Sei sulla pagina 1di 91

2 Project Management

For Operations Management, 9e by


PowerPoint Slides
Krajewski/Ritzman/Malhotra
by Jeff Heyl © 2010 Pearson Education
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2–1
Projects

 Projects are an interrelated set of activities


with a definite starting and ending point,
which results in a unique outcome from a
specific allocation of resources
 Projects are common in everyday life
 The three main goals are to:
 Complete the project on time
 Not exceed the budget
 Meet the specifications to the satisfactions of
the customer

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2–2


Projects

 Project management is a systemized,


phased approach to defining, organizing,
planning, monitoring, and controlling
projects
 Projects often require resources from
many different parts of the organization
 Each project is unique
 Projects are temporary
 A collection of projects is called a program

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2–3


Defining and Organizing Projects
 Define the scope, time frame, and
resources of the project
 Select the project manager and team
 Good project managers must be
 Facilitators
 Communicators
 Decision makers
 Project team members must have
 Technical competence
 Sensitivity
 Dedication

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2–4


Organizational Structure

 Different structures have different


implications for project management

 Common structures are


 Functional

 Pure project
 Matrix

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2–5


Planning Projects

 There are five steps to planning projects

1. Defining the work breakdown structure


2. Diagramming the network
3. Developing the schedule
4. Analyzing the cost-time trade-offs
5. Assessing risks

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2–6


Work Breakdown Structure

 A statement of all the tasks that must be


completed as part of the project

 An activity is the smallest unit of work


effort consuming both time and resources
that the project manager can schedule and
control

 Each activity must have an owner who is


responsible for doing the work

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2–7


Work Breakdown Structure
Relocation of St. John’s Hospital Level 0

Organizing and Site Preparation Physical Facilities and Infrastructure Level 1

Select administration staff Purchase and deliver equipment

Site selection and survey Construct hospital

Select medical equipment Develop information system Level 2

Prepare final construction plans Install medical equipment

Bring utilities to site Train nurses and support staff

Interview applicants for


nursing and support staff Figure 2.1

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2–8


Diagramming the Network

 Network diagrams use nodes and arcs to


depict the relationships between activities
 Benefits of using networks include
1. Networks force project teams to identify and
organize data to identify interrelationships
between activities
2. Networks enable the estimation of completion
time
3. Crucial activities are highlighted
4. Cost and time trade-offs can be analyzed

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2–9


Diagramming the Network

 Precedent relationships determine the


sequence for undertaking activities

 Activity times must be estimated using


historical information, statistical analysis,
learning curves, or informed estimates

 In the activity-on-node approach, nodes


represent activities and arcs represent the
relationships between activities

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 10


Diagramming the Network

AON Activity Relationships

S T U S precedes T, which
precedes U.

S S and T must be
U completed before U
can be started.
T

Figure 2.2

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 11


Diagramming the Network

AON Activity Relationships

T
T and U cannot
S begin until S has
U been completed.

S U U and V can’t begin


until both S and T
have been completed.
T V

Figure 2.2

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 12


Diagramming the Network

AON Activity Relationships

U cannot begin until


S U both S and T have been
completed; V cannot
begin until T has been
T V
completed.

T and U cannot begin


S T V
until S has been
completed and V cannot
U begin until both T and U
have been completed.

Figure 2.2

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 13


Developing the Schedule

 Schedules can help managers achieve the


objectives of the project

 Managers can
1. Estimate the completion time by finding the
critical path
2. Identify start and finish times for each activity
3. Calculate the amount of slack time for each
activity

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 14


Critical Path

 The sequence of activities between a


project’s start and finish is a path

 The critical path is the path that takes the


longest time to complete

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 15


St. John’s Hospital Project
Activity Immediate Activity Times Responsibility
Predecessors (wks)
ST. JOHN’S HOSPITAL PROJECT Kramer
START 0
ORGANIZING and SITE PREPARATION Stewart
A. Select administrative staff START 12 Johnson
B. Select site and survey START 9 Taylor
C. Select medical equipment A 10 Adams
D. Prepare final construction plans B 10 Taylor
E. Bring utilities to site B 24 Burton
F. Interview applicants for nursing and A 10 Johnson
support staff
PHYSICAL FACILITIES and INFRASTRUCTURE
G. Purchase and deliver equipment C 35 Walker
H. Construct hospital D 40 Sampson
I. Develop information system A 15 Casey
J. Install medical equipment E, G, H 4 Murphy
K. Train nurses and support staff F, I, J 6 Pike
FINISH K 0 Ashton

Example 2.1
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 16
St. John’s Hospital Project
Activity Immediate Activity Times Responsibility
Predecessors (wks)
ST. JOHN’S HOSPITAL PROJECT
Completion Time I
START 15
ORGANIZING
Activity IP and
Time SITE PREPARATION
A A. Select
STARTadministrative
12 staff
A F K
B B. Select
STARTsite and 9 survey 12 10 6
C A 10
C. Select medical equipment
D B 10
E D. Prepare
B final24construction plans
F E. Bring
A 10to site
utilities C G
Start Finish
G C 35 10 35
F. Interview applicants for nursing and
H D
support staff40
I A 15
J PHYSICAL
E, G, H FACILITIES
4 and INFRASTRUCTURE
B D H J
K G. Purchase
F, I, J and6 deliver equipment 9 10 40 4
H. Construct hospital
I. Develop information system
E
J. Install medical equipment
24
K. Figureand
Train nurses 2.3 support staff
FINISH

