PAMA

MINE SCHEDULLING

Engineering Dept, May 2007


KPCS - Sangatta
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

MINE BUSSINES
1. EXPLORATION
2. GEOLOGICAL MODELING
3. GEOLOGICAL RESERVING & RANKING
MANAGEMENT
4. PIT OPTIMATION
5. SCHEDULLING
6. MINING OPERATION
7. PROCESSING GEOLOGIST OPERATION
8. MARKETING

ENGINEER
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

EXPLORATION
SUATU KEGIATAN UNTUK MENCARI PERSPEKTIF
MELIPUTI :
1. BAHAN GALIAN MINERAL
2. ORE / BIJIH (EMAS, TEMBAGA)
3. DEPOSIT (COAL, BOUXSITE)
4. MINYAK, GAS ALAM
5. DLL
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

GEOLGICAL MODELING
SUATU PROSES UNTUK MENDAPATKAN MODEL GEOLOGI
DARI SUATU PERSPEKTIF
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

GEOLOGICAL RESERVING
& RANKING
SUATU PROSES UNTUK MENDAPATKAN CADANGAN GEOLOGI
DAN QUALITY

RESERVE

Model Rank

Database
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

PIT OPTIMATION
SUATU PROSES UNTUK MENDAPATKAN DESIGN TAMBANG
YANG MEMENUHI SYARAT TEKNIS, EKONOMIS, UU
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

MAN TOPOGRAPHY
PT. PAMAPERSADA NUSANTARA

OPTIMUM PIT
DISTRICT KPC SANGATTA - KALTIM
PAMA

DYKE S W

E
N

FAULT ZONE
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA
RANKING : PIT OPTIMIZATION

Nested Pits

By changing sale price $12


(eg) the pit grows and
shows best NPV
sequence.
$14

$16

$18 sale price

$20
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

SCHEDULLING
Drill Hole, Down Hole
Data Collection Geophysics, Seismic,
Survey, Blast Hole.

Correlation & Interpretation

Geological Modeling
Phase 1

Ranking & Mining Model


(Stripping Ratios, Optimization, NPV)
Phase 2
Design (Pit/Bench/Strip/Block)

Scheduling (Equip & Calendars)


PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

MINING OPERATION
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

PROCESSING
1. COAL CRUSHING, COAL BLENDING
2. METALURGI, PENGOLAHAN EMAS, TEMBAGA

MARKETING
1. BARGING, DELIVERY
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

MINE
SCHEDULING
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

JOB DESCRIPTION

1. DEWATERING
2. BREAK YEARLY DESIGN TO MONTHLY & WEEKLY
3. FLEET MATCHING
4. PIT SEQUENCE
5. BLAST SEQUENCE
6. TECHNICAL SUPPORT
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

Scheduling allows the engineer to

•Design a pit
•Calculate volumes & quality
•Report the designs
•Schedule the pit
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

PIT DESIGN
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

PIT DESIGN
What is a bench
Bench is what
we dig

2
3
Benches number
down.
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

What is a bench

CREST Bench 2

2
Benches have a toe
and a crest Toe Bench 2
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

Slope is from
horizon

2
With a toe
and a crest a
bench has a slope
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

Berm in metres

2
Berms separate
benches
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

RAMPS
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

DUMPS
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

DIP

DE-COALED AREA
INCROP
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

RESERVES
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

RESERVE
Flow sheet

Pit Design Geological


+ Model

Pit Block
Database
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

OB

IB

COAL
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

1. OB = $/BCM
2. CL = $/TON

$
REVENUE
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

Lower wedge Upper wedge


PT. PAMAPERSADA NUSANTARA

What is a design?
DISTRICT KPC SANGATTA - KALTIM
PAMA

Basically blocks
Pit Reserves building strips &
benches
BLOCK 1 BLOCK 2

BENCH 1

BENCH 2
SEAM A SEAM B
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

STRIPS
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

2D PLAN OUT PUT


PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

RESERVES
REPORT
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

Strip Ratio

3 - 5 BCM / TONNE

2 - 3 BCM / TONNE

0 - 2 BCM / TONNE
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

Overburden Mining Cost


PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

OB Vol
(Mbcm)
values
in Plan
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

Sulfur
colored
by value
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

SCHEDULING
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

RATE
CALENDAR
UTILISATION
FACTORS
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

BLOCK HAS VOLUMES


EQUIPMENT HAS A RATE
CALENDAR HAS DELAYS

TIME = VOLUME / RATE


= SCHEDULE
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA
EQUIP PLACEMENT
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

Schedule ….
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

Schedule ….
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

Schedule ….
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA
POSITION OF PIT AT THE END OF 1st
YEAR
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

POSITION OF PIT AT THE END OF 5th


YEAR

MIDDLE
SEAM

DE - COALED AREA
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA
PRODUCTION
SCHEDULING

suggest mining 1, 2, 3, 4

2 1
4 3

C A
B
D B
C
D

schedule mines A,B,C,D


PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

SCHEDULE OUTPUT
Bar Chart
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

GANT CHART
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

FLEET
MATCHING
SIMULATION
1. SPREED SHEET
2. TALPAC
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

FLEET
REQUIREMENT
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

PIT SIMULATION
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

TABEL
PT. PAMAPERSADA NUSANTARA
DISTRICT KPC SANGATTA - KALTIM
PAMA

DISKUSI

TARGET JAN FEB MAR


OB 6000 6000 6000
EXPOSE 1500 2000 2000
PC300 4 BCM/HARI
PC100 2 BCM/HARI