Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
A D
C
PERT :
This method uses three time estimates : Optimistic
time, Most likely time and Pessimistic time.
Optimistic time (a): This is the shortest time for
completing an activity.
Most likely time (m): This refers to the time that
is expected to occur, if the activities are repeated
under exactly the same condition.
PERT & CPM
Beta curve
Probability
a m tei b
Time duration of activity
PERT & CPM
The
three time estimates are reduced into a
single expected time (tei ) which can be computed
using following formula :
tei = where
tei = Expected time of the ith activity
a = Optimistic time
m = Most likely time
b = Pessimistic time
The standard deviation, i of the completion time
of an activity is calculated as follows :
i =
The variance = = ()2
PERT & CPM
EF LF
4 4
EF LF 3
9
C=1 9
EF LF A=2 7 EF LF
0
7 E=3 5
0
t=0 F=2
4
1
B=4 D=2
2
EF LF
4 4
EF = ES + t Slack = LS - ES
LF = LS + t Slack = LF EF
PERT & CPM
0 1 2 3 4 5 6 7 8 9
A C
B D
E
F
DAY ACTIVITY REQUIREMENT OF MONEY
1 A +B 50 + 50 = 100
2 A+B 50 + 50 = 100
3 B +C 50 + 40 = 90
4 B 50
5 D+E 100 + 100 = 200
6 D+E 100 + 100 = 200
7 E 100
8 F 60
9 F 60
PERT & CPM
EF LF EF LF
28 36
28 36
EF LF
C,7 F,8
EF LF
21 38
21 38
G,
A,21 2
E,
5
33
D, 36
B,5 EF
2
LF 26 28
26 28
EF LF EF LF
PERT & CPM
Activity a b m Expected
Activity
Completion
Time
Te =(a + 4m +
b)/6
A 10 12 28 22.33
B 4 4 10 8
C 4 6 14 11
D 1 2 3 2.5
E 1 5 9 7
F 7 8 9 8.16
G
Completion2time of 2Critical path
2 A C 2 F G =
22.33+11+8.16+2 Expected project
completion time =
= 43.49
PERT & CPM
= 43.49 weeks
Completion of critical path A B D F G =
22.33+8+2.5+8.16
+2 = 42.99 weeks
So, the total project completion time = 43.49 weeks
Q. The owner of a restaurant is considering a
new computer project for inventory control. A
computer company sent the following
information about the system installation :
Activity Immediate Most Most Most
predecessor Optimist Likely Pessimis
ic Time Time tic Time
A - 4 6 8
B A 5 7 15
C A 4 8 12
D B 15 20 25
E B 10 18 26
F C 8 9 16
G E 4 8 12
H D,F 1 2 3
I G,H 6 7 8
(a) Determine critical path and expected project
completion time.
(b)Determine the probability that the project will be
completed in 55 days.
3 E
5
B D G
A 2
H
1 6 7 8
I
C
F
4
Calculation of expected time and variances
Activit a m b Tei i = (b- i2
y =(a+4m+b)/ a)/6
6
A (1-2) 4 6 8 6 4/6 4/9
B (2-3) 5 7 15 8 10/6 25/9
C (2-4) 4 8 12 8 8/6 16/9
D (3-6) 15 20 25 20 10/6 25/9
E (3-5) 10 18 26 18 16/6 64/9
F (4-6) 8 9 16 10 8/6 16/9
G (5-7) 4 8 12 8 8/6 16/9
H (6-7) 1 2 3 2 2/6 1/9
I (7-8) 6 7 8 7 2/6 1/9
Length of different project paths from the project network :
Path : 1-2-3-5-7-8 = 6+8+18+8+7 = 47 days
Path : 1-2-3-6-7-8 = 6+8+20+2+7 = 43 days
Path : 1-2-4-6-7-8 = 6 + 8 + 10 + 2 + 7 = 33 days
(a) Using the expected time of activity duration, we obtain the critical
path as
1 2 3 5 7 8 since the duration of this path is longest.
Thus we have the expected project length, Te = 6+8+18+8+7
= 47 days
The variance of the project length, VT = 4/9 + 25/9 + 64/9 + 16/9 + 1/9
= 110/9
(b) The project duration is
normally distributed with
Mean(TE ) = 47 days
Standard deviation =(V T )=(110/9)
=3.496
The probability of project being
Completed in 55 days is equal to =47
55
The area under the normal curve lying to the left of X=55 as
shown in Figure above. We have, Z = (55-47)/3.496 = 2.29. From
the Normal Table, the area between Mean and Z = 2.29 under the
Normal curve = 0.4890.
Thus the required probability = 0.5 + 0.4890 = 0.9890