GLAST LAT Project September 15, 2006: Pre-Shipment Review

GLAST Large Area Telescope

Gamma-ray Large
Area Space
Telescope LAT Pre-Shipment Review

EMI/EMC

Michael Lovellette, Test Director


Naval Research Lab

EMI/EMC 1
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

EMI/EMC The Bottom Line


No emissions excesses found in any LAT system level test, CE or RE

One susceptibility found


Tracker occupancy specification of <10-4 violated at ~100 MHz
vertical polarization in RS
Nothing on the vehicle radiates in this frequency band
Also unlikely for external radiation
Not considered a problem, waiver submitted

EMI report in preparation, LAT-TD08585-01

EMI/EMC 2
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Purpose / Contents

Demonstrate LAT complies with all EMI/EMC requirements:


Conducted and radiated emissions below required levels
LAT does not exhibit susceptibilities when exposed to
conducted or radiated energy at required levels
Test Categories
Conducted emissions (CE)
Radiated emissions (RE)
Conducted susceptibility (CS)
Radiated susceptibility (RS)
Requirements flowdown
Mission System Spec 433-SPEC-0005
LAT Environmental Requirements Spec LAT-SS-00778
LAT Performance Verification Plan LAT-MD-00408-04c
EMI Test Plan LAT-MD-02726-02

EMI/EMC 3
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Subsystem EMI/EMC Test Summary


RE101 RE102 CE101 CECM CS102 CS06 RS101 RS103 St. Mag
TKR
ProtoFlight X X X X X X X X X 0
Flight (Acpt) X X 0

CAL
ProtoFlight X X X X X X X X X 0
Flight (Acpt) X X 0

ACD
Qual BEA X X X X X X X X X
ProtoFlight (a)

T&DF
Qual X X X X X X X X X 3(b)
Flight (Acpt) X X 0

Mech (Radiators)
ProtoFlight X (c )

(a) ACD Subsystem EMI testing Waivered - LAT-XR-06733


(b) Qual TEM/TPS, GASU exceeded radiated emissions spec (RE102) in S band, GPS notch;
HCB exceeded CECM spec - Waiver approved, CCR 433-0374
(c ) Radiator subsystem test of VCHP heater power source deferred to LAT level configuration

EMI/EMC 4
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Radiator Subsystem EMI/EMC Test


VCHP heater Radiated Emissions testing
S/C power source for LAT VCHP heaters is an unfiltered DC-
DC converter.
Concern is the conducted noise for this power source will
become radiated emission issue for LAT system test.
This issue shall be resolved by special subsystem (Radiator)
test RE102 using simulated S/C power source.
The test was performed just prior to LAT RE102 test.

Not formally part of the LAT level EMI test, performed on an STR

EMI/EMC 5
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

LAT EMI Test


LAT test levels derived from LAT-SS-0778
Test Suite:
CE102 Conducted Emissions, Power Leads, 10 kHz to 10 MHz, MIL-STD-462,
CE03
CECM & CEDM* Conducted Emissions, Time Domain, 150 MHz Bandwidth
CS102 Conducted Susceptibility, Power Leads, 10 kHz to 10 MHz, MIL-STD-
462, CS02
CSCM Conducted Susceptibility, Common Mode, 30 Hz to 150 MHz, MIL-STD-
462, CS02
CS06 Conducted Susceptibility, Spike, Power Leads, MIL-STD-462
RE101 Radiated Emissions, Magnetic Field, 20 Hz to 50 kHz
RE102 Radiated Emissions, Electric Field, 10 kHz to 18 GHz, MIL-STD-461E
RS101 Radiated Susceptibility, Magnetic Field, 20 Hz to 50 kHz
RS103 Radiated Susceptibility, Electric Field, 30 MHz to 18 GHz
Verify by Analysis:
RS103 Radiated Susceptibility, Electric Field, 18 GHz to 40 GHz
Static Magnetic Field

* Not required but we did it anyway

EMI/EMC 6
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

LAT Power Interfaces


SC-LAT Power Interfaces
SC PRU (P) - LAT DAQ
SC PRU (R) - LAT DAQ
SC PRU (P) - LAT SIU (P)
SC PRU (R) - LAT SIU (R)
SC PRU (P) - LAT VCHP +Y Heaters
SC PRU (P) - LAT VCHP Y Heaters
SC PRU (R) - LAT VCHP +Y Heaters
SC PRU (R) - LAT VCHP Y Heaters
SC PDU (P) - LAT Makeup Heaters (Survival)
SC PDU (R) - LAT Makeup Heaters (Survival)

Makeup circuit power interfaces are not tested.


VCHP heater testing limited to RE102
EMI/EMC 7
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Test Limitations
RS103 upper limit of 18GHz (40GHz)
18 40 GHz addressed by analysis.

