How to plan and Control Linear Projects by

measuring performance of construction


works
Tekin Guvercin
Civil Engineer

Who is
Essential Business Commination

FND is an exclusive
solution providers
of international
project
management
systems

81

Founded in 2009 in Poland


57 Partners worldwide
2000+ Customers
Customers in 84 countries
Deliver Support 7*24h*365d
9 Language Speaking Company
Very strong AEC Background
Very Strong Partner Network

Our Solution Partners


FND has an outreach to more than 80 countries across the globe.
.

Costumer Map
FND has more than 2000+ costumers.
.

Construction Companies who use Linear


Planning

Linear Projects Characteristics

Have an axis (ROW) along which the work is performed

Repetition of each activity along the length of the project


The goal is to have exact quantities and optimize the productivity rates
Minimizing the total time of crews and avoid clashes
Reducing project duration
Reducing overall cost

Linear Planning usage at any project stage


Feasibilty Studies
Overall Plan
Production plan
Tender
Special studies
Predesign

Offer Preparation

Planning

Procurement

Execution

Owner / Engineering companies


Contractor & Sub-Contractor & Supplier

Claims

500,000 m3
Excavation
2000 m

Start Location 0 m

End Location 2000 m

Start Date 15th of March

Duration 46 days

Finish Date 30th of April

Average Productivity 21m/day


Average Productivity 10,870m3/day

21m/d

z1

20m/d

z2
z3

500,000 m3
Excavation

10m/d
14m/d

z4
z5

9m/d

25m/d

2000 m

z6

16m/d

z7

z1

z2

z3

z4

z5

z6

z7

20m/d
21m/d
10m/d
14m/d
9m/d

DELAY
21days

25m/d

16m/d

z1

z2

z3

z4

z5

z6

CREW1
CREW2

TARGET LINE

z7

2000 m

TILOS add Extra dimention to your project planing and control process

LIVE DEMO