Example 2.1
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 17
St. John’s
Path Hospital
Estimated Time (weeks) Project
A–I–K 33
A–F–K
Activity 28 Immediate Activity Times Responsibility
Predecessors (wks)
A–C–G–J–K 67
ST. JOHN’S HOSPITAL PROJECT
Completion I
B–D–H–J–K
START 69 Time
15
B–E–J–K 43
ORGANIZING and SITE PREPARATION
A. Select administrative staff
A F K
B. Select site and survey 12 10 6
C. Select medical equipment
D. Prepare final construction plans
E. Bring utilities to site C G
Start Finish
10 35
F. Interview applicants for nursing and
support staff
PHYSICAL FACILITIES and INFRASTRUCTURE
B D H J
G. Purchase and deliver equipment 9 10 40 4
H. Construct hospital
I. Develop information system
E
J. Install medical equipment
24
K. Figureand
Train nurses 2.3 support staff
FINISH

Example 2.1
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 18
St. John’s
Path Hospital
Estimated Time (weeks) Project
A–I–K 33
A–F–K
Activity 28 Immediate Activity Times Responsibility
Predecessors (wks)
A–C–G–J–K 67
ST. JOHN’S HOSPITAL PROJECT
Completion I
B–D–H–J–K
START 69 Time
15
B–E–J–K 43
ORGANIZING and SITE PREPARATION
A. Select administrative staff
A F K
B. Select site and survey 12 10 6
C. Select medical equipment
D. Prepare final construction plans
E. Bring utilities to site C G
Start Finish
10 35
F. Interview applicants for nursing and
support staff
PHYSICAL FACILITIES and INFRASTRUCTURE
B D H J
G. Purchase and deliver equipment 9 10 40 4
H. Construct hospital
I. Develop information system
E
J. Install medical equipment
24
K. Figureand
Train nurses 2.3 support staff
FINISH

Example 2.1
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 19
Application 2.1

The following information is known about a project

Immediate
Activity Activity Time (days) Predecessor(s)
A 7 —
B 2 A
C 4 A
D 4 B, C
E 4 D
F 3 E
G 5 E

Draw the network diagram for this project

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 20


Application 2.1
Immediate
Activity Activity Time (days) Predecessor(s)
A 7 —
B 2 A
C 4 A
D 4 B, C
E 4 D
F 3 E
G 5 E

B F
2 3
A D E
Start Finish
7 4 4
C G
4 5

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 21


Project Schedule

 The project schedule specifies start and


finish times for each activity

 Managers can use the earliest start and


finish times, the latest start and finish
times, or any time in between these
extremes

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 22


Project Schedule

 The earliest start time (ES) for an activity is the


latest earliest finish time of any preceding
activities
 The earliest finish time (EF) is the earliest start
time plus its estimated duration
EF = ES + t

 The latest finish time (LF) for an activity is the


latest start time of any preceding activities
 The latest start time (LS) is the latest finish time
minus its estimated duration
LS = LF – t

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 23


Early Start and Early Finish Times
EXAMPLE 2.2
Calculate the ES, EF, LS, and LF times for each activity in the
hospital project. Which activity should Kramer start
immediately? Figure 2.3 contains the activity times.

SOLUTION
To compute the early start and early finish times, we begin at
the start node at time zero. Because activities A and B have no
predecessors, the earliest start times for these activities are
also zero. The earliest finish times for these activities are

EFA = 0 + 12 = 12 and EFB = 0 + 9 = 9

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 24


Early Start and Early Finish Times
Because the earliest start time for activities I, F, and C is the
earliest finish time of activity A,

ESI = 12, ESF = 12, and ESC = 12


Similarly,
ESD = 9 and ESE = 9

After placing these ES values on the network diagram, we


determine the EF times for activities I, F, C, D, and E:

EFI = 12 + 15 = 27, EFF = 12 + 10 = 22, EFC = 12 + 10 = 22,


EFD = 9 + 10 = 19, and EFE = 9 + 24 = 33

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 25


Early Start and Early Finish Times
The earliest start time for activity G is the latest EF time of all
immediately preceding activities. Thus,

ESG = EFC = 22, ESH = EFD = 19


EFG = ESG + t = 22 + 35 = 57, EFH + t = 19 + 40 = 59

Activity

Earliest start time


Earliest finish time
A
0 12

Latest start time 2 14


12 Latest finish time

Duration
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 26
Network Diagram
12
I 27

15

A
0 12 12 F 22 63 K 69
12 10 6

12
C 22 22
G 57
Start Finish
10 35

0
B 9 9
D 19 19
H 59 59
J 63

9 10 40 4

9 E 33
24
Figure 2.4

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 27


Early Start and Early Finish Times

To compute the latest start and latest finish times,


we begin by setting the latest finish activity time of
activity K at week 69, which is the earliest finish time
as determined in Figure 2.4. Thus, the latest start
time for activity K is

LSK = LFK – t = 69 – 6 = 63

If activity K is to start no later than week 63, all its


predecessors must finish no later than that time.
Consequently,

LFI = 63, LFF = 63, and LFJ = 63

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 28


Early Start and Early Finish Times
The latest start times for these activities are shown in Figure 2.4
as

