Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Chapter 3
Project Management
OBJECTIVES
Project Management
Defined
Project is a series of related jobs usually
directed toward some major output and
requiring a significant period of time to
perform
Project Management are the management
activities of planning, directing, and controlling
resources (people, equipment, material) to meet
the technical, cost, and time constraints of a
project
The McGraw-Hill Companies,
Horizontal
Horizontalbars
barsused
usedtotodenote
denotelength
length
ofoftime
timefor
foreach
eachactivity
activityor
orjob.
job.
Activity 1
Activity 2
Activity 3
Activity 4
Activity 5
Activity 6
Time
Horizontal
HorizontalAxis:
Axis:Always
AlwaysTime
Time
The McGraw-Hill Companies,
Pure Project
Defined
A pure project is where a self-contained team
works full-time on the project
Duplication of resources
Organizational goals and policies are ignored
Lack of technology transfer
Team members have no functional area
"home"
Functional Project
Defined
A functional project is housed within a
functional division
President
Research and
Development
Project Project Project
A
B
C
Engineering
Project Project Project
D
E
F
Manufacturing
Project Project Project
G
H
I
Example,
Example, Project
Project B
B is
is in
in the
the functional
functional
area
area of
of Research
Research and
and Development.
Development.
The McGraw-Hill Companies,
Structuring Projects
Functional Project: Advantages
A team member can work on several
projects
Technical expertise is maintained within
the functional area
The functional area is a home after the
project is completed
Critical mass of specialized knowledge
10
Structuring Projects
Functional Project: Disadvantages
Aspects of the project that are not
directly related to the functional area get
short-changed
Motivation of team members is often
weak
Needs of the client are secondary and are
responded to slowly
11
Structuring Projects:
Matrix Project Organization Structure
President
Research and
Development
Engineering
Manufacturing
Marketing
Manager
Project A
Manager
Project B
Manager
Project C
The McGraw-Hill Companies,
12
Structuring Projects
Matrix: Advantages
Enhanced communications between functional
areas
Pinpointed responsibility
Duplication of resources is minimized
Functional home for team members
Policies of the parent organization are followed
The McGraw-Hill Companies,
13
Structuring Projects
Matrix: Disadvantages
Too many bosses
Depends on project managers
negotiating skills
Potential for sub-optimization
14
1
2
Program
Project 1
Project 2
Task 1.1
Task 1.2
Subtask 1.1.1
Subtask 1.1.2
Work Package 1.1.1.2
The McGraw-Hill Companies,
15
Network-Planning Models
A project is made up of a sequence of
activities that form a network representing a
project
The path taking longest time through this
network of activities is called the critical
path
The critical path provides a wide range of
scheduling information useful in managing a
project
Critical Path Method (CPM) helps to identify
the critical path(s) in the project networks
The McGraw-Hill Companies,
16
17
Time-Cost Models
Used when cost trade-off information is a major
consideration in planning
Used to determine the least cost in reducing total project
time
The McGraw-Hill Companies,
18
19
20
21
A
B
C
None
A
B
2
1
1
D
E
F
C
C
D,E
2
5
5
A(2)
B(1)
D(2)
C(1)
F(5)
G(1)
E(5)
The McGraw-Hill Companies,
22
ES=2
EF=3
ES=3
EF=4
A(2)
B(1)
C(1)
Hint:
Hint:Start
Startwith
withES=0
ES=0
and
andgo
goforward
forwardin
inthe
the
network
networkfrom
fromAAto
toG.
G.
D(2)
ES=4
EF=9
ES=9
EF=14
ES=14
EF=15
F(5)
G(1)
E(5)
Example 1:
Determine late
starts and late finish
times
ES=0
EF=2
ES=2
EF=3
ES=3
EF=4
A(2)
B(1)
C(1)
LS=0
LF=2
LS=2
LF=3
LS=3
LF=4
23
Hint:
Hint:Start
Startwith
withLF=15
LF=15or
or
the
thetotal
totaltime
timeof