Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
VI
SLIP FORM CONSTRUCTION
PARUL
BHYAN(1210463011)
INTRODUCTION
Slip form construction, or continuously formed construction, is a
construction method in which concrete is poured into a continuously
moving form.
KAFD, Riyadh, KSA
HISTORICAL BRIEF
The slip forming technique was in use by the early 20th century for
building silos and grain elevators.
James MacDonald, of MacDonald Engineering of Chicago was the
pioneer in utilizing slip form concrete for construction.
His concept of placing circular bins in clusters was patented, with
photographs and illustrations, contained in a 1907 book, The Design
Of Walls, Bins, And Grain Elevators.
Skylon Tower, 1965
Types of Slip-form
Construction
1- Vertical Slip-form
2- Horizontal Slip-form
In horizontal slip forming for pavement and traffic separation walls,
concrete is cast, vibrated, worked, and settled in place while the form itself
slowly moves ahead.
This method was initially devised and utilized in Interstate Highway
construction initiated during the 1950s
Factor
Description
1. Time
2. Durability
3. Cost
4. Maintenance
5. Flexibility
6. Labor
Applications of Slip-form
Construction
Slip-form construction is used for tall structures, such as towers,
buildings, and dams, as well as horizontal structures, such as
roadway barriers.
It enables continuous, non-interrupted, cast-in-place joint-less
concrete structures which have superior performance
characteristics over construction methods using discrete form
elements.
Slip forming relies on the quick- setting properties of concrete, and
requires a balance between quick-setting capacity and workability.
nn Canal, Germany
King Abdul-Aziz A
Structural Concerns
It is necessary to use a low slump concrete in slip forming processes
where the formwork is moved horizontally in order for the slab or
pavement to retain its shape as the paving machine advances.
Presently, slip form pavements use "high early strength" concrete,
which achieves the required strength in approximately 12 hours, as
compared to conventional concrete which requires 5-14 days.
The water content of this type of concrete is lower than it is for
standard material, resulting in improved strength as well as improved
resistance to the permeation of salt, thereby increasing the finished
concrete's resistance to deterioration from chloride ions.
Construction
Sequence
1. The formwork and the access
platform are assembled on the
ground.
2. The assembly is raised using
hydraulic jacks which are mounted
on strategically located steel
frames to lift the formwork as the
concrete is poured into the forms.
3. As the formwork rises continuously,
continuous concrete and rebar
supply are needed until the
operation is finished.
4. As the formwork is raised,
reinforcement is held in the correct
position using guides, horizontal
reinforcement is tied to the vertical
reinforcement.
Construction Sequence
Slip forming relies on the quick-setting properties of concrete, and
requires a balance between quick-setting capacity and workability.
Concrete needs to be workable enough to be placed into the form and
consolidated via vibration.
This strength is needed because the freshly set concrete must not only
permit the form to "slip" passed the concrete without disturbing it, but
also support the pressure of the new concrete as well as resist collapse
caused by the vibration of the compaction machinery.
Tapered Slip-forming
Slip-forming is also used in the construction of conical chimneys, cooling
towers, piers and other tall concrete structures involving constant or
changing thicknesses in walls, diameters and/or shapes A form is used
with sections which overlap so that one gradually slides over the other.
This is commonly done in chimney construction but it is not satisfactory
for architectural concrete because the lap shows.
While the tapered slip-forming process is similar to that used on the
standard slip-forming, it requires greater attention, contractor
experience and expertise ensures the success of such projects.
Jump Form
Another but similar method that
is in use for this type of
construction is the jump form
method. In this method the
form work jumps up to the next
layer after the bottom layer is
cast. The concrete pouring is
not continuous as in the slipform method. Jump forms climb
in steps following each concrete
pour.
This type of construction is
more suited to high rise building
cores where there are regular
floors and joints will not be
seen.
SUMMARY
Slip form construction is a construction method in which concrete
is poured into a continuously moving form.
There are two types of slip-forms; vertical and horizontal.
Slip-form construction consumes very less time but requires careful
planning of construction process to achieve high production rates.
Due to continuous concrete pouring in slip-form construction it
produces better concrete joint less and watertight structures.
Slip form systems require a few but highly skilled workforce.
Slip-forming is also used in the construction of tapered structures
involving changing thicknesses in walls, diameters and/or shapes.
Another but similar method that is in use for this type of
construction is the jump form method. In this method the form
work jumps up to the next layer after the bottom layer is cast. The
concrete pouring is not continuous as in the slipform method.