LSI = 63 – 15 = 48, LFF = 63 – 10 = 53, and LSJ = 63 – 4 = 59

After obtaining LSJ, we can calculate the latest start times for
the immediate predecessors of activity J:

LSG = 59 – 35 = 24, LSH = 59 – 40 = 19, and LSE = 59 – 24 = 35

Similarly, we can now calculate the latest start times for


activities C and D:

LSC = 24 – 10 = 14 and LSD = 19 – 10 = 9

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 29


Early Start and Early Finish Times

Activity A has more than one immediately following


activity: I, F, and C. The earliest of the latest start
times is 14 for activity C. Thus,

LSA = 14 – 12 = 2

Similarly, activity B has two immediate followers: D


and E. Because the earliest of the latest start times
of these activities is 9.

LSB = 9 – 9 = 0

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 30


Network Diagram
12
I 27
48
15 63
S = 36

A
0 12 12 F 22 63 K 69
2 12 14 53 63 63 6 69
10
S=2 S = 41 S=0

12
C22 22
G 57
Start 24 Finish
14 10 24 35 59
S=2 S=2

0
B 9 9
D 19 19
H 59 59
J
63
9 19 59
0 9 9 10 19 40 59 4 63

S=0 S=0 S=0 S=0

9 E 33
35 59
24
Figure 2.4
S = 26
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 31
Gantt Chart

Figure 2.5

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 32


Activity Slack

 Activity slack is the maximum length of


time an activity can be delayed without
delaying the entire project
 Activities on the critical path have zero
slack
 Activity slack can be calculated in two
ways

S = LS – ES or S = LF – EF

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 33


Application 2.2
Calculate the four times for each activity in order to determine
the critical path and project duration.

Earliest Latest Earliest Latest On the


Start Start Finish Finish Slack Critical
Activity Duration (ES) (LS) (EF) (LF) (LS-ES) Path?
A 7 0 0 7 7 0-0=0 Yes
B 2
C 4
D 4
E 4
F 3
G 5

The critical path is A–C–D–E–G with a project duration of 24 days

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 34


Application 2.2
Calculate the four times for each activity in order to determine
the critical path and project duration.

Earliest Latest Earliest Latest On the


Start Start Finish Finish Slack Critical
Activity Duration (ES) (LS) (EF) (LF) (LS-ES) Path?
A 7 0 0 7 7 0-0=0 Yes
B 2 7 9 9 11 9-7=2 No
C 4 7 7 11 11 7-7=0 Yes
D 4 11 11 15 15 11-11=0 Yes
E 4 15 15 19 19 15-15=0 Yes
F 3 19 21 22 24 21-19=2 No
G 5 19 19 24 24 19-19=0 Yes

The critical path is A–C–D–E–G with a project duration of 24 days

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 35


Application 2.2
Earliest Latest Earliest Latest On the
Start Start Finish Finish Slack Critical
Activity Duration (ES) (LS) (EF) (LF) (LS-ES) Path?
A 7 0 0 7 7 0-0=0 Yes
B 2 7 9 9 11 9-7=2 No
C 4 7 7 11 11 7-7=0 Yes
D 4 11 11 15 15 11-11=0 Yes
E 4 15 15 19 19 15-15=0 Yes
F 3 21 21 22 24 21-19=2 No
G 5 19 19 24 24 19-19=0 Yes

The critical path is A–C–D–E–G with a project duration of 24 days

B F
2 3
A D E
Start Finish
7 4 4
C G
4 5

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 36


Application 2.2
Earliest Latest Earliest Latest On the
Start Start Finish Finish Slack Critical
Activity Duration (ES) (LS) (EF) (LF) (LS-ES) Path?
A 7 0 0 7 7 0-0=0 Yes
B 2 7 9 9 11 9-7=2 No
C 4 7 7 11 11 7-7=0 Yes
D 4 11 11 15 15 11-11=0 Yes
E 4 15 15 19 19 15-15=0 Yes
F 3 21 21 22 24 21-19=2 No
G 5 19 19 24 24 19-19=0 Yes

The critical path is A–C–D–E–G with a project duration of 24 days

B F
2 3
A D E
Start Finish
7 4 4
C G
4 5

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 37


Cost-Time Trade-Offs

 Total project costs are the sum of direct


costs and indirect costs
 Projects may be crashed to shorten the
completion time
 Costs to crash
1. Normal time (NT) 3. Crash time (CT)
2. Normal cost (NC) 4. Crash cost (CC)

CC – NC
Cost to crash per period =
NT – CT

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 38


Cost-Time Relationships

8000 —
Crash cost (CC)
7000 —
Direct cost (dollars)

Linear cost assumption


6000 —
Estimated costs for
5200 a 2-week reduction,
5000 — from 10 weeks to
8 weeks
4000 —

3000 — Normal cost (NC)

0— | | | | | |
5 6 7 8 9 10 11
(Crash time) (Normal time)
Time (weeks)
Figure 2.6

