ANALISIS SISMICO

Alumno:
Cristopher Prez Gonzales
Predimensionamiento


1.-LOSA =

LOSA

Distancia Espesor (e)


Losa 1 = 6m 0.25 m
Losa 2 = 5m 0.20 m

2.-VIGA = =

VIGA
V-1 h= 0.70m b=0.35m 35x70
V- 2 h=0.60m b=0.30m 30x60
V- 3 h=0.50m b=0.25m 25x50
3.-COLUMNAS
Zona de alta sismicidad rea mnima = 1000 cm2

Tipo de columnas rea tributaria m2


C-1 36.00
C-2 30.00
C-3 21.00
C-4 18.00
C-5 15.00
C-6 15.00
C-7 10.50
C-8 7.50
Primer Anlisis
Categoria B , P = 125 Kgf/m2
Columnas Centradas C-1 y C-2
/
= = .
. /
43.64cm 45 cm

45x45=2025cm2

/
= = .
. /
39.84cm 40cm

40x40=1600cm2
Columnas Excntricas C-3, C-4, C-5, C-6

/ /
= = . = = .
. / . /
37.80cm 40 cm 31.9cm 35cm
40x40=1600cm2 35x35=1225cm2

/ /.
= = . = = .
. / . /
34.99cm 35cm 31.9cm 35cm
35x35=1225cm2 35x35=1225cm2
Columnas Esquinadas C-7, C-8

/(, )
= = .
. /
30x35=1050cm2

/(.)
= = .
./

30x35=1050cm2
Mtodo de comprobacin
Hcritico=4.30 m
a) Columnas Centradas
a=H/8 = 430/8 = 53.75cm 55 x 55
a) Columnas Excntricas
a=H/9 = 430/9 = 47.78 cm 50 x 50
a) Columnas Esquinadas
a= H/10 = 430/10 = 43 45 x 45
DIRECCION Y - Y
VERIFICACION VIGA COLUMNA
VIGA b(cm) h(cm) I(cm4) COLUMNA b(cm) h(cm) I(cm4) Verificacion
CAMBIO DE V-1 35 70 1000416.67
v-3 25 50 260416.667 C-1 60 65 1373125.00 OK
DIMENSIONES DE 1260833.33
COLUMNAS POR V-3 25 50 260416.6667
V-3 25 50 260416.6667 C-2 65 50 677083.33 OK
ROTULA PLASTICA 520833.33
V-1 35 70 1000416.667 65 60 1170000.00
C-3 OK
>
V-1 35 70 1000416.667
V-3 25 50 260416.67 C-4 60 65 1373125.00 OK
1260833.33
V-3 25 50 260416.6667
V-3 25 50 260416.6667 C-5 55 50 572916.67 OK
520833.33
V-3 25 50 260416.6667 65 50 677083.33
C-6 OK

V-1 35 70 1000416.67 60 60 1080000.00


C-7 OK

V-3 25 50 260416.67 55 50 572916.67


C-8 OK
DIRECCION X - X
VIGA COLUMNA
VIGA b(cm) h(cm) I(cm4) COLUMNA
b(cm) h(cm) I(cm4) Verificacion
V-2 30 60 540000.00
V-2 30 60 540000.00 C-1 65 60 1170000.00 OK
1080000.00 Columnas
V-2 30 60 540000.00
C-1 60x65
V-2 30 60 540000.00 C-2 50 65 1144270.83 OK
1080000.00 C-2 65x50
V-2 30 60 540000.00 C-3 65x60
V-2 30 60 540000.00 C-3 60 65 1373125.00 OK
1080000.00 C-4 55x50
V-2 30 60 540000.00
C-4
65 60 1170000.00
OK
C-5 60x60
V-2 30 60 540000.00 50 55 693229.17
C-5 OK

V-2 30 60 540000.00
V-2 30 60 540000.00 C-6 50 65 1144270.83 OK
1080000.00
V-2 30 60 540000.00 60 60 1080000.00
C-7 OK

V-2 30 60 540000.00 50 55 693229.17


C-8 OK
4. ZAPATAS


.
.

