0+641.588 6.22

C20 PW0+641.588 PW0+647.808 6.22

C28 PW0+691.348 PW0+697.568 6.22


Notes:
C29 PW0+697.568 PW0+701.611 4.043
S = Straight Section
C = Curve Section
S44 PW0+701.611 PW0+713.611 12

S45 PW0+713.611 PW0+725.611 12

S72 PW1+037.611 PW1+049.611 12

S73 PW1+049.611 PW1+055.84 6.229

www.pln.co.id 7
UNIT PELAKSANA PROYEK PEMBANGKIT JBT 2

• From 2# tank  • 1 set of 20


4’’ steel pipe to EL. m3/min
91m  1.5” compressor
rubber pipe to
working face

Water Supply Air Supply

Production &
Transportation Power Supply
of Concrete

• HZS60/HZS90 • T1 Substation with


batching plant 380V output
• 6 m3 concrete mixer • 252 kW mobil
• Concrete pump diesel generator

www.pln.co.id 8
CONSTRUCTION
METHOD
UNIT PELAKSANA PROYEK PEMBANGKIT JBT 2

Surface
Preparation

Installation of
reinforcement

Embedding of
grouting pipes

Concrete
Placement

Concrete
Curing

www.pln.co.id 9
UNIT PELAKSANA PROYEK PEMBANGKIT JBT 2

www.pln.co.id 9