INTRODUCTION
CHAIRMAN
GENERAL
CIVIL ENVIRONMENT
SITE ENGINEER
S.ENGINEER I.T
OUTLINE OF THE PROJECTS WORKED UPON AT ONDO STATE
ASPHALT COMPANY
Road rehabilitation
Drainage construction
Culvert construction
Road construction
Road channelization
DRAINAGE CONSTRUCTION
When it rains, some water naturally seeps into the ground. The rest makes
its way through drainage systems, into rivers and creeks and eventually
into the bays, or directly to the bays through storm water beach outlets.
The drainage system is an essential part of living in a city or urban area, as
it reduces flood damage by carrying water away.
The removal of this excess water is known as drainage system
Steps in drainage construction :-
Level taking
excavation of trenches
Blinding
Preparation of reinforcement
Concrete base
Form work
concrete casting
Level taking:-This is the process by which the ground of different
elevation is measured to cut or fill.
Rock is any form of soil. However, their sizes differ from a form to another and
whenever a big rock is expected to be excavated, it is advised to blast the rock.
Blasting of rock involves the following processes;
Drilling
Inserting dynamite into the hole
Threading
Ignition
STAGES IN BLASTING OF ROCK
EXPERIENCE GAINED
CONCLUSION
In line with the objectives of the Students Industrial Work Experience
scheme (SIWES) the Industrial Training experience has been very insightful
and interesting and has helped in witnessing the industry-based application of
known theoretical laws and principles taught in school. The training has also
done its part in educating me on interpersonal relationship with co-workers and
the values enjoyed in working as a team.
RECOMMENDATIONS