Asumimos Calculo de la Carga de Servicio


= +
> /
Dnde:
. Uso Centro Penitenciario : 400kgf/m2
= /
.Azotea: 100 kg/m
PISO 4

PISO 4 WL
WD
PESO DIMENSIONES
DIMENSIONES USO SC [T/m2] PESO [T]
ESPECFICO AREA m2
ELEMENTO CANTIDAD PESO [T]
ANCHO LARGO ALTURA Techo 0.1 306 30.6
[T/m3]
[m] [m] [m]
Columnas
C-1 4 2.4 0.6 0.65 3.3 12.36
C-2 4 2.4 0.65 0.5 3.3 10.30
C-3 2 2.4 0.65 0.6 3.3 6.18
C-4 2 2.4 0.55 0.5 3.3 4.36 4 = 257.57 + 30.6 = 288.17
C-5 4 2.4 0.6 0.6 3.3 11.40
Vigas
V-1 4 2.4 0.35 6.08 0.7 14.30
V-2 1 2.4 0.3 62.33 0.6 26.93
V-3 4 2.4 0.25 8.68 0.5 10.42
Losa Aligerada
Losa e=20 1 0.3 156.45 46.94
Losa e=25 1 0.35 108.28 37.90
Tabiqueria 1 0.15 306 45.90
Acabados 1 0.1 306 30.60
TOTAL 257.57
PISO 2 y 3

PISO 2,3 WL
WD
PESO DIMENSIONES
DIMENSIONES USO SC [T/m2] PESO [T]
CANTIDA ESPECFICO
ELEMENTO PESO [T] AREA m2
D ANCHO LARGO ALTURA
[T/m3] Centro Penitenciario 0.4 306 122.40
[m] [m] [m]
Columnas
C-1 4 2.4 0.6 0.65 3.3 12.36
C-2 4 2.4 0.65 0.5 3.3 10.30
C-3 2 2.4 0.65 0.6 3.3 6.18
C-4 2 2.4 0.55 0.5 3.3 4.36
C-5 4 2.4 0.6 0.6 3.3 11.40
Vigas
23 = 257.57 + 122.40 = 379.97
V-1 4 2.4 0.35 6.08 0.7 14.30
V-2 1 2.4 0.3 62.33 0.6 26.93
V-3 4 2.4 0.25 8.68 0.5 10.42
Losa Aligerada
Losa e=20 1 0.3 156.45 46.94
Losa e=25 1 0.35 108.28 37.90
Tabiqueria 1 0.15 306 45.90
Acabados 1 0.1 306 30.60
TOTAL 257.57
PISO 1

PISO 1 WL
WD
PESO DIMENSIONES
DIMENSIONES USO SC [T/m2] PESO [T]
ESPECFICO
ELEMENTO CANTIDAD PESO [T] AREA m2
ANCHO LARGO ALTURA
[T/m3] Centro Penitenciario 0.4 306 122.40
[m] [m] [m]
Columnas
C-1 4 2.4 0.6 0.65 4.3 16.10
C-2 4 2.4 0.65 0.5 4.3 13.42 1 = 257.57 + 122.40 = 393.48
C-3 2 2.4 0.65 0.6 4.3 8.05
C-4 2 2.4 0.55 0.5 4.3 5.68
C-5 4 2.4 0.6 0.6 4.3 14.86
Vigas
V-1 4 2.4 0.35 6.08 0.7 14.30
V-2 1 2.4 0.3 62.33 0.6 26.93
V-3 4 2.4 0.25 8.68 0.5 10.42
Losa Aligerada
Losa e=20 1 0.3 156.45 46.94
Losa e=25 1 0.35 108.28 37.90
Tabiqueria 1 0.15 306 45.90
Acabados 1 0.1 306 30.60
TOTAL 271.08
= . + . + .
= .

= . . = rea tributaria
zapata
m2
Z-1(centrada) 36.00
. Z-2(centrada) 30.00
= = . Z-3(excntrica) 21.00

Z-4(excntrica) 18.00
Z-5(excntrica) 15.00
Z-6(excntrica) 15.00
Z-7(esquinada) 10.50
. Z-8(esquinada) 7.50
.
Columnas Dimensiones
Zapata At(m2) Punit K qa(T/m) Az(m2) hz(m) C1-C2
Tipo b h B L
Z-1 36 4.7110 0.9 40 4.711 0.60 C-1 0.6 0.65 0.05 2.15 2.20
Z-2 30 4.7110 0.9 40 3.926 0.60 C-2 0.65 0.5 0.15 2.1 1.90
Z-3 21 4.7110 0.9 40 2.748 0.60 C-3 0.65 0.6 0.05 2.20 1.25
Z-4 18 4.7110 0.9 40 2.356 0.60 C-1 0.6 0.65 0.05 1.20 2.00
Z-5 15 4.7110 0.9 40 1.963 0.60 C-4 0.55 0.5 0.05 1.85 1.10
Z-6 15 4.7110 0.9 40 1.963 0.60 C-2 0.65 0.5 0.15 1.93 1.10
Z-7 10.5 4.7110 0.9 40 1.374 0.60 C-5 0.6 0.6 0 1.20 1.20
Z-8 7.5 4.7110 0.9 40 0.981 0.60 C-4 0.55 0.5 0.05 1.10 1.00
VERIFICACIN POR PUNZONAMIENTO :

= = 2. (1+ + 2+)

= . [ ] =1 /2
1 =

= 2 =

= =

= = 0.075.= v

= = 0.85

,
= , + . . .

