Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1.1 Inspect & repair all steam traps All plants of the brew ery 31-12-03 Phat, Thien, Tich 7099610.82 5.68 X
1.2 Return condensate to the boiler up to >80% All plants of the brew ery 31-12-03 Thai, Thien, Thanh 4259766.49 3.41 X
1.3 Optimization steam manifolds, main lines, All plants of the brew ery 30-4-04 Thai, Thien,Sau 2839844.33 2.27 X
branches
1.4 Insulate Steam Distribution and Condensate All plants of the brew ery 31-12-03 Phat 2839844.33 2.27 X
Return Lines
1.5 Isolate steam from unused lines All plants of the brew ery 30-4-03 Thai, Thien, Sau 2839844.33 2.27 X
2.1 Improve Boiler's combustion eff iciency Utilities 31-12-03 Thao, Sau' Liem 2839844.33 2.27 X
2.2 Minimize boiler blow dow n Utilities 31-12-03 Anh, Thanh, Liem 709961.08 0.57 X
2.3 Recover heat f rom boiler blow dow n Utilities 31-3-04 Sau, Liem 709961.08 0.57 X
3
Re trofitting & Investm ent
3.1 Use feed w ater economizers f or w aste heat Utilities 30-10-04 Sau, Liem 7099610.82 5.68 X
Recovery
3.2 Use vapor recommpression to recover low - Brew house 2 30-4-05 Sau, Liem 8519532.98 6.82 X
pressure w aste steam
1-Housekeeping
-To continue the insulation works for bare piping systems and
removable insulation blocks for valve and fittings. To be complete before 15-
11-03.
-To installed 02 steam flowmeters for 02 10t/h boilers. Make
generated steam totalizer for boiler No 3. To be complete before 30-11-03.
-To installed 03 feed water flowmeters for 03 boilers. To be
complete before 31-12-03.
-To prepare some short training modules: STEAM TRAP SELECTION
AND CHECKING TECHNIC, CORRECT PIPING INSTALLATION.
-Complete installation of main condensate return flowmeters before
31-11-03
-Complete making all steam/air/condensate layouts and indicate all
necessary metering points. Before 31-10-03.
3-Retrofit
-Complete installation of two new burners for boiler 1&2 before 20-
10-03.
New burner of Boiler No1 was New burner of Boiler No2 is being
complete. Its been put in operation. installed.
3-Retrofit
-Studying on installation of auto-blowoff systems for boilers 1&2
following TDS content in boiler water.
3-Retrofit
-Studying on installation of electronic de-scaler for boiler make-up
water. SOFPAC ELECTRONIC DESCALERs specialist has been invited to discuss
and have made an investigation.
01 set will be installed at the second NH3 evaporative condenser.
Another set will be installed at boilers softener.
3-Retrofit
-Studying on installation 03 sets of economizers for 03 boilers, to
make use of waste heat exhausted from their chimneys. Potential supplier is
being discussed the design.
3-Retrofit
-Studying on installation 03 sets of economizers for 03 boilers, to
make use of waste heat exhausted from their chimneys. Potential supplier is
being discussed.
3-Retrofit
-Studying on installation 03 sets of economizers for 03 boilers, to
make use of waste heat exhausted from their chimneys. Potential supplier is
being discussed.