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 39


Cost-Time Relationships

TABLE 2.1 | DIRECT COST AND TIME DATA FOR THE ST. JOHN’S HOSPITAL PROJECT

Activity Normal Time Normal Cost Crash Time Crash Cost Maximum Time Cost of
(NT) (weeks) (NC)($) (CT)(weeks) (CC)($) Reduction Crashing per
(week) Week ($)
A 12 $12,000 11 $13,000 1 1,000
B 9 50,000 7 64,000 2 7,000
C 10 4,000 5 7,000 5 600
D 10 16,000 8 20,000 2 2,000
E 24 120,000 14 200,000 10 8,000
F 10 10,000 6 16,000 4 1,500
G 35 500,000 25 530,000 10 3,000
H 40 1,200,000 35 1,260,000 5 12,000
I 15 40,000 10 52,500 5 2,500
J 4 10,000 1 13,000 3 1,000
K 6 30,000 5 34,000 1 4,000
Totals $1,992,000 $2,209,500

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 40


A Minimum-Cost Schedule
EXAMPLE 2.3
Determine the minimum-cost schedule for the St. John’s
Hospital project.

SOLUTION
The projected completion time of the project is 69 weeks. The
project costs for that schedule are $1,992,000 in direct costs,
69($8,000) = $552,000 in indirect costs, and (69 – 65)($20,000)
= $80,000 in penalty costs, for total project costs of $2,624,000.
The five paths in the network have the following normal times:

A–I–K 33 weeks
A–F–K 28 weeks
A–C–G–J–K 67 weeks
B–D–H–J–K 69 weeks
B–E–J–K 43 weeks
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 41
A Minimum-Cost Schedule
STAGE 1
Step 1. The critical path is B–D–H–J–K.
Step 2. The cheapest activity to crash per week is J at $1,000,
which is much less than the savings in indirect and penalty
costs of $28,000 per week.
Step 3. Crash activity J by its limit of three weeks because the
critical path remains unchanged. The new expected path times
are
A–C–G–J–K: 64 weeks and B–D–H–J–K: 66 weeks
The net savings are 3($28,000) – 3($1,000) = $81,000. The total
project costs are now $2,624,000 - $81,000 = $2,543,000.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 42


A Minimum-Cost Schedule
STAGE 1
Step 1. The critical path is B–D–H–J–K.
I
15
Step 2. The cheapest activity to crash per week is J at $1,000,
which is much less than the savings in indirect and penalty
A F K
costs of $28,000 per week. 12 10 6
Step 3. Crash activity J by its limit of three weeks because the
critical path remains unchanged. The new expected path times
C G
are Start
10 35
Finish

A–C–G–J–K: 64 weeks and B–D–H–J–K: 66 weeks


B – 3($1,000)
The net savings are 3($28,000) D = $81,000.
H The
J total
9
project costs are now $2,624,000 10
- $81,000 40 1
= $2,543,000.

E
24

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 43


A Minimum-Cost Schedule
STAGE 2
Step 1. The critical path is still B–D–H–J–K.
Step 2. The cheapest activity to crash per week is now D at
$2,000.
Step 3. Crash D by two weeks. The first week of reduction in
activity D saves $28,000 because it eliminates a week of penalty
costs, as well as indirect costs. Crashing D by a second week
saves only $8,000 in indirect costs because, after week 65, no
more penalty costs are incurred. These savings still exceed the
cost of crashing D by two weeks. Updated path times are
A–C–G–J–K: 64 weeks and B–D–H–J–K: 64 weeks
The net savings are $28,000 + $8,000 – 2($2,000) = $32,000. Total
project costs are now $2,543,000 – $32,000 = $2,511,000.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 44


A Minimum-Cost Schedule
STAGE 2
Step 1. The critical path is still B–D–H–J–K.
I
15
Step 2. The cheapest activity to crash per week is now D at
$2,000.
A F K
Step 3. Crash D by two The week of weeks.
in 12 first
10 reduction
6
activity D saves $28,000 because it eliminates a week of penalty
costs, as well as indirect costs. Crashing D by a second week
C G
saves only $8,000 in indirect
Start costs because,
10
after
35
week 65, no
Finish
more penalty costs are incurred. These savings still exceed the
cost of crashing D by two weeks. Updated path times are
B D H J
A–C–G–J–K: 64 weeks
9 and B–D–H–J–K:
8 40 64 weeks
1

The net savings are $28,000 + $8,000 – 2($2,000) = $32,000. Total


project costs are now $2,543,000 – $32,000
E
= $2,511,000.
24

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 45


A Minimum-Cost Schedule
STAGE 3
Step 1. After crashing D, we now have two critical paths. Both
critical paths must now be shortened to realize any savings in
indirect project costs.
Step 2. Our alternatives are to crash one of the following
combinations of activities—(A, B); (A, H); (C, B); (C, H); (G, B);
(G, H)—or to crash activity K, which is on both critical paths (J
has already been crashed). We consider only those alternatives
for which the costs of crashing are less than the potential
savings of $8,000 per week. The only viable alternatives are (C,
B) at a cost of $7,600 per week and K at $4,000 per week. We
choose activity K to crash.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 46


A Minimum-Cost Schedule
STAGE 3
Step 3. We crash activity K to the greatest extent possible—a
reduction of one week—because it is on both critical paths.
Updated path times are