Limited area of RS101 test


Requires scanning each 10cm x 10cm area, ~16min/scan
~1450 scans for the LAT, another ~1200 for the radiators (~29 days)
Scan selected locations around connectors, PMTs, BEA

Redundant side testing limited to Conducted Emissions (CE102) and


Conducted Susceptibility (CS102)

EMI/EMC 8
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

As Run Test Sequence


12 June - High Bay 22 June
CE102 DAQ hot & ret redundant bus CSCM DAQ primary bus
CE102 SIU hot & ret redundant bus CSCM SIU primary bus
13 June CS06 DAQ primary bus
CS 102 DAQ ret redundant bus
CS06 SIU primary bus
CS102 SIU hot & ret redundant bus
CS102 DAQ primary bus
15 June - Anechoic Chamber
RE 102 calibration CS102 SIU primary bus
RE102 Test 23 June
16 June CS06 SIU primary bus
RE102 continued CS102 DAQ primary bus
17 June CS102 SIU primary bus
RS103 24 June
19 June CS102 DAQ redundant bus
RS103 continued CE102 DAQ primary bus
20 June CE102 SIU primary bus
RS103
CECM SIU primary bus
RE101
CEDM SIU primary bus
RS103 retest
21 June CS06 retest
RS103 retest CECM DAQ primary bus
RS101 RS101 retest
10 July - High Bay
EMI/EMC CS102 retest DAQ & SIU primary bus 9
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Deviations from EMI Test Plan


UHF Notch shown in Figure 36 not included in RE102 requirement
Table 6 Gives correct notches

CS102 pulse level 10 V as indicated in text, not 20V as shown in Figures 27 and
30.

CEDM test not required


We did it anyway

During initial RE testing some radiator connectors not connected


No change noted once they were connected

During redundant side CS test 150kHz to 10MHz signal injection was lead was
inadvertently connected to a thermistor lead
Incorrect lead stripped for access
Thermistor passed CS testing with flying colors
Test successfully repeated during primary side CS testing using correct pin
number

EMI/EMC 10
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Deviations from EMI Test Plan - CS102


Impossible to locate current probe
between injection point and LAT
connector due to the twisted pair type
wiring
Current probe was located at LSC
Reduced current feedback sensitivity
Pre calibrated current limits used

Chamber
Bulkhead RF
Generator

Attenuator

RF
Amp Spectrum
Analyzer
100 H
(if necessary)
Attenuator

(+) LAT-SIU
LSC Interface
VSC 5 cm
(-)
In Out

EMI/EMC 11
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

LAT Grounding

Before Radiated Testing the LAT was positioned on


copper sheets and all grounds were connected with 18
Cu sheets

EMI/EMC 12
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Radiator EMI Test


The radiator was
connected to the special
power supply

The first run showed power


supply harmonics over the
limit

EMI/EMC 13
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

So We Shielded the Power Supply

EMI/EMC 14
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Conducted Emissions
All conducted
emissions tests passed
comfortably
Representative plot
shown here.

EMI/EMC 15
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Conducted Susceptibility
The only susceptibilities detected during conducted testing
were additional noise on RTD temperature measurements
This imposed 2 or 3 degrees noise on the temperature
readout
Some of the readouts affected were VCHP reservoir
temperatures used by the thermal control software
Does not violate any requirements, but worth noting for
thermal control software design

This additional noise can be accommodated by a modification to


the digital filter in the thermal control system
D. Wood has modified filter and tested against noise data
taken during EMI CS test

EMI/EMC 16
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Conducted Susceptibility

EMI/EMC 17
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

CECM, CSCM, CS06


All LAT system tests nominal

There was an exceedence during subsystem CECM test on the


heater control box (HCB) VCHP reservoir heater feed.
No retest performed at system level
Waiver approved by project office, CCR 433-0374

EMI/EMC 18
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Radiated Emissions
All radiated emissions, RE101 & RE102, were below required
levels

All broad band was well below the limit

SGLS notch also passed easily

GPS notch required some additional shielding of test harnesses,


connectors and connector savers to get below limits

EMI/EMC 19
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Radiated Emissions - SGLS Notch

EMI/EMC 20
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Radiated Emissions - GPS Notch Hor.

EMI/EMC 21
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Radiated Emissions - GPS Notch Vert.

EMI/EMC 22
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Radiated Susceptibility - RS103


RS103 Test sweeps
were performed and
data analysis
performed off line

ACD, CAL and TKR


performance verified

EMI/EMC 23
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Radiated Susceptibility - RS101


RS101 tested
limited
locations

Connectors
Tracker

EMI/EMC 24
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Radiated Susceptibilities
LAT exhibited increased tracker occupancy at ~33, 66, & 99 MHz
during testing with vertical polarization
Effect noted during post test processing
Only the 99 MHz frequency violated tracker occupancy
requirement of < 10-4

There are no sources of EM radiation on the S/V at these


frequencies and the frequency is below most external sources

Considered not to be a problem

Waiver submitted to project office

EMI/EMC 25
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Radiated Susceptibility - TKR

EMI/EMC 26
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review

Personnel
EMI/EMC Test Director - Michael Lovellette
EMI/EMC Facility Operations
Mike Obara - Test Conductor
Tony Gray - Test Conductor

LAT Instrument Operations


Brian Grist Operations Lead
Standard LAT I&T Operators and Online analysis support
Anders Borgland Offline instrument analysis lead
Elliott Bloom LAT181 analysis lead

EMI/EMC 27