Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
20.12.2017
Items Nos.
Sl No. Location Junction with
Major Junctions 3
Minor Junctions 25
Manakhelli Starting Point
1
Service Road Nil cross SH - 15 and NH - 65 Junction
Chainage
SL No Lane Configuration Section SH / MDR
From To
Manakhelli cross to Near
1 000+000 17+100 5.5 m (IL) SH- 15
Tumkunta.
2 17+100 17+350 5.5 m (IL) Near Tumkunta to Tumkunta. SH- 15
Continues…
CHAINAGE SUMMARY : PAVEMENT CONDITION
Over all
Condition of Embankment
Chainage pavement
Shoulder Condition Village/
SL No. condition SH / MDR
Town
From To
Left Right Left Right Left Right
(km) (km)
1 0+000 1+000 P P P P F F Manakhelli cross SH-15
2 1+000 1+500 P P P P F F SH-15
3 1+500 2+000 P P P P F F Meenkhera SH-15
4 2+000 3+000 P P P P F F SH-15
5 3+000 4+000 P P P P P P SH-15
6 4+000 5+000 P P P P P P SH-15
7 5+000 6+000 P P P P P P SH-15
8 6+000 6+500 P P P P P P Vittalpur SH-15
9 6+500 7+000 P P P P P P SH-15
10 7+000 8+000 P P P P P P SH-15
11 8+000 9+000 P P P P P P Polakpally cross SH-15
12 9+000 10+000 P P P P P P SH-15
13 10+000 11+000 P P P P P P Changleri SH-15
14 11+000 12+000 P P P P P P SH-15
15 12+000 13+000 P P P P P P SH-15
16 13+000 14+000 P P P P P P SH-15
17 14+000 15+000 P P P P P P Chauki Tanda SH-15
18 15+000 16+000 P P P P P P SH-15
19 16+000 17+000 G G F F F F SH-15
20 17+000 18+000 G G F F F F SH-15
21 18+000 19+000 G G F F F F Tumkunta SH-15 Contd…
Over all Condition
Embankment
Chainage pavement of
Condition Village/
SL No. condition Shoulder SH / MDR
Town
From To
Left Right Left Right Left Right
(km) (km)
22 19+000 20+000 G G F F F F SH-15
23 20+000 21+000 G G F F F F Nagaidlai SH-15
24 21+000 22+000 G G F F F F SH-15
25 22+000 23+000 G G F F F F SH-15
26 23+000 24+000 G G F F F F Kollur SH-15
27 24+000 25+000 P P P P P P SH-15
28 25+000 26+000 P P P P P P SH-15
29 26+000 27+000 P P P P P P SH-15
30 27+000 28+000 P P P P P P SH-15
31 28+000 29+000 ROAD UNDER CONSTRUCTION SH-15
32 29+000 30+000 ROAD UNDER CONSTRUCTION SH-15
33 30+000 31+000 G G G G F F SH-15
34 31+000 32+000 G G G G F F SH-15
35 32+000 33+000 G G G G F F Chincholi SH-15
36 33+000 34+000 G G G G F F SH-15/SH-122
37 34+000 35+000 G G G G F F Chandapur SH-122
38 35+000 36+000 G G F F F F SH-122
39 36+000 37+000 G G F F F F Polakpally SH-122
40 37+000 38+000 G G F F F F SH-122
41 38+000 39+000 G G F F F F SH-122
42 39+000 40+000 G G F F F F Konchavaram Cross SH-122
Contd…
Over all Condition
Embankment
Chainage pavement of
Condition Village/
SL No. condition Shoulder SH / MDR
Town
From To
Left Right Left Right Left Right
(km) (km)
Konchavaram Road & Sedam SH-122/
43 40+000 41+000 G G F F F F
Road crosses MDR
44 41+000 42+000 G G F F F F MDR
45 42+000 43+000 G G F F F F MDR
46 43+000 44+000 G G F F F F MDR
47 44+000 45+000 G G F F F F MDR
48 45+000 46+000 G G F F F F Kallur MDR
49 46+000 47+000 G G F F F F Mariyan MDR
Karnataka Telangan
50 47+000 48+000 G G F F F F MDR
Boarder
Existing Utilities
TYPES Nos.
