Sei sulla pagina 1di 42

Unit III

Life-Cycle Phases

1
Introduction

we need BALANCE between research and


development (R&D) and production activities
Need some kind of balance between:
Concentrating on capturing and modeling
functionality and
Building a robust product that has the performance,
reliability, and scalability customers desire.

2
Further, we need a process that supports this
balance.

Need a process to help balance:


Planning, capturing, and modeling requirements and
establishing a baseline architecture,
with
Continuous assessment, measuring risk, and testing to
ensure progress and quality
with
Evolution and verification of the applications functionality
through series of customer demonstrations and ultimate
validation.
3
Engineering and Production Stages
To achieve the ROI for software development, we
need to use a manufacturing process that is
characterized by the

highest utilization of automated development tools


and

use of component-based approaches to


development.

4
Engineering and Production Stages

Engineering and Production

Engineering work: This centers on risk reduction,


prototyping, establishing architectural baseline,
assessment, analysis, design, and planning

Production work: programming and unit test, system


and integration testing, demonstrations, assessment,
base-lining (alpha, beta, ) configuration, and
releases; operations

5
Two Stages: Far Too Abstract
a life cycle of two stages is far too abstract to track the many detailed activities all with
actors, activities, and artifacts.
Map RUP Phases into these more comprehensive phases.
Enter: Engineering Phase = Inception and Elaboration
Enter: Production Phase = Construction and Transition

Engineering, i.e., Inception and Elaboration, focuses on the concept (idea) of the
application and its architectural components (analysis and preliminary design
perhaps a wee bit of detailed design)
Artifacts are established and base-lined; (Configurations)

Production, i.e., Construction and Transition, focuses on programming, testing,


releases and converting / establishing operational capabilities
Implies that artifacts from earlier stage (engineering) more difficult to change
as activities more downstream activities occur

6
Royce Claims that:
These phases can be mapped into the famous Spiral
Model for Software Development
developed by (Barry Boehm) (shall see ahead)
Now have:
Conventional Software Development Model (as represented by
the Waterfall Model and its many variants;
OOSE approach (as represented by the RUP);

7
Spiral Model - Overview
Spiral Model is another incremental model.
well known for these
prototyping,
iterative software development, and
risk assessment.
Model is graphed like a spiral.
Development can be halted at the end of any cycle
depending on evaluation of previous cycle.
IS ROI still looking good?
Are expended costs in line with anticipated costs so far?
Have risks been mitigated?
Functionality delivered evolving properly via high priority
requirements? And much more..

8
Spiral Model
Very much a Risks-Driven Approach
Different idea of software development.
How does this project affect the developers
and the clients?
How does each step in the project affect
its overall development?
Not used in previous development models.
They were usually code-driven or document-driven.

9
Previous Software Process Models
An evolution of models
Code & Fix
Stagewise & Waterfall
Evolutionary Development
Others

Code & Fix


First, elementary model
Write code now; fix it later
No planning involved
Problems:
Code is poorly structured.
The software developed was usually a poor match for users
needs.

10
Stagewise & Waterfall
Born out of the shortsightedness of the Code & Fix
model.
- need for a design phase, requirements phase,
and a testing phase.

First used to develop SAGE (Semi-Automated


Ground Environment), an early warning system for
the Cold War era.

11
Stagewise
A development process of successive phases.
Phases included operational plan, operational
specs, coding specs, coding, parameter
testing, assembly testing, shakedown, system
evaluation.
Underwent two refinements in 1970.
Now referred to as the Waterfall Model.

12
Waterfall Model
Introduced:
Feedback loops across multiple stages: Validation and
verification steps.
Prototyping via a build it twice step alongside of
requirements and design.

Difficulties exposed even as revisions were made to


the model.
Required elaborated documents. (Document- driven;
lengthy development cycles, etc.
Led to pursuing stages of development in the wrong
order

13
14
Evolutionary Development
Evolution of the system in directions based on
experience.
Provides rapid initial operational capability.
I cant tell you what I want, but Ill know it when I see it.
Flexible, yet uncertain approach.

