Vietnam Brewery Limited

Our journey towards


Leading in operational excellent

STEAM & AIR SAVING


5th Presentation
14-10-2003
Presented by Pham Minh Trung

No one learns without doing

Steam & Air Saving Practice Pham Minh Trung


1
Agenda

Part 1: Project Planning


Part 2: Report some last actions
Part 3: Coming Actions

Steam & Air Saving Practice Pham Minh Trung


2
Project Planning
Project Leader : Pham Minh Trung
Title : EM
Section : Packaging
VBL - FIT - STEAM & AIR SAVING PROJECT
Date : 07 Oct 2003

Saving Target Progress


No. WHAT WHERE WHEN WHO
MJ/yr MJ/hl None Doing Done
1 Distribution & Recovery system

1.1 Inspect & repair all steam traps All plants of the brew ery 31-12-03 Phat, Thien, Tich 7099610.82 5.68 X

1.2 Return condensate to the boiler up to >80% All plants of the brew ery 31-12-03 Thai, Thien, Thanh 4259766.49 3.41 X

1.3 Optimization steam manifolds, main lines, All plants of the brew ery 30-4-04 Thai, Thien,Sau 2839844.33 2.27 X
branches
1.4 Insulate Steam Distribution and Condensate All plants of the brew ery 31-12-03 Phat 2839844.33 2.27 X
Return Lines
1.5 Isolate steam from unused lines All plants of the brew ery 30-4-03 Thai, Thien, Sau 2839844.33 2.27 X

2 Im provem ent in te chnology

2.1 Improve Boiler's combustion eff iciency Utilities 31-12-03 Thao, Sau' Liem 2839844.33 2.27 X

2.2 Minimize boiler blow dow n Utilities 31-12-03 Anh, Thanh, Liem 709961.08 0.57 X

2.3 Recover heat f rom boiler blow dow n Utilities 31-3-04 Sau, Liem 709961.08 0.57 X

2.4 Utilities 31-12-03 Thao, Sau, Liem 1419922.16 1.14 X


Optimizing Deaerator steam consumption

3
Re trofitting & Investm ent

3.1 Use feed w ater economizers f or w aste heat Utilities 30-10-04 Sau, Liem 7099610.82 5.68 X
Recovery
3.2 Use vapor recommpression to recover low - Brew house 2 30-4-05 Sau, Liem 8519532.98 6.82 X
pressure w aste steam

Steam & Air Saving Practice Pham Minh Trung


3
Part 1: Report some last actions

1-Insulation work for bare equipment and piping systems: 80%


2-Installed two isolating devices for BH1, and one for canning line,
together with their heat-up valves.
3-Replaced/ repaired 10 sets of steam traps.
4-Complete installation of 04 new boiler feed water pumps that have
higher efficiency and better performance.
5-Finish making layouts for steam and air distribution and
condensate collecting system.
6-Preparing to install Spirax-Sarco steam flowmeters for boiler 1&2
for measuring steam quantity generated: 70%. Completion in
November.
7-Complete installing 02 in-line CO2 purity meters for by-pass
supplying for saving electricity consumption at Haffmans and Seeger
plants.
8-Optimized 03 piping systems.
Steam & Air Saving Practice Pham Minh Trung
4
Part 1: Report some last actions

Removable Insulation Blocks with


Internal Devices Code Stickers

Steam & Air Saving Practice Pham Minh Trung


5
Part 1: Report some last actions
Removable Insulation Blocks with
Internal Devices Code Stickers

Steam & Air Saving Practice Pham Minh Trung


6
Part 1: Report some last actions

Optimization of steam piping system


at BH1: the second branch.

Flowmeters have been installed at all


condensate pumps discharges.

Steam & Air Saving Practice Pham Minh Trung


7
Part 1: Report some last actions

Main steam traps and control valves


were installed removable insulation
blocks.

Steam & Air Saving Practice Pham Minh Trung


8
Part 1: Report some last actions

Hot water pipes of re-generation


system of 04 Carbon filters have
been linked and insulated.

Two Carbon filters were already


insulated with welded claddings.

Steam & Air Saving Practice Pham Minh Trung


9
Part 1: Report some last actions
Complete installation of 04 Boiler
Feed pumps

Steam & Air Saving Practice Pham Minh Trung


10
Part 1: Report some last actions

Additional Caustic heater for


Caustic Zone 1- Bottle Washer

Steam & Air Saving Practice Pham Minh Trung


11
Part 1: Report some last actions

Fabricating new St.St. Caustic heater for Caustic


Zone 2- Bottle Washer. It will be installed in
November 2003.
The heater of Zone 1 has been designed. It will
be installed after TET.

Steam & Air Saving Practice Pham Minh Trung


12
Part 2: Coming Actions (to 31-12-03)

1-Housekeeping

-To continue the insulation works for bare piping systems and
removable insulation blocks for valve and fittings. To be complete before 15-
11-03.
-To installed 02 steam flowmeters for 02 10t/h boilers. Make
generated steam totalizer for boiler No 3. To be complete before 30-11-03.
-To installed 03 feed water flowmeters for 03 boilers. To be
complete before 31-12-03.
-To prepare some short training modules: STEAM TRAP SELECTION
AND CHECKING TECHNIC, CORRECT PIPING INSTALLATION.
-Complete installation of main condensate return flowmeters before
31-11-03
-Complete making all steam/air/condensate layouts and indicate all
necessary metering points. Before 31-10-03.

Steam & Air Saving Practice Pham Minh Trung


13
Part 2: Coming Actions (to 31-11-03)

2-Low Cost execution


-To continue modification of some more incorrect steam/ condensate
piping systems for better performance and avoiding of water hammer.

EX.: Split-up condensate lines of


BH1 and BH2- Week 39.

Steam & Air Saving Practice Pham Minh Trung


14
Part 2: Coming Actions (to 20-10-03)

3-Retrofit
-Complete installation of two new burners for boiler 1&2 before 20-
10-03.

New burner of Boiler No1 was New burner of Boiler No2 is being
complete. Its been put in operation. installed.

Steam & Air Saving Practice Pham Minh Trung


15
Part 2: Coming Actions (2004)

3-Retrofit
-Studying on installation of auto-blowoff systems for boilers 1&2
following TDS content in boiler water.

Surface blowdown bases on TDS Bottom blowdown bases on boiler


water hardness.

Steam & Air Saving Practice Pham Minh Trung


16
Part 2: Coming Actions (2004)

3-Retrofit
-Studying on installation of electronic de-scaler for boiler make-up
water. SOFPAC ELECTRONIC DESCALERs specialist has been invited to discuss
and have made an investigation.
01 set will be installed at the second NH3 evaporative condenser.
Another set will be installed at boilers softener.

Steam & Air Saving Practice Pham Minh Trung


17
Part 2: Coming Actions (2004)

3-Retrofit
-Studying on installation 03 sets of economizers for 03 boilers, to
make use of waste heat exhausted from their chimneys. Potential supplier is
being discussed the design.

Steam & Air Saving Practice Pham Minh Trung


18
Part 2: Coming Actions (2004)

3-Retrofit
-Studying on installation 03 sets of economizers for 03 boilers, to
make use of waste heat exhausted from their chimneys. Potential supplier is
being discussed.

Steam & Air Saving Practice Pham Minh Trung


19
Part 2: Coming Actions (2004)

3-Retrofit
-Studying on installation 03 sets of economizers for 03 boilers, to
make use of waste heat exhausted from their chimneys. Potential supplier is
being discussed.