1. Introduction
2. Mitigation equipment
3. Dip immunization capability
4. Other aspects
5. Conclusion
LABORELEC
LABORELEC 2006 2
1. Introduction
LABORELEC
LABORELEC 2006 3
Voltage dips / sags
> 10%
<2s
Dip
Dips are mainly caused by short circuits
LABORELEC
LABORELEC 2006 4
Cost per process outage
(cases Laborelec 2004/2005)
Basic Chemicals
Semiconductor
Automotive
Textile
Non-Ferro
Food 190 000
100 000
Textile
Textile
Textile
Textile
Dairy
Textile
Textile
Plastics
Food
Textile
Food
Dairy
Dairy
0 10.000 20.000 30.000 40.000 50.000 60.000 70.000 80.000 90.000 100.000
LABORELEC
LABORELEC 2006 5
Mitigation possibilities
a. Adaptation processes
b. Adaptations protections
a c. Installing mitigation equipment
d. Grid restructuring
VSD 1 b
c d
VSD 2 Entrance grid
company
PLC
Sensitive Processes
LABORELEC
LABORELEC 2006 6
2. Mitigation equipment
LABORELEC
LABORELEC 2006 7
Flywheel
grid load
static switch
G M/G
converters
LABORELEC
LABORELEC 2006 8
Static UPS
grid load
AC/DC-converter DC/AC-converter
battery
LABORELEC
LABORELEC 2006 9
Dynamic Voltage Restorer
grid load
transformer
converter
DC-link with
possibleenergy
reserve
LABORELEC
LABORELEC 2006 10
Statcom
grid load
transformer
converter
LABORELEC
LABORELEC 2006 11
Shunt connected
synchronous motor
synchronous machine
LABORELEC
LABORELEC 2006 12
Transformerless series
injection
staticswitch
load
LABORELEC
LABORELEC 2006 13
3. Dip immunization
capability
LABORELEC
LABORELEC 2006 14
Dip distribution
100
100
voltage drop
drop
9090
8080
than voltage
7070 B1
6060
F
5050
less than
4040
B2
NL
sags less
3030 PP
2020 US
of sags
1010 C
% of
0 0
%
0 0 2020 4040 60
60 80
80 100
100
Voltage
Voltagedrop
drop(%)
(%)
LABORELEC
LABORELEC 2006 15
Immunization level
sag (% Urated)
0 1. 2. 3. 4. .5. 6.
-100
LABORELEC
LABORELEC 2006 16
Immunization level
being protected in %
due to sags that will be
immunity 30%
immunity 10%
immunity 30%
immunity 10%
reduced:
40 - 60%
60 - 80%
80 -100%
Flywheel 100 /
Static UPS 100 /
DVR-Cap1 / 30
DVR-Cap2, 200% load / 50
DVR-Cap2, 400% load / 25
Statcom-SMES / 60
Shunt Connected SM / 60
Transformerless series injection 50 /
LABORELEC
LABORELEC 2006 17
4. Other aspects
LABORELEC
LABORELEC 2006 18
Size
- : only > 1MW
= : only > 100 kW
+ : also < 100 kW
Purchase cost
- : > 250 /kVA
= : 150 250 /kVA
+ : < 150 /kVA
Maintenance
- : annual maintenance required
+ : no annual maintenance required
LABORELEC
LABORELEC 2006 19
Efficiency
+ : losses <0,5% Srated
= : losses 0,5-2% Srated
- : losses >2% Srated
Reaction time
+ : reaction or activation transient < 1 ms
= : transient 1-5 ms
- : transient > 5 ms
LABORELEC
LABORELEC 2006 20
Summary
Reactive power
Purchase cost
Reaction time
Maintenance
Technology
harmonics
harmonics
Efficiency
maturity
Voltage
Current
Size
Flywheel = - - - = + + + +
Static UPS + = - - + + + + +
DVR-1 + + + = = = = + =
DVR-2, 200% load - + + - = + = = =
DVR-2, 400% load - + + - = + = = =
Statcom-SMES - = - = - = = + -
Shunt connected SM + - - -/= = + +1 + -
Transformerless series injector + = + + = = = = =
1 The harmonic currents are reduced by creating a low impedance path through the SM
LABORELEC
LABORELEC 2006 21
5. Conclusion
LABORELEC
LABORELEC 2006 22
Most cost efficient
DVR without energy storage
Transformerless series injector
If harmonics are an issue
Synchronous motor
If all sags have to be dealt with
Flywheel or static UPS
further information on
manufacturers or concrete case studies
marcel.didden@laborelec.com
LABORELEC
LABORELEC 2006 23