Evolutionary Development Problems:


No formal design phase (same problem as Code & Fix).
One bad assumption the unplanned paths will be
compatible.
Hard-to-change code resulted.
Many problems when new software was incrementally
replacing old software 15
16
17
Spiral Model - Overview
In the Spiral Model, prototyping, evaluation, planning, and all engineering and
production activities are executed in different quadrants. (Different variations of the
model)

But the basic notion of iteration is very firmly established.

For each cycle:


risk is assessed,
more design and development is undertaken,
the work products and evaluated, and
planning for the next cycle in the spiral is undertaken;
Iterate..

Please note that in reality, the Spiral Model curve is actually


skewed to the right, as the spirals do not carve out equal areas.

Area in each cycle is a determinant of effort and cost.


18
Spiral Model - Overview
Quadrants in a cycle:
Creation of a prototype as a means to gather and lock in
requirements; gain customer buy-in.
Risk is assessed and if acceptable,
Development activities then follow using the waterfall model
Specifications are created from the prototyping effort,
Then Requirements, Analysis, Design, Implementation,
ensue
Review and release are undertaken

Restart and iterate as above


Planning for next iteration is undertaken or not
Iterate until application is developed fully and totally
released to the clients.

19
Spiral Model - more
May be several cycles of prototypingbut as prototypes evolve,
these may become official releases of the product (internal or
external).
Before a cycle ends, the review discusses experiences, assesses
risk, and decision made whether or not to proceed.

Note: for each cycle, FIRST thing before embarking is to decide


what are the major requirements to be handled.
Adjust the architecture and requirements and/or project plan as
needed.

The Spiral forms the basis for entire life cycle of the product.
Thus, the Spiral Model continues the spiral process for
Maintenance, and the model continues until the application is
ultimately retired or replaced
20
Spiral Model and the RUP Phases
R & D Stage Production Stage

Inception Elaboration Construction Transition

Idea Architecture Beta Releases Products

Prototypes Change managed baselines


Coarse artifacts Elaborate artifacts
Major risk items Low Risk Items
Creative, judgment Engineering, reasoned
Business Rules Well-instrumented processes
Stakeholder Vision Skewness:21
Back to our Process Model (RUP)
Lets look more closely at the phases for our process model:
Inception
Elaboration
Construction
Transition
Each phase has
primary objectives,
essential activities, and
primary evaluation criteria
to judge its success at milestone time.
Since the process that is underpinning our management of
software processes and personnel course is the RUP, it is
imperative that we understand this management process,
the RUP, as much as possible
22
Inception Phase (1 of 3)
Overriding Goal: achieve concurrence among
stakeholders on life-cycle objectives for the project
Primary Objectives: (by end of phase)
Establish project software scope and boundary conditions
Includes operational concept, acceptance criteria, and a clear
understanding of what is and what is not intended in the product
Identify critical use cases (core functionalities) of system and
the primary scenarios that will drive the activities
Demonstrate at least one candidate architecture against some
of the primary scenarios (walk through it)
Estimate the cost and schedule for the entire project (including
detailed estimates for the elaboration phase)
Estimate potential risks (sources of unpredictability)
Know These!
23
Inception Phase (2 of 3)
Essential Activities
Develop Project Scope
Capture requirements and concept of operations repository
Describes users view of the requirements
Repository contains information used to define problem space
Repository must contain information to capture acceptance criteria
Develop a Candidate Architecture and Demonstrate it
Repository contains enough information to demonstrate at least a single
candidate architecture
This might be at a very high level, such as deployment level;
A general layered architecture may also be demonstrated.
But considerable Requirements have not yet been done and almost NO
Analysis and Design have been undertaken.
Repository must include enough data to support make/buy decisions so
that cost, schedule, resources can be costed out.
Planning and Preparing the Business Case
Risk management strategies, staffing, general iteration plans,
cost/schedule/profitability tradeoffs are all evaluated.
Environmental (Infrastructure) support is defined.
ROI, market share, etc.
24
Inception Phase (3 of 3)
Primary Evaluation Criteria
Stakeholder concurrence on scope definition and
cost/schedule estimates?
Do critical use cases demonstrate that the requirements
are understood?
Do we have credible estimates for
cost/schedule/resources/risks/development?
Does the architectural prototype support previous items?
(Does the prototype indicate that the scope of project is
understood, and does the development group indicate
prevalent understanding?)
Are actual expenditures verses planned expenditures
acceptable? <<end inception>
25
Elaboration Phase (1 of 5)
Clearly the most important phase! Overriding goals are
several, varied, and critical!
At end of phase:
engineering is complete,
almost all use cases are designed (certainly all critical use cases and flows),
a prototype for gathering requirements and to demonstrate proof of
concept is accommodated, and
an analysis model is constructed, and
a baseline executable architecture is established and demonstrated.