A–C–G–J–K: 63 weeks and B–D–H–J–K: 63 weeks

Net savings are $8,000 - $4,000 = $4,000. Total project costs are
$2,511,000 – $4,000 = $2,507,000.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 47


A Minimum-Cost Schedule
STAGE 3
Step 3. We crash activity K to the greatest
I extent possible—a
reduction of one week—because it is15on both critical paths.
Updated path times are
A F K
12 10 5
A–C–G–J–K: 63 weeks and B–D–H–J–K: 63 weeks
C G
Start Finish
10 35
Net savings are $8,000 - $4,000 = $4,000. Total project costs are
$2,511,000 – $4,000 = $2,507,000.
B D H J
9 8 40 1

E
24

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 48


A Minimum-Cost Schedule
STAGE 4
Step 1. The critical paths are still B–D–H–J–K and A–C–G–J–K.
Step 2. The only viable alternative at this stage is to crash
activities B and C simultaneously at a cost of $7,600 per week.
This amount is still less than the savings of $8,000 per week.
Step 3. Crash activities B and C by two weeks, the limit for
activity B. Updated path times are
A–C–G–J–K: 61 weeks and B–D–H–J–K: 61 weeks
The net savings are 2($8,000) – 2($7,600) = $800. Total project
costs are now $2,507,000 – $800 = $2,506,200.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 49


A Minimum-Cost Schedule
STAGE 4
Step 1. The critical paths are still B–D–H–J–K
I and A–C–G–J–K.
15
Step 2. The only viable alternative at this stage is to crash
activities B and C simultaneously at a cost of $7,600 per week.
A F K
This amount is still less than
12 the savings
10 of $8,000 per
5 week.
Step 3. Crash activities B and C by two weeks, the limit for
activity B. Updated path times are
C G
Start
A–C–G–J–K: 61 weeks and B–D–H–J–K:
8 35 61 weeksFinish
The net savings are 2($8,000) – 2($7,600) = $800. Total project
costs are now $2,507,000 – $800
B = $2,506,200.
D H J
7 8 40 1

E
24

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 50


A Minimum-Cost Schedule

Stage Crash Time Resulting Project Project Crash Total Total Total
Activity Reduction Critical Duration Direct Cost Indirect Penalty Project
(weeks) Path(s) (weeks) Costs, Added Costs Costs Costs
Last Trial ($000) ($000) ($000) ($000)
($000)
0 — — B-D-H-J-K 69 1,992.0 — 552.0 80.0 2,624.0

1 J 3 B-D-H-J-K 66 1,992.0 3.0 528.0 20.0 2,543.0

2 D 2 B-D-H-J-K 64 1,995.0 4.0 512.0 0.0 2,511.0


A-C-G-J-K
3 K 1 B-D-H-J-K 63 1,999.0 4.0 504.0 0.0 2,507.0
A-C-G-J-K
4 B, C 2 B-D-H-J-K 61 2,003.0 15.2 488.0 0.0 2,506.2
A-C-G-J-K

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 51


Application 2.3
Indirect project costs = $250 per day and penalty cost = $100
per day for each day the project lasts beyond day 14.

Project Activity and Cost Data


Normal Normal Crash Time Crash Immediate
Activity Time (days) Cost ($) (days) Cost ($) Predecessor(s)
A 5 1,000 4 1,200 —
B 5 800 3 2,000 —
C 2 600 1 900 A, B
D 3 1,500 2 2,000 B
E 5 900 3 1,200 C, D
F 2 1,300 1 1,400 E
G 3 900 3 900 E
H 5 500 3 900 G

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 52


Application 2.3
Direct cost and time data for the activities:
Project Activity and Cost Data
Activity Crash Cost/Day Maximum Crash Time (days)
A 200 1
B 600 2
C 300 1
D 500 1
E 150 2
F 100 1
G 0 0
H 200 2

Solution:
Original costs:
Normal Total Costs = $7,500
Total Indirect Costs = $250 per day  21 days = $5,250
Penalty Cost = $100 per day  7 days = $700
Total Project Costs = $13,450
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 53
Application 2.3
Step 1: The critical path is B–D–E–G–H , and the project
duration is 21 days.
Step 2: Activity E on the critical path has the lowest cost of
crashing ($150 per day). Note that activity G cannot be
crashed.
Step 3: Reduce the time (crashing 2 days will reduce the project
duration to 19 days) and re-calculate costs:

Costs Last Trial = $7,500


Crash Cost Added = $150  2 days = $300
Total Indirect Costs = $250 per day  19 days = $4,750
Penalty Cost = $100 per day  5 days = $500
Total Project Cost = $13,050
Note that the cost to crash ($250 per day) is less than
the combined indirect cost and the penalty cost per
day savings ($350).
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 54
Application 2.3
Step 4: Repeat until direct costs greater than savings
(step 2) Activity H on the critical path has the next lowest cost
of crashing ($200 per day).
(step 3) Reduce the time (crashing 2 days will reduce the
project duration to 17 days) and re-calculate costs:

Costs Last Trial = $7,500 + $300 (the added crash costs) = $7,800
Crash Cost Added = $200  2 days = $400
Total Indirect Costs = $250 per day  17 days = $4,250
Penalty Cost = $100 per day  3 days = $300
Total Project Cost = $12,750

Note that the cost to crash ($200 per day) is less than
the combined indirect cost and the penalty cost per
day savings ($350).

