Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CLAIM MANAGEMENT
Basics:
Whats a Contract?
But a contract is typically enforceable only when all the parties have
signed and agreed to the obligations and entitlements.
Legal
consequence
Contract
Claims
Co
nt
ra
ct
Supplier
Co
nt
ra
ct
Contract
Employer
Contractor
Joint
Venture
Contractor
Contractor
Sub-Contractor
Contractor
Engineer
Sub-Contractor
CLAIM MANAGEMENT
DELAY
& EOT
CONTRACT TIME
In order to have certainty a contract will have a
start and a completion date.
If the Employer does not hand over the site at
the start date then he immediately puts the
Contractor into delay for which he may then
become liable for granting extension of time and
prolongation costs.
By contrast if the project completes late then in
the absence of an extension of time award the
Contractor may be liable for the costs of the
delay.
CLAIM MANAGEMENT
DELAY
&OF
EOT
BUT WHAT IS THE CONSEQUENCE
TIME AT LARGE
Without a mechanism for extending completion
date, the Contractors obligation would be simply
to complete the works by the contract completion
date.
however If there was any act of prevention by
the Employer or anyone on his behalf, then time
becomes at large, and the Contractor would
have a reasonable period of time for
completing the works.
TIME AT LARGE happens ..
CLAIM MANAGEMENT
DELAY
& EOT
CLAIM MANAGEMENT
DELAY
& EOT
NB: if contractor failed to give early warning of a delay or failed to cooperate in dealing with a
delay, the delay by this failure shall not be considered in assessing the new intended completion
date
9/23/16
13
CLAIM MANAGEMENT
DELAY
& EOT
CLAIM MANAGEMENT
DELAY
& EOT
16
DELAY
& EOT
CLAIM MANAGEMENT
8.
17
CLAIM MANAGEMENT
DELAY
& EOT
Clause 20 discoveries
9/23/16
CLAIM MANAGEMENT
DELAY
& EOT
Employer to give
possession of site as
per the approved
program
Cost + time
(eng. to determine by
how much to increase
the contract price and by
how much the intended
completion date has to
be extended)
9/23/16
Compensation event!!!
19
DELAY
EOT
CLAIM &
MANAGEMENT
The engineer shall check the contractors work and notify the contractor of any defects
that are found.
The engineer may instruct the contractor to search for a defect and to uncover and test any
work that the engineer considers may have a eefect.
If the test is not specifies in the
contract, and if the test shows
that it doesnt have any defect
9/23/16
Compensation event
20
DELAY
EOT
CLAIM &
MANAGEMENT
3. NOTICE REQUIREMENTS
4. OBLIGATION TO MITIGATE
5. EVIDENCE OF DELAY
DOCUMENTATION REQUIREMENTS
all documentation requirements have to be
followed by the contractor.
General rule: Document all deviations from the
plan!
Keep contemporary records if required by the
Contract
Delays
Increased costs
Unforeseen conditions and events
Oral instructions
Number and location of the work-force
CLAIM MANAGEMENT
DELAY
& DO
EOT
WHAT ADDITIONAL SET OF RECORDS
GLOBAL CLAIM
Global Claims are claims that show no
connection between the matters complained of
and their consequences in terms of time and
money are not spelled out.
The claimant must be specific as to the delay it
alleges to have been caused by a particular
event.
This requires proper presentation of a claim
based on contemporaneous records in order to
show a discernible link between the relevant
event and the delay.
CLAIM MANAGEMENT
DELAY
& EOT
6. EFFECT ON COMPLETION
PRESENTATION OF CLAIMS
Claims can be presented in a variety of ways, the
following outline suggests the general approach
for claim submission:
Summary of the claim briefly described at the
beginning of the claim presentation
It is quite common to start with a short
introduction giving an outline of the claim and to
substantiate the claim later.
substantiated not only the factual background
but also the legal background of the claim
state the relevant clauses in a logical context
CLAIM MANAGEMENT
DELAY
& EOT
and to give further support on legal issues,
PRESENTATION OF CLAIMS
The claim should be presented in a clear and
logical manner, preferably including the following:
An introduction providing details of the parties involved in the claim
and all relevant dates and information;
A description of the claim events as they occurred and their effects;
An analysis of the facts showing the grounds upon which the claim
was based, with reference to the relevant provisions and clauses of
the contract;
A description and reference to the steps already taken by the
contractor, such as notices given;
A calculation of the cost impact based on a breakdown of actual
direct and indirect costs incurred; and
A determination of the claimed extension of time based on an
analysis of critical and noncritical delays;
CLAIM MANAGEMENT
DELAY
& EOT