Risks have to have been addressed and strategies understood;


Business Rules have been subscribed to closely;
Cost and schedule are acceptable and predictable and updated, if necessary,
Stakeholder acceptance is achieved (the vision is realized in the artifacts), etc.
and
We have stability
We want to graduate from a low-cost effort into a full-blown production
process, where costs are maxed and personnel are on staff.

26
Elaboration Phase (2 of 5)
Primary Objectives (at end of phase)
Base-lining the architecture asap (establishing
configuration management proceduresfor tracking
all artifacts!
Base-lining the Vision. It is now solid and
accommodated in the artifacts so far.
Base-lining a detailed plan for Construction
Demonstrating the baseline architecture such that it
clearly supports the vision at, of course, reasonable
cost in reasonably time.
27
Elaboration Phase (3 of 5)
Essential Activities
Detail the Vision.
Ensure all have this shared functional vision and that this is
reflected in the Use Cases that will drive the architecture and
planning.
Discuss: What does this mean to you??? Explain!
Detail the process (to come) and the infrastructure
support.
Must be spelled out; the plans for each iteration in Construction
(project management supporting discipline) and the anticipated
assessment at the end of each iteration, the functionality
accommodated by each iteration must be spelled out in general.
Detailed iteration planning (after first iteration or two) will come
later. But overview planning is now!
Discuss: What does this mean? Explain!

28
Elaboration Phase (4 of 5)
Essential Activities continued
Build the Architecture
Group classes into packages; subsystems; consider existing
executable components that may be reusable e.g. GUI
Components (commonly available); can you reverse engineer
existing components? (Should you seek to buy components?
Contract for them? Develop them?)
But you MUST integrate these into architectural units (layers,
packages, subsystems, all with dependencies, well-defined
interfaces, )
Bounce your candidate architecture against your primary scenarios
to trace that all functionality is accommodated by these artifacts.
May result in a number of design choices and changes in model
elements (e.g. classes, responsibilities)
May point out some requirements missing
Remember, requirements are singular; but there is not a
single, perfect design.
29
Elaboration Phase (5 of 5)
Primary Evaluation Criteria
Remember, at the end of Elaboration Phase we have the LCA
Life Cycle Architecture Milestone. So,
Is the Vision solid? Stable?
Is the architecture stable? Demonstratable?
Execute example of addressing a high risk scenario?
Does the architecture indicated that all risk elements have been
addressed/mitigated?
Have we looked carefully into Construction and established sufficient
planning detail to project credibility in our estimates? (initial
iteration one or two carefully planned?)
Do we have stakeholder buy-in that their vision can be
accommodated if we proceed as plans indicate?
Are actual resource expenditures verses planned resource
expenditures acceptable so far? 30
Construction Phase (1 of 5)
Great mindset change: now interested in producing a
deployable product! (implementation)
iterate, iterate, integrate/assess/plan as we go.
No longer engineering; rather, production!!!

Need to manage resources, control operations to


optimize costs, schedules, and quality.
Emphasis on the development of intellectual property
shifts to the reality of usable products.

