Gamma-ray Large
Area Space
Telescope LAT Pre-Shipment Review
EMI/EMC
EMI/EMC 1
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
EMI/EMC 2
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
Purpose / Contents
EMI/EMC 3
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
CAL
ProtoFlight X X X X X X X X X 0
Flight (Acpt) X X 0
ACD
Qual BEA X X X X X X X X X
ProtoFlight (a)
T&DF
Qual X X X X X X X X X 3(b)
Flight (Acpt) X X 0
Mech (Radiators)
ProtoFlight X (c )
EMI/EMC 4
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
Not formally part of the LAT level EMI test, performed on an STR
EMI/EMC 5
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
EMI/EMC 6
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
Test Limitations
RS103 upper limit of 18GHz (40GHz)
18 40 GHz addressed by analysis.
EMI/EMC 8
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
CS102 pulse level 10 V as indicated in text, not 20V as shown in Figures 27 and
30.
During redundant side CS test 150kHz to 10MHz signal injection was lead was
inadvertently connected to a thermistor lead
Incorrect lead stripped for access
Thermistor passed CS testing with flying colors
Test successfully repeated during primary side CS testing using correct pin
number
EMI/EMC 10
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
Chamber
Bulkhead RF
Generator
Attenuator
RF
Amp Spectrum
Analyzer
100 H
(if necessary)
Attenuator
(+) LAT-SIU
LSC Interface
VSC 5 cm
(-)
In Out
EMI/EMC 11
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
LAT Grounding
EMI/EMC 12
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
EMI/EMC 13
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
EMI/EMC 14
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
Conducted Emissions
All conducted
emissions tests passed
comfortably
Representative plot
shown here.
EMI/EMC 15
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
Conducted Susceptibility
The only susceptibilities detected during conducted testing
were additional noise on RTD temperature measurements
This imposed 2 or 3 degrees noise on the temperature
readout
Some of the readouts affected were VCHP reservoir
temperatures used by the thermal control software
Does not violate any requirements, but worth noting for
thermal control software design
EMI/EMC 16
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
Conducted Susceptibility
EMI/EMC 17
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
EMI/EMC 18
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
Radiated Emissions
All radiated emissions, RE101 & RE102, were below required
levels
EMI/EMC 19
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
EMI/EMC 20
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
EMI/EMC 21
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
EMI/EMC 22
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
EMI/EMC 23
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
Connectors
Tracker
EMI/EMC 24
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
Radiated Susceptibilities
LAT exhibited increased tracker occupancy at ~33, 66, & 99 MHz
during testing with vertical polarization
Effect noted during post test processing
Only the 99 MHz frequency violated tracker occupancy
requirement of < 10-4
EMI/EMC 25
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
EMI/EMC 26
Presentation 7 of 12
GLAST LAT Project September 15, 2006: Pre-Shipment Review
Personnel
EMI/EMC Test Director - Michael Lovellette
EMI/EMC Facility Operations
Mike Obara - Test Conductor
Tony Gray - Test Conductor
EMI/EMC 27
Presentation 7 of 12