HT Lines 6
Transformer 5
Photographs
ACCIDENT PRONE AREAS
1 2 3 4 5
CROSS DRAINAGE STRUCTURES
Contd…
Details of Pipe Culverts (45 Nos.)
Sl.No Chainage Diameter of pipe Number of Condition of Formation width
(mm) pipes Pipe culvert (m)
1 75+300 900 1 Poor 10.0
2 76+100 1200 2 Poor 10.0
3 76+300 1200 3 Good 11.50
4 77+100 900 3 Poor 11.40
5 77+250 600 2 Poor 11.50
6 77+550 1800 3 Poor 11.50
7 78+000 600 2 Fair 11.40
8 78+456 600 6 Poor 11.50
9 79+128 900 5 Fair 11.30
10 79+300 900 2 Good 11.50
11 79+500 900 1 Good 11.30
12 80+800 900 1 Good 11.50
13 82+200 900 1 Fair 11.30
14 84+175 900 5 Good 12.00
Contd…
Details of Pipe Culverts (45 Nos.)
Sl.No Chainage Diameter of pipe Number of Condition of Formation width
(mm) pipes Pipe culvert (m)
Contd…
Details of Pipe Culverts (45 Nos.)
Sl.No Chainage Diameter of pipe Number of pipes Condition of Pipe Formation width
(mm) culvert (m)
29 94+460 1200 1 Good 12.00
30 97+830 900 1 Good 12.00
31 98+950 1200 2 Good 12.00
32 99+560 1200 3 Good 11.70
32 100+588 900 2 Poor 19.00 (Canal)
33 101+450 1200 2 Good 11.80
34 104+200 600 1 Good 10.00
35 104+800 900 2 Good 11.00
36 105+300 1200 1 Good 14.00
37 105+800 1200 3 Good 14.00
38 106+300 1200 2 Good 14.00
39 107+000 900 2 Good 14.00
40 110+900 900 2 Good 12.00
41 111+900 1200 1 Good 11.60
Contd…
Details of Pipe Culverts (45 Nos.)
Sl.N Chainage Diameter of pipe Number of Condition of Formation width
o (mm) pipes Pipe culvert (m)
42 112+450 1200 1 Good 12.00
TYPES Nos.
Bridges 13
Slab Culvert 10
Pipe Culvert 45
DISCUSSION ON ALIGNMENT
KMZ file
HORIZONTAL ALIGNMENT
The highway basically follows the alignment of SHs and MDRs upgraded from ODR over the years. Most of
the places the alignment is over curves and bends which will need improvement as per the geometric
requirement of NH Two lane/Four lane specifications. The details of sharp curves which require
improvement is shown below in the Table. In accordance with provisions of clause 2.2 of IRC SP:73-2007,
the existing alignment will be examined and realignment suggested where essential. As can be seen from
the table below, there are a large number of chainages which will require curve improvement. In certain
cases realignment may also be required.
VERTICAL ALIGNMENT
The vertical geometry is an issue of significance. Especially in the ghat section substantial improvement in
the vertical profile will be required. This issue will be clearer once the details of topographical survey are
available. It may be pointed out that the vertical profile appears to confirm to the Stopping Sight Distance
and not the Intermediate sight distances. JMSPL will design the same in accordance with the relevant code
of practise for the vertical alignment once the detailed surveyed data are available. Presently no major
vertical alignment correction reaches are observed.
