HEARTIEST

WELCOME TO

Dr T K Chand
Chairman-cum-Managing Director

NALCO
1
220 KV Transmission Line project

Project Cost CAPEX Target CAPEX Actual till Expected Completion for
2017-18 2017-18 Transmission line
103.81 Cr 18.19 Cr (BE) 4.84 Cr 15.04.18
14.00 Cr (RE) Total completion by Aug’18

SubStation M/s ABB Cable M/s KEI


Transmission Line M/s
For First Circuit, work First Circuit
EMPTL
completed with all respect. completed with all
Erection of towers110
 For 2nd Circuit, respect.
nos completed out of 145.
Transformer inspection Second Circuit
scheduled in the Dec 2017.
Stringing of 8.0 Km
Cable supply expected
Site foundation work is completed for both the
by Mar’18.
under progress. circuit out of 37Km.

2
5th Stream Expansion
Project Cost CAPEX Target CAPEX Actual till Expected Completion
2017-18 2017-18
4104 Cr 70.51 Cr (RE) 44.08 Cr Dec 2020

Alumina Refinery by M/s tkIS:


▪ Major Basic Engineering completed and finalisation by Jan 18.
▪ Overall Plot Plan and General Engineering Specifications Completed.
▪ Boundry wall North side extension work started on 06.10.17 with the help of
Police protection but again came to an halt due to local people resistence.
▪ Soil Investigation and Contur survey work awarded on 15.12.2017.
▪ Draft NIT and MR for Bauxite Handling, Evaporation & Calcination reviewed
expected to be floated in Jan 18.

3
5th Stream Expansion (Cont.)

Steam Power Plant by M/s Dasturco:


▪ Overall Layout, Design Specifications are being Finalised
▪ Battery Limit between Alumina Refinery & SPP has been finalised.
Area of Concern:
 Higher level intervention required from State Capital.
 EPCM consultency for the alternate arrangement for sourcing of Bauxite from
Panchpatmali Mine.
 Finalisation of Railway Works.
 Finalisation of Township Expansion.

4
Conversion of Conventional Settler & Washer to HRD & DCW
Project Cost CAPEX Target CAPEX Actual till Expected Completion
2017-18 2017-18
355 Cr 18.00 Cr (BE) 13.88 Cr Nov 2020
22.71 Cr (RE)

▪ Basic Engineering completed.


▪ Plot Plan and General Engineering Specifications completed
▪ Placement of Order for Rake Mechanism on M/s RTAIL expected in Dec’18.
▪ Draft NIT and MR for LSTK package is expected in Dec’18.

5
2nd Water Intake
Project Cost CAPEX Target CAPEX Actual Expected Completion
BE 2017-18 2017-18
98 .00 Cr 6 .00 Cr 0.44 Cr Jan 2019

▪ Survey work completed


▪ Pipe culvert at NH crossing work completed.
▪ NIT for supply and erection contract has been floated and opening scheduled
on 21.12.2017.
▪ Request letter for laying of Pipe, Road and Electrical Installations in
Government Land shall be submitted by 20.12.2017

6
BPTG#5
MAJOR ACHIEVENTS BALANCE JOBS
TG #5 Syncronised on 18.10.2017 Attending to Controller
PRDS Line Charged on 24.11.2017 Problems

Stable Operation (14 Days Trial Run) of Completion of PG Test


TG#5 has started on 27.11.2017 with
loading upto 18.5 MW . However TG#5
was stopped on 16.12.2017 to attend
the suspected Governor Controller
problem for achieving the rated load of
19.5 MW .

7
Rectification Work of Bauxite Stock Pile – 06

▪ Initial static pile load test conducted on 06.11.2017


▪ Piling Work started from 28.11.2017.
▪ Total 20 nos out of 163 nos Pilies has been completed as on date.
▪ Pile cap and rail foundation work scheduled to start from 20.01.2017.
▪ The Stock Pile shall be handed over for Normal Operation in June 2018.

8
9
Reclaimar and Associated Conveyors Package by M/s FLSmidth

 Total Order Value: Rs. 59,69,63,859.00


 Date of Commissioning of Reclaimer and Conveyor 1104 & 1106: 19th Oct’12.
 Date of Commissioning of Conveyor 1105 & 1107: 3rd May’13
 Stock Pile - 6 defect identified on: 12th June 2013.
 After lot of discussions with M/s FLS and studies by IIT Delhi and IIT Madras, it
was decided for ground improvement. Accordingly, it was decided to go for PVD
(Prefabricated Vertical Drains) method.
 Due to reluctance from M/s FLSmidth it was decided to go ahead for rectification
at risk and cost of M/s FLS. Accordingly, job was awarded to M/s Trinath
Engineers for “Partial Ground Improvement” and Low Strain Integrity & Ultrasonic
Pulse Velocity testing of Piles/ Beams by M/s S Ghosh & Associates on
20.09.2014.

10
Reclaimar and Associated Conveyors Package by M/s FLSmidth (Cont.)

During erection it was noticed that there is a discontinuity in the piles and by
exposing the piles up to 5 to 6 meters depth, it was noticed that some piles are
like mushrooms.
 Accordingly, mater was taken up with M/s FLS and they agreed to take up the
rectification work in the moth September 2015.
 Then they started working after detail testing and accordingly, they mobilized
the pilling agency in month of December 2016.
 During Piling, it is observed that there is a clay material from 22 meters to 28
meters depth. Accordingly, further tests have been carried out i.e. SPT (Standard
Penetration Test) and completed in August 2017.
 On initial pile load test completion of 22 meters pile on 06.11.2017, they
mobilized a piling agency on 28.11.2017 and piling job is under progress.
 Rectification works are expected to be completed by June 2018.

11
5th Stream Alumina Refinery Progress Statistics as on Nov 2017

12
Tentative Project Expenditure per financial year
for 5th Stream Expansion

Cash Flow for the year Expenditure in ` Cr.


Apr-2017 to Mar-2018: 80
Apr-2018 to Mar-2019: 428
Apr-2019 to Mar-2020: 1,320
Apr-2020 to Mar-2021: 1469
Apr-2021 to Mar-2022: 807
Total Cash Flow 4,104

13