Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Lathe Headstock
Design Considerations:
Design Considerations:
The overhang of the tool holder must be kept as less as possible to avoid
vibrations.
Design Considerations:
Added Bases
Diameter to be Machined
4000
393
4200
393
4400
303
4600
303
4800
197
5100
197
5400
106
5800
1.
2.
3.
4.
Cutting Forces:
Fz = 2146.3kN
Fy = 645.37kN
Fx = 1496.18kN
= P / 0.707hl
Where, P = tensile force on plates
= Fy = 645.37kN = 645370N
h = leg of the weld (mm) =
8mm
l = total length of the weld
= 1980mm
= 645370 / (0.707 x 8 x 1980)
= 57.63MPa
Now the maximum yield strength
of IS 2062 Grade A steel is
240MPa > 57.63Mpa. Hence the
design of the welds on the support
plate ribs is safe.
= P / 0.707hl
Where, P = tensile force on
plates = Fh = 1672.46kN =
1672460N
h = leg of the weld
(mm) = 8mm
l = total length of the
weld = 1600mm
= 1672460 / (0.707 x 8 x
1600)
= 184.81Mpa
Now the maximum yield
strength of IS 2062 Grade A
steel is 240MPa >
184.81Mpa. Hence the design
of the welds on the rear plate
ribs is safe.
Inspection:
ThyssenKrupp Industries India
QUALITY ASSURANCE
FINAL INSPECTION REPORT
Quantity: 1
The item was inspected and the following are the observations
Sr. No.
Required Dimensions
Observed Dimensions
1.
25
2.
462 mm
3.
526 mm
4.
280 mm
5.
245 mm
Remarks
Costing:
The approximate weight of the fixture was calculated using the weights of the
plates used and the total weight of the filler material used. Now the total volume
of metal plates used was calculated to be 204999.41cm3. The plates used were
M.S. plates and the density of mild steel is = 7.86g/cm3.
V1 = 204999.41cm3
Therefore, the weight of the metal plates used was calculated as:
M1 = V1 x
M1 = 204999.41 x 7.86
M1 = 1611295.363g
M1 = 1611.29Kg
The cost of IS 2062 Grade A steel is Rs 52 per Kg
Hence the raw material cost can be calculated as
C1 = 52 x 1611.29
C1 = Rs 83,787
Weld specifications:
CO2 Welding at 220A 28V,
8 x 8 mm fillet welds
Filler Material: 1.2 mm FCAW wire fed at 9m/min
The total time taken for the fit up of the fixture was approximately 3hrs.
T1 = 3hrs
Wire feed rate = 9m/min = 150mm/sec
Wire cross section area = /4 x 1.22
Wire feed rate in terms of volume of filler material per second is
F = 150 x /4 x 1.22
F = 170mm3/sec
Weld time can be calculated as
T2 = V/F
T2 = 1707584/170
T2 = 10044.61sec
T2 = 173.3min or 2hrs 53min
Based on timings recorded during the welding, it was found that on an average,
50% of the weld time was required for slag removal and cooling of the welded
area.
Hence, Weld cooling and slag removal time
T3 = 0.5 x T1
T3 = 0.5 x 173.3
T3 = 86.65min or 1hr 27min
For welding the multi-pass weld, preheating was carried out for a period of
15min/pass. Therefore the time required for preheating is calculated as
T4 = 15 x 5
T4 = 75min or 1hr 15min
Taking into account the various stoppages in work such as replacement of wire
spool as well as relaxation of the worker, the contingency and relaxation allowance
must also be considered. This allowance is assumed to be 10% of the weld time.
Therefore,
T5 = 0.1 x 173.3
T5 = 17min
The total time required to weld the fixture can be calculated as
Tw = T1 + T2 + T3 + T4 + T5
Tw = 9hrs 52min
The wage rate of a welder is Rs 350 per day for an 8hour shift.
Therefore the total labour cost associated with the welding of the fixture can be
calculated as :
C3 = 9.866 x 350/8
C3 = Rs 432
The time required for drilling 30mm holes in top plate can be calculated as :
T6 = d x N / sr x n
Where sr = Feed per revolution
n = rpm
d = depth of hole = 32mm
N = No. Of holes to be drilled
Therefore,
T6 = 32 x 12 / 0.3 x 150
T6 = 8.53min
Similarly, the time required for drilling 24mm holes in bottom plate can
be calculated as:
T7 = d x N / sr x n
Where sr = Feed per revolution
n = rpm
d = depth of hole = 32mm
N = No. Of holes to be drilled
Therefore,
T7 = 32 x 10 / 0.3 x 150
T7 = 7.11min
Time required for milling top plate can be calculated as:
T8 = Lm / s
Where Lm = Length of machining
s = Feed per min
Lm = 22050mm
s = 1200mm/min
T8 = 22050/1200
T8 = 18.375min
Similarly, Time required for milling support plate can be calculated as:
T9 = Lm / s
Where Lm = Length of machining
s = Feed per min
Lm = 4800mm
s = 1200mm/min
T9 = 4800/1200
T9 = 4min
Similarly, Time required for milling bottom plate can be calculated as:
T10 = Lm / s
Where Lm = Length of machining
s = Feed per min
Lm = 38700mm
s = 1200mm/min
T10 = 38700/1200
T10 = 32.25min
The total time required to machine the fixture is calculated as :
Tm = T6 + T7 + T8 + T9 + T10
Tm = 70.265min or 1hr 10min or 1.17hrs
Cost operating the machine tool is Rs 1500 per hour
Hence, total machining cost is calculated as :
C4 = 1.17 x 1500
C4 = Rs 1,755
Therefore the total cost of the fixture is
C = C1 + C2 + C3 + C4
C = Rs 87182
Conclusion:
After addition of second gearbox the required feed rate
was achieved resulting in satisfactory performance of the
fixture. The addition of the third fixture enabled
simultaneous machining operations to be carried out at
both the bearing support tyres as well as the girth gear
flange. Such an integration of the third machining
process led to machining time reduction. Also the new
fixture was lighter in weight than its previous
counterparts. As a result, there was greater ease in
setting up the operation and time required for non-valueadded activities was greatly reduced.