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 55


Application 2.3

(step 4) Repeat
(step 2) Activity D on the critical path has the next lowest
crashing cost ($500 per day).
(step 3) Reduce the time (crashing 1 day will reduce the project
duration to 16 days) and re-calculate costs:

Costs Last Trial = $7,800 + $400 (the added crash costs) = $8,200
Crash Cost Added = $500  1 day = $500
Total Indirect Costs = $250 per day  16 days = $4,000
Penalty Cost = $100 per day  2 days = $200
Total Project Cost = $12,900 which is greater than the last trial.
Hence we stop the crashing process.

Note that the cost to crash ($500 per day) is greater


than the combined indirect cost and the penalty cost
per day savings ($350).
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 56
Application 2.3
The summary of the cost analysis follows. The recommended
completion date is day 17 by crashing activity E by 2 days and
activity H by 2 days.
Resulting Project Costs Crash Total Total Total
Crash Critical Reduction Duration Last Cost Indirect Penalty Project
Trial Activity Paths (days) (days) Trial Added Costs Costs Costs

0 — B-D-E-G-H — 21 $7,500 — $5,250 $700 $13,450

1 E B-D-E-G-H 2 19 $7,500 $300 $4,750 $500 $13,050

2 H B-D-E-G-H 2 17 $7,800 $400 $4,250 $300 $12,750

Further reductions will cost more than the savings in indirect


costs and penalties.
The critical path is B – D – E – G – H.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 57


Assessing Risk

 Risk is the measure of the probability and


consequence of not reaching a defined
project goal
 Risk-management plans are developed to
identify key risks and prescribe ways to
circumvent them
 Project risk can be assessed by
 Strategic fit
 Service/product attributes
 Project team capabilities
 Operations

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 58


Simulation and Statistical Analysis

 When uncertainty is present, simulation


can be used to estimate the project
completion time

 Statistical analysis requires three


reasonable estimates of activity times
1. Optimistic time (a)
2. Most likely time (m)
3. Pessimistic time (b)

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 59


Statistical Analysis

Area under curve


between a and b
is 99.74%

a m Mean b
Time
Beta distribution
3σ 3σ
a m b
Mean
Time
Normal distribution
Figure 2.7

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 60


Statistical Analysis

 The mean of the beta distribution can be


estimated by
a + 4m + b
te =
6

 The variance of the beta distribution for


each activity is
2
b–a
σ2 =
6

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 61


Calculating Means and Variances
EXAMPLE 2.4
Suppose that the project team has arrived at the
following time estimates for activity B (site selection
and survey) of the St. John’s Hospital project:
a = 7 weeks, m = 8 weeks, and b = 15 weeks

a. Calculate the expected time and variance for


activity B.
b. Calculate the expected time and variance for
the other activities in the project.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 62


Calculating Means and Variances
SOLUTION
a. The expected time for activity B is

7 + 4(8) + 15 54
te = = = 9 weeks
6 6
Note that the expected time does not equal the most likely
time. These will only be the same only when the most likely
time is equidistant from the optimistic and pessimistic
times.
The variance for activity B is
2 2
15 – 7 8
σ2 = = = 1.78
6 6

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 63


Calculating Means and Variances
b. The following table shows the expected activity times and
variances for this project.

Time Estimates (week) Activity Statistics

Activity Optimistic (a) Most Likely (m) Pessimistic (b) Expected Time (te) Variance (σ2)

A 11 12 13 12 0.11

B 7 8 15 9 1.78

C 5 10 15 10 2.78

D 8 9 16 10 1.78

E 14 25 30 24 7.11

F 6 9 18 10 4.00

G 25 36 41 35 7.11

H 35 40 45 40 2.78

I 10 13 28 15 9.00

J 1 2 15 4 5.44

K 5 6 7 6 0.11

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 64


Application 2.4
Bluebird University: activity for sales training seminar

Most
Immediate Optimistic Likely Pessimistic Expected Variance
Activity Predecessor(s) (a) (m) (b) Time (t) (σ)
A — 5 7 8 6.83 0.25
B — 6 8 12 8.33 1.00
C — 3 4 5 4.00 0.11
D A 11 17 25 17.33 5.44
E B 8 10 12 10.00 0.44
F C, E 3 4 5 4.00 0.11
G D 4 8 9 7.50 0.69
H F 5 7 9 7.00 0.44
I G, H 8 11 17 11.50 2.25
J G 4 4 4 4.00 0.00

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 65


Analyzing Probabilities
 Because the central limit theorem can be applied, the mean
of the distribution is the earliest expected finish time for the
project

TE =
 Expected activity times
on the critical path =
Mean of normal
distribution

 Because the activity times are independent

σ2 =  (Variances of activities on the critical path)

 Using the z-transformation


where
T – TE
z= T = due date for the project
 σ2

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 66


Calculating the Probability
EXAMPLE 2.5
Calculate the probability that St. John’s Hospital will become
operational in 72 weeks, using (a) the critical path and (b) path
A–C–G–J–K.

