Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Open all cable ends, test cable for IR and continuity and document results
Install LV CBs into existing MCC cubicle and doors
Install the Kirk-key interlock in the switchgear panel
Gland power and control cables in each panel cubicles
Prepare MV power cables, splice cables using appropriate rated splicing kits and test cables
Prepare power and control cables for termination using appropriate heat shrink termination kits
After heat shrinking cables, lug cable ends and do confirmatory tests before terminations.
Tag each power and control cable
Terminate power and control cables using preset torque machine
Ensure proper earth bond/links for each switchgear, remote control, 48VDC and UPS panels
Excavate substation earthing groundbed locations/points
Using appropriate tools, sink substation grounding system and link conductors to all equipment
Carry out earth resistance test for each ground points. Document readings
Using appropriate conducts, make equipotential bond for the station earthing, test and document.
Provide earhing busbar for internal & external equipotential bonding for equipment, panels, doors
Grease all earth link points
Replace existing window AC unit and ensure adequate panel and comfort switchroom cooling
Backfill all cable trenches using with slabs and sharp sand.
Using appropriate test equipment, carryout commissioning of 11kv switchgear which includes
Carryout power & control cable harnessing on the 11kv and control panels
Open all cable ends, test cable for IR and continuity and document results
MAIN GATE ELECTRICAL & INSTRUMENTATION INSTALLATIONS AND COMMISSIONING:
Using appropriate test equipment, carryout commissioning of 11kv switchgear which includes:
Ducter tester (Digital microhm tester), continuity test, HV & LV IR tests, contact resistance test.
Prepare and obtain approval for HV switch procedure for final commissioning of switchgear panel
Using switching procedure carryout energization of all installations
Ensure complete LOTO and confirm isolation of obsollete equipmet prior to decommissioning
Disconnect, cut and remove existing identified MV cable from existing Ring Main Unit (RMU)
Dismantle and remove existing RMU and its structural supports, etc
Dismantle and remove existing cubicle door of existing 400V MCC
Remove existing window-type air conditioning unit
Proper documentations and handover of all decommissioned equipment to client designated area
Carryout proper segregation of waste
Carryout site good house keeping and restore site to operations
MODIFICATION AND COMMISSIONING OF ABB MV SWITCHGEARS AND MIMIC PANEL: