Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
10/26/2017
EARNED VALUE
SV SCHEDULE VARIANCE CV COST VARIANCE SPI SCHEDULE
PERFORMANCE INDEX
VAC VARIANCE AT
COMPLETION
By Er. NikhilRaj
2
10/26/2017
Definition
Earned value management (EVM) is a methodology that combines scope,
schedule, and resource measurements to assess project performance and
progress.
It is a commonly used method of performance measurement for projects.
It integrates the scope baseline with the cost baseline, along with the
schedule baseline, to form the performance baseline, which helps the
project management team assess and measure project performance and
progress
- PMBOK 5th Edition Pg.217
3
10/26/2017
Why EVM?
Quantify and measure program/contract performance,
Provide an early warning system for deviation from a baseline,
Mitigate risks associated with cost and schedule overruns,
Provide a means to forecast final cost and schedule outcomes
4
10/26/2017
EVM practiced industries
Department of Defense (DoD)
The Federal government
Construction
IT sector
Commercial sector
R&D
Aerospace
5
Example
10/26/2017
PLANNED
Imagine Ms Ann is the project manager of 100 miles road work
She must finish the project in 5 weeks
She can spent $10000/week
1W
2W
3W
4W
5W
2 weeks into the project
ACTUAL
2W
10/26/2017
TOTAL PROJECT BUDGET=$50000
PLAN PLAN PLAN ACTUAL ACTUAL ACTUAL
(TIME) (COST) (%COMPLETE) (TIME) (COST) (%COMPLETE)
W1 $10000 20%
20MILES W1
W2 $20000
PV
40%
40 MILES W2 $15500
AC
35%
35 MILES
W3 $30000 60%
60 MILES W3
W4 $40000 80%
80 MILES W4
W5 $50000
BAC
100%
100 MILES W5
7
VALUE
NAME DEFINITION EQUATION INTERPRETATION
10/26/2017
2nd week
BAC | BUDGETED AT
The value of total planned work, the project cost baseline $50000
VALUES
COMPLETION
FROM
PLAN
PV | PLANNED VALUE
The value of the work planned to be completed to a point in
COST
time, usually the data date, or project completion $20000
EV | EARNED VALUE The planned value of all the work completed (earned) to a
$17500
ACTUAL
VALUES
COST point in time, usually the data date, without reference to actual
FROM
costs
AC | ACTUAL COST The actual cost of all the work completed to a point in time,
usually the data date $15500
The difference between the value of work completed to a point Positive = Under planned cost
CV = EV
CV | COST VARIANCE in time, usually the data date, and the actual costs to the same
AC $2000 Neutral = On planned cost
point in time Negative = Over planned cost
VALUES CALCULATED
USING EQUATION
A measure of the cost efficiency of budgeted resources >1.0 = Under planned cost
CPI | COST
PERFORMANCE INDEX
expressed as the ratio of earned value to actual cost. CPI = EV/AC 1.129 Exactly 1.0 = On planned cost
<1.0 = Over planned cost
8
10/26/2017
Project forecast
ETC= EAC-AC
AC= $15500 =$28786 (money to finish project)
2W
BAC= $50000 (Planned budget)
EAC= $44287 (Forecasted Budget calculated Based On 2nd week actual values)
9
VALUE
NAME DEFINITION EQUATION
10/26/2017
2nd week
If future work will be accomplished at the planned rate, use: EAC = AC + BAC EV $48000
EAC | ESTIMATE AT
FORECASTED VALUES
COMPLETION
If the initial plan is no longer valid, use: EAC = AC + Bottom-up ETC
If both the CPI and SPI influence the remaining work, use EAC = AC + [(BAC EV)/(CPI x SPI)] $48398.899
Assuming work is proceeding on plan, the cost of completing the
ETC | ESTIMATE TO remaining authorized work can be calculated using:
ETC = EAC AC $28786
COMPLETION
Reestimate the remaining work from the bottom up ETC = Reestimate
10
10/26/2017
See Mix
in Action!
https://mix.office.com/watch/1otxpj7hz6kbx
(Copy the link and paste into your browser.
Or, when in a slide show, click the photo.)
11
10/26/2017
Get the add-in
Office Mix