31
Construction Phase (2 of 5)
One very nice attribute in Construction:
Parallel development
Based on architecturedo homework up front!!!!
Accelerates delivery of deployable releases
Downside: complicates project management and
synchronization of teams, integration, and workflow.
Architecture will drive this
A good architecture will support parallel development
Emphasized during Elaboration planning for
Construction.

32
Construction Phase (3 of 5)
Primary Objectives
Develop the system rapidly but with high
quality that is, construction (programming and
unit testing) implements the design; realize the
design
Take advantage of the process, versioning,
reviews, assessment, etc. to minimize costs due to
needless rework and scrap.
Develop alpha, beta, or what have you releases
for Transition phase.

33
Construction Phase (4 of 5)
Essential Activities
Manage resources; control development (via
plans, configuration management, change
management, );
Perform unit testing (component testing) against
requirements (verification)
Assess releases against acceptance criteria cited in
vision. (validation)
V&V Discuss.

34
Construction Phase (5 of 5)
Primary Evaluation Criteria (at end)
Milestone is Initial Operational Capability (IOC)
Is the product reliable enough for deployment?
Does not mean everything must be perfectShowstoppers?
Does it fail frequently??
Is product stable enough for deployment?
Pending changes are okay
But are we getting change requests a-plenty?
Are defects being identified rapidly as we speak?
How significant are the changes??
Is the stakeholder community ready to transition?
Are actual expenditures reasonably close to planned
expenditures?
35
Transition Phase
Recall end of phase milestone: product release to user
domain.
Implies product is stable, has high quality, has accompanying
user documentation (on-site or web-based training), customer
support is ready, etc...
Phase could include any of these
Beta testing to validate new system against expectations
Beta testing in parallel with legacy system to be replaced
Installation
Conversion of operational data bases
Training users, maintenance team, customer support

36
Transition Phase
Phase concludes when the baseline realizes the
original vision and we are ready to put it in the users
hands.
Might be end of project development or starting
point for next cycle, or starting point for next version
of deployable version...
Might be forwarding whole shooting match over to
the maintenance group or
third party for future work

37
Transition Phase
Transition is not uncomplicated
May involve several iterations including
Beta1, beta2, testing and levels of releases (all releases
may not be equal)
Custom software?
Conversion software?
Development of user documentation,
User training, especially in initial use of product
Web-X; on developers site; on clients site.
Who pays for what? How does this work? Millions!!!
Usability problems and tuning,

38
Transition Phase
Essential Activities
Synchronization and integration of concurrent construction
increments into consistent deployable baselines ensure
all flows
Installation / Conversion
Cut over (complete switch to new application)
Run in parallel, or
Phased
Assessment against vision and acceptance criteria.
Evaluation Criteria
Is user satisfied?
Are actual expenditures reasonably close to planned
expenditures?

39
Summary - Know These
Recognize each phase has one or more iterations
Phases end with major milestones; (Know these!)
Iterations within phases have minor milestones.
Each have deliverable(s) and undergoes assessment
against criteria
Each iteration entails a sequence of activities that
culminate in a minor milestones or major milestones (if
iteration ends phase)
Scope and results of iterations are captured via artifacts
produced.

40
Summary (continued) Know!
Major Milestones (phase end):
Approved by stakeholders
Map to significant management/business decisions rather than to
completion of a specific software development activity.
Minor milestones (iteration end):
Approved internally and
Realized by artifacts / new versions of artifacts in repository;
internal synchronization,
internal assessment,
Additional planning take place
Executable releases (not necessary deployable)

41
Lessons Learned Organizational Change
Middle management is where the war is won
Championed by respected leaders who own the plan and
execution.
Project Management: Can be immense pressures from above (Sr.
Management) and different sets of problems/issues from below
(actual developers)
ROI on first implementation
Disruption costs must be absorbable in the benefit
Implemented on business critical project
This is where the A-players are
Success breeds success (like the NFL)
First increment needs to be ambitious, but realistic
Results drive incentives
Such as: milestone demonstrations, release timeliness, release
content, etc
Not: processes, methods, expended energy, reuse, audits,
meetings, subjective assessments, document production,
42

Potrebbero piacerti anche