For the fire test

5 Studs RY 145 and 2 Runners SKY 145 and 10 stiffners AA


Electric Screw driver with charger and Screws for steel
Exterior board 2 pcs (Visaka exterior or Gyproc Fireline
Twiga Insulation blocks
Double interior boards internal Visaka and External Gyproc fireline
Or 2 gyproc firreline boards
Assembly

Take 2 runners and 2 studs and as per drawing lay them on a even floor
Put the stiffners
With a right angle join each corner with only one screw slightly loose
With a metal measuring tape measure the cross corners

Both measurements to be the same


Put the two screws diagonally and tighten all four corners
Lift the frame and reverse and tighten screw the second side
similarly
Pls check if this is the correct drawing given to Yuvraj
Assembly next three runners
Put the stiffners on each end and then place the runners
inside keeping the point to point distance as per drawing and
screw 2 diagonal screws on eahc side
Put external boards first
Fill insulation
Fut first internal board 2 pcs only
Put second internal board 3 pcs

Pls follow steps as per instructions


rd 2400 x 1220 second board to be cut
ews at every 60 cm boards to fit on stud no 3 center to centerStud no 3

For exterior
board and
first
Interior
board
This gap to be 2 m

Second board
Stud no 2 and 4

For second
interior
board

This gap to be 2 m

Second board