LIMAR P.

CANDO

PROJECT

SCHEDULE
PROJECT NAME: COST CENTER
DAY START FINISH
1.0 EVERGREEN GYPSUM BUNKER PCE – 16 – 60058 30 DEC 20,2016 JAN 20, 2017
4.00M X 32.00M SLAG BLOCK FENCE
(DOUBLE)

MANPOWER: ACTIVITIES:

MANPOWER ACTIVITIES REMARKS

1.0 FOREMAN 1
1.0 LAY OUT DONE
2.0 LEADMAN 1

3.0 MASON 5 2.0 FOOTING EXCAVATION 32 / 32 MTR

4.0 CARPENTER 1 3.0 GRAVEL BEDDING Done


5.0 LABORER 10
4.0 CONCRETING OF FOOTING Done
6.0
5.0 RE BARS INSTALLATION Done
7.0
6.0 LAYING OF SLAG BLOCKS on going
TOTAL 18
7.0 CONCRETING OF COLUMN AND BEAMS jan 20
EG GYPSUM BUNKER
EG GYPSUM BUNKER
EG GYPSUM BUNKER
EG GYPSUM BUNKER
EG GYPSUM BUNKER
EG GYPSUM BUNKER
EG GYPSUM BUNKER
EG GYPSUM BUNKER
EG GYPSUM BUNKER
LIMAR P. CANDO

UPCOMING PROJECT

SCHEDULE
PROJECT NAME: COST CENTER
DAY START FINISH
1.0 DRY CHARGE SLAB REPAIR

PHASE 1 AREA 38.50M X 6.00M

MANPOWER: ACTIVITIES:

MANPOWER ACTIVITIES REMARKS

NOTE:
1.0
FOR SUBMISSION OF QUOTATION
1.0 CHIPPING OF SLAB (MAX. 0.10M)
2.0
2.0 SONOBOND APPLICATION
3.0

4.0 3.0 SLAB CONCRETING

5.0 4.0

6.0
5.0
7.0
6.0
DC SLAB REPAIR
LIMAR P. CANDO

PROJECT

SCHEDULE
PROJECT NAME: COST CENTER
DAY START FINISH
1.0 DC LAGOON WALL SUPPORT 14 JAN 05 JAN 19
PCE – 17 - 10085

MANPOWER: ACTIVITIES:

MANPOWER ACTIVITIES REMARKS

1.0 FOREMAN 1

2.0 MASON 2
1.0 LAY OUT DONE

3.0 STEELMAN 1 2.0 EXCAVATION 47/ 7


4.0 LABORER 4 3.0 REBARS FABRICATION DONE
5.0
4.0 REBARS INSTALLATION 7 /7
6.0
5.0 CONCRETING OF FOOTING/BEAMS 7 /7 done
7.0
6.0 slab restoration jan 20
total 8
clearing and hauling of waste
jan 21
materials
DC LAGOON WALL SUPPORT
DC LAGOON WALL SUPPORT
DC LAGOON WALL SUPPORT
DC LAGOON WALL SUPPORT
DC LAGOON WALL SUPPORT
LIMAR P. CANDO

PROJECT

SCHEDULE
PROJECT NAME: COST CENTER
DAY START FINISH
1.0 MCB COVERED WALKWAY 35 JAN 6 MAR 10
PCE – 17 - 10086

138.00 MTR COVERED WALKWAY

MANPOWER: ACTIVITIES:

MANPOWER
ACTIVITIES REMARKS

1.0

2.0 1.0 LAY OUT FOR APPROVAL


3.0 2.0 EXCAVATION FOR APPROVAL
4.0
3.0 REBARS FABRICATION DONE
5.0
4.0 REBARS INSTALLATION DONE
6.0 status: on hold
5.0 CONCRETING OF PRECAST FOOTING 34 / 34 PCS
7.0
6.0 CONCRETING OF SIDEWALK 00 / 138 M
MCB COVERED WALKWAY
MCB COVERED WALKWAY
MCB COVERED WALKWAY
MCB COVERED WALKWAY