= , . . .
Dimensiones Columnas
Zapata At Punit Pu u
B(m) L(m) Tipo b h
Z-1 36 4.7110 169.60 2.15 2.20 35.8556 C-1 0.6 0.65
Z-2 30 4.7110 141.33 2.10 1.90 35.4212 C-2 0.65 0.5
Z-3 21 4.7110 98.93 2.20 1.25 35.9751 C-3 0.65 0.6
Z-4 18 4.7110 84.80 1.20 2.00 35.3327 C-1 0.6 0.65
Z-5 15 4.7110 70.67 1.85 1.1 34.7250 C-4 0.55 0.5
Z-6 15 4.7110 70.67 1.85 1.1 34.7250 C-2 0.65 0.5
Z-7 10.5 4.7110 49.47 1.20 1.2 34.3512 C-5 0.6 0.6
Z-8 7.5 4.7110 35.33 1.10 1.0 32.1206 C-4 0.55 0.5

h(m) d(m) b0(cm) c Vup (TN) Vcp1 Vcp2 Verificacion

0.60 0.525 4.60 0.923 122.20 161.955 103.476 OK


0.60 0.525 4.40 1.300 98.67 123.825 98.977 OK
0.60 0.525 4.60 1.083 51.38 145.373 103.476 OK
0.60 0.525 4.60 0.923 38.09 161.955 103.476 OK
0.60 0.525 4.20 1.100 32.40 131.410 94.478 OK
0.60 0.525 4.40 1.300 28.84 123.825 98.977 OK
0.60 0.525 4.50 1.000 5.99 149.999 101.226 OK
0.60 0.525 4.20 1.100 -0.06 131.410 94.478 OK
CARGA VIVA
PISOS CARGA MUERTA
(CV) [T]
PISO 1 271.8 122.04

PISO 2 257.57 122.04

PISO 3 257.57 122.04

PISO 4 257.57 30.6

TOTAL 1044.51 396.72

= 1441.57
III. CLCULO DEL CENTRO DE MASA FINAL:
a) Hallamos el centro de masa inicial
. .
= =

Elemento Peso Dimensiones
Xi Yi Pi PiXi PiYi
Corte especifico H b h
1 0.00 0.00 2.40 3.30 0.55 0.50 2.18 0.00 0.00
2 6.00 0.00 2.40 3.30 0.65 0.50 2.57 15.44 0.00
3 12.00 0.00 2.40 3.30 0.65 0.50 2.57 30.89 0.00
4 18.00 0.00 2.40 3.30 0.55 0.50 2.18 39.20 0.00
5 0.00 5.00 2.40 3.30 0.55 0.50 2.18 0.00 10.89
6 6.00 5.00 2.40 3.30 0.65 0.50 2.57 15.44 12.87
7 12.00 5.00 2.40 3.30 0.65 0.50 2.57 30.89 12.87
8 18.00 5.00 2.40 3.30 0.55 0.50 2.18 39.20 10.89
9 0.00 10.00 2.40 3.30 0.60 0.65 3.09 0.00 30.89
Xcmi= 9.00m
10 6.00 10.00 2.40 3.30 0.60 0.65 3.09 18.53 30.89 Ycmi= 8.63m
11 12.00 10.00 2.40 3.30 0.60 0.65 3.09 37.07 30.89
12 18.00 10.00 2.40 3.30 0.60 0.65 3.09 55.60 30.89
13 0.00 17.00 2.40 3.30 0.60 0.60 2.85 0.00 48.47
14 6.00 17.00 2.40 3.30 0.65 0.60 3.09 18.53 52.51
15 12.00 17.00 2.40 3.30 0.65 0.60 3.09 37.07 52.51
16 18.00 17.00 2.40 3.30 0.60 0.60 2.85 51.32 48.47
43.24 389.19 373.03
a) Excentricidades Accidentales

= = 0,05.
= = 0,05.

= 0,05. 18,00m = 0.90 m


= 0,05. 17.00m = 0.85m

= . + . = .
= . + . = .