TYPICAL CROSS-SECTIONS
SHOULDER
SHOULDER
CARRIAGEWAY
CORRIDOR
CORRIDOR
SHOULDER
SHOULDER
EARTHEN
EARTHEN
UTILITIY
UTILITY
PAVED
PAVED
Prop.CL
GRANULAR FILL GRANULAR FILL
ROW
ROW
2 2
1 1
GL GL
1M 1M
(MIN) (MIN)
BITUMINOUS CONCRETE (BC)
UNLINED OPEN DRAIN DENSE BITUMINOUS MACADAM (DBM) UNLINED OPEN DRAIN
SHOULDER
SHOULDER
SHOULDER
CARRIAGEWAY CARRIAGEWAY
CORRIDOR
CORRIDOR
KERB SHYNESS
KERB SHYNESS
500 500
EARTHEN
EARTHEN
UTILITIY
UTILITIY
Prop.CL
PAVED
PAVED
RAILING
ROW
ROW
2 .5% 2 .5% 3%
3%
2 2
1 1
GL GL
1M 1M
(MIN) BITUMINOUS CONCRETE (BC) (MIN)
BITUMINOUS CONCRETE (BC)
UNLINED OPEN DRAIN DENSE BITUMINOUS MACADAM (DBM) DENSE BITUMINOUS MACADAM (DBM) UNLINED OPEN DRAIN
WET MIX MACADAM (WMM)
WET MIX MACADAM (WMM)
GRANULAR SUB BASE (GSB)
GRANULAR SUB BASE (GSB)
SUBGRADE SUBGRADE
SHOULDER
SHOULDER
CUM DRAIN
CARRIAGEWAY
CUM DRAIN
PAVER FLOORING PAVER FLOORING
FOOTPATH
CORRIDOR
FOOTPATH
CORRIDOR
UTILITIY
PAVED
PAVED
UTILITY
PAVER BLOCK PAVER BLOCK
Prop.C
L
ROW
ROW
RAILING RAILING
2 .5% 2 .5% 2 .5% 2.5 %
GL. GL.
RIGHT OF WAY
26500
2000 1750 7000 2500 7000 1750 2000
CUM DRAIN
KERB SHYNESS
KERB SHYNESS
500 500
CORRIDOR
FOOTPATH
CUM DRAIN
1500
UTILITIY
UTILITY
Prop.C
L
L
ROW
ROW
RAILING
RAILING RAILING
2.5 % 2.5 %
2.5 %
2.5 %
GL. GL.
Type of
Sl. No Count No Location Duration Remarks
Surveys
Time Period in
Stage
Activity days from date of Key Date
No.
commencement
3 LA & Clearance I Report
(i) Draft LA & Clearances I Report including Draft
90 2 January 2018
3(A) report
(i) Comments of Client 105 17 January 2018
(i) Final LA & Clearances I Report incorporating
120 22 January 2018
compliance of comments of Client
4 Detailed Project Report
(i) Draft DPR 165 20 March 2018
(i) Comments of Client 195 19 April 2018
(i) Final DPR incorporating compliance of
210 1 May 2018
comments of client
5 Technical Schedules
(i) Draft Technical Schedules 135 15 February 2018
(i) Comments of Client 150 2 March 2018
(i) Final Technical schedule 165 17 March 2018
Clearances II Report
Approval of Project Clearance from concerned
7 agencies e.g. from MOEF; Rly for approval of GAD 240 31 May 2018
and detail engineering drawing of ROB/RUB;
Irrigation Department;
PROJECT OFFICE
Contact Persons: Er. Shivakumar B Yelasangimath, Deputy Team Leader
Address:
Jalavahini Management Services Pvt. Ltd
JMS (p) ltd “Lumbini plot No-187 GDA layout Opp. Ghatage,
Layout Beside Central bus stand
Kalaburgi 585102
Email:jmsplnh@gmail.com
MEETING:
Kick-off meeting had been arranged at EE office, Kalaburagi along with NH sub-
divisional officers and DPR consultant team on 12th September 2017. Accordingly,
MOM had been issued through our vide letter no. 4029 dated 15.09.2017.
Internal meetings with all discipline heads were conducted at our regional office for
the preparation and submission of Inception/Feasibility/Detailed project Report.
WORK PROGRAMME