SOLUTION
a. The critical path B–D–H–J–K has a length of 69 weeks.
From the table in Example 2.4, we obtain the variance of
path B–D–H–J–K: σ2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11. Next,
we calculate the z-value:

72  69 3
z   0.87
11.89 3.45

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 67


Calculating the Probability

Using the Normal Distribution appendix, we go down the left-


hand column to 0.8 and then across to 0.07. This gives a value
of 0.8078. Thus the probability is about 0.81 that the length of
path B–D–H–J–K will be no greater than 72 weeks.
Because this is the
critical path, there is a Length of Normal distribution:
critical path Mean = 69 weeks;
19 percent probability σ = 3.45 weeks
that the project will take
longer than 72 weeks.
Probability of Probability of
meeting the exceeding 72
schedule is weeks is 0.1922
0.8078

69 72
Figure 2.8
Project duration (weeks)

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 68


Calculating the Probability
EXAMPLE 2.5
Calculate the probability that St. John’s Hospital will become
operational in 72 weeks, using (a) the critical path and (b) path
A–C–G–J–K.

SOLUTION
b. From the table in Example 2.4, we determine that the sum
of the expected activity times on path A–C–G–J–K is 67
weeks and that σ2 = 0.11 + 2.78 + 7.11 + 5.44 + 0.11 = 15.55.
The z-value is
72  67 5
z   1.27
15.55 3.94

The probability is about 0.90 that the length of path


A–C–G–J–K will be no greater than 72 weeks.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 69


Application 2.5
The director of the continuing education at Bluebird
University wants to conduct the seminar in 47 working days
from now. What is the probability that everything will be ready
in time?

T = 47 days

TE is: 43.17 days

And the sum of the variances


for the critical activities is: (0.25 + 5.44 + 0.69 + 2.25) = 8.63

The critical path is A–D–G–I,


and the expected completion time is 43.17 days.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 70


Application 2.5

T = 47 days
TE = 43.17 days
And the sum of the variances for the critical activities is: 8.63

T – TE 47 – 43.17 3.83
z= = = = 1.30
 σ2  8.63 2.94

Assuming the normal distribution applies, we use the table


for the normal probability distribution. Given z = 1.30, the
probability that activities A–D–G–I can be completed in 47
days or less is 0.9032.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 71


Near-Critical Paths

 Project duration is a function of the critical


path

 Since activity times vary, paths with nearly


the same length can become critical during
the project

 Project managers can use probability


estimates to analyze the chances of near-
critical paths delaying the project
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 72
Monitoring and Controlling Projects

 Tracking systems collect information on


three topics
 Open issues that require resolution
 Risks that might delay the project completion
 Schedule status periodically monitors slack
time to identify activities that are behind
schedule

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 73


Project Life Cycle

Definition Planning Execution Close out


and
organization
Resource requirements

Start Finish
Figure 2.9 Time
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 74
Monitoring and Controlling Projects

 Problems can be alleviated through


 Resource leveling
 Resource allocation
 Resource acquisition

 Project close out includes writing final


reports, completing remaining
deliverables, and compiling the team’s
recommendations for improving the
project process

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 75


Solved Problem 1

Your company has just received an order from a good


customer for a specially designed electric motor. The contract
states that, starting on the thirteenth day from now, your firm
will experience a penalty of $100 per day until the job is
completed. Indirect project costs amount to $200 per day. The
data on direct costs and activity precedent relationships are
given in Table 2.2.

a. Draw the project network diagram.


b. What completion date would you recommend?

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 76


Solved Problem 1

TABLE 2.2 | ELECTRIC MOTOR PROJECT DATA

Activity Normal Time Normal Cost Crash Time Crash Cost Immediate Predecessor(s)
(days) ($) (days) ($)
A 4 1,000 3 1,300 None

B 7 1,400 4 2,000 None

C 5 2,000 4 2,700 None

D 6 1,200 5 1,400 A

E 3 900 2 1,100 B

F 11 2,500 6 3,750 C

G 4 800 3 1,450 D, E

H 3 300 1 500 F, G

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 77


Solved Problem 1
SOLUTION
a. The network diagram is shown in Figure 2.10. Keep the
following points in mind while constructing a network
diagram.
1. Always have start and finish nodes.
2. Try to avoid crossing paths to keep the diagram simple.
3. Use only one arrow to directly
connect any two nodes.
A D
4. Put the activities with no 4 6
predecessors at the left G Finish
4
and point the arrows
B E H
from left to right. Start 7 3 3
5. Be prepared to revise
the diagram several
times before you come C F
5 11
up with a correct Figure 2.10
and uncluttered diagram.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 78


Solved Problem 1

b. With these activity times, the project will be completed in 19


days and incur a $700 penalty. Using the data in Table 2.2,
you can determine the maximum crash-time reduction and
crash cost per day for each activity. For activity A

Maximum crash time = Normal time – Crash time =


4 days – 3 days = 1 day

Crash cost Crash cost – Normal cost CC – NC


= =
per day Normal time – Crash time NT – CT

$1,300 – $1,000
= = $300
4 days – 3 days

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 79


Solved Problem 1

Activity Crash Cost per Day ($) Maximum Time Reduction (days)

A 300 1
B 200 3
C 700 1
D 200 1
E 200 1
F 250 5
G 650 1
H 100 2

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 80


Solved Problem 1

TABLE 2.3 | PROJECT COST ANALYSIS

Stage Crash Time Resulting Project Project Crash Total Total Total
Activity Reduction Critical Duration Direct Cost Indirect Penalty Project
(days) Path(s) (days) Costs, Added Costs Costs Costs
Last ($) ($) ($) ($)
Trial ($)

0 — — C-F-H 19 10,100 — 3,800 700 14,600

1 H 2 C-F-H 17 10,100 200 3,400 500 14,200

2 F 2 A-D-G-H 15 10,300 500 3,000 300 14,100

B-E-G-H

C-F-H

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 81


Solved Problem 1

Table 2.3 summarizes the analysis and the resultant project


duration and total cost. The critical path is C–F–H at 19 days,
which is the longest path in the network. The cheapest activity
to crash is H which, when combined with reduced penalty
costs, saves $300 per day. Crashing this activity for two days
gives

A–D–G–H: 15 days, B–E–G–H: 15 days, and C–F–H: 17 days

Crash activity F next. This makes all activities critical and no


more crashing should be done as the cost of crashing exceeds
the savings.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 82


Solved Problem 2

An advertising project manager developed the network diagram


in Figure 2.11 for a new advertising campaign. In addition, the
manager gathered the time information for each activity, as
shown in the accompanying table.

a. Calculate the expected time


and variance for each
activity.
D Finish
b. Calculate the activity slacks
A E
and determine the critical
path, using the expected Start C G
activity times. B

c. What is the probability of F


completing the project Figure 2.11
within 23 weeks?

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 83


Solved Problem 2

Time Estimate (weeks)


Activity Optimistic Most Likely Pessimistic Immediate Predecessor(s)

A 1 4 7 —
B 2 6 7 —
C 3 3 6 B
D 6 13 14 A
E 3 6 12 A, C
F 6 8 16 B
G 1 5 6 E, F

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 84


Solved Problem 2
SOLUTION
a. The expected time and variance for each activity are
calculated as follows

a + 4m + b
te =
6

Activity Expected Time (weeks) Variance


A 4.0 1.00
B 5.5 0.69
C 3.5 0.25
D 12.0 1.78
E 6.5 2.25
F 9.0 2.78
G 4.5 0.69

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 85


Solved Problem 2
SOLUTION
b. We need to calculate the earliest start, latest start, earliest
finish, and latest finish times for each activity. Starting with
activities A and B, we proceed from the beginning of the
network and move to the end, calculating the earliest start
and finish times.

Activity Earliest Start (weeks) Earliest Finish (weeks)


A 0 0 + 4.0 = 4.0
B 0 0 + 5.5 = 5.5
C 5.5 5.5 + 3.5 = 9.0
D 4.0 4.0 + 12.0 = 16.0
E 9.0 9.0 + 6.5 = 15.5
F 5.5 5.5 + 9.0 = 14.5
G 15.5 15.5 + 4.5 = 20.0

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 86


Solved Problem 2

Based on expected times, the earliest finish date for the


project is week 20, when activity G has been completed.
Using that as a target date, we can work backward through
the network, calculating the latest start and finish times

Activity Latest Start (weeks) Latest Finish (weeks)


G 15.5 20.0
F 6.5 15.5
E 9.0 15.5
D 8.0 20.0
C 5.5 9.0
B 0.0 5.5
A 4.0 8.0

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 87


Solved Problem 2

4.0 D 16.0
Finish
8.0 12.0 20.0

0.0 A 4.0 9.0 E 15.5


4.0 4.0 8.0 9.0 6.5 15.5

C
Start 5.5 9.0
5.5 3.5 9.0

0.0 B 5.5 15.5 G 20.0


0.0 15.5 4.5 20.0
5.5 5.5
F
5.5 14.5
6.5 9.0 15.5
Figure 2.12

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 88


Solved Problem 2
Start (weeks) Finish (weeks)
Activity Earliest Latest Earliest Latest Slack Critical Path
A 0 4.0 4.0 8.0 4.0 No
B 0 0.0 5.5 5.5 0.0 Yes
C 5.5 5.5 9.0 9.0 0.0 Yes
D 4.0 8.0 16.0 20.0 4.0 No
E 9.0 9.0 15.5 15.5 0.0 Yes
F 5.5 6.5 14.5 15.5 1.0 No
G 15.5 15.5 20.0 20.0 0.0 Yes

Path Total Expected Time (weeks) Total Variance


A–D 4 + 12 = 16 1.00 + 1.78 = 2.78
A–E–G 4 + 6.5 + 4.5 = 15 1.00 + 2.25 + 0.69 = 3.94
B–C–E–G 5.5 + 3.5 + 6.5 + 4.5 = 20 0.69 + 0.25 + 2.25 + 0.69 = 3.88
B–F–G 5.5 + 9 + 4.5 = 19 0.69 + 2.78 + 0.69 = 4.16

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 89


Solved Problem 2

So the critical path is B–C–E–G with a total expected time of


20 weeks. However, path B–F–G is 19 weeks and has a large
variance.

c. We first calculate the z-value:

T – TE 23 – 20
z= = = 1.52
 σ2 3.88

Using the Normal Distribution Appendix, we find the


probability of completing the project in 23 weeks or less
is 0.9357. Because the length of path B–F–G is close to
that of the critical path and has a large variance, it might
well become the critical path during the project

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 90


Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2 – 91

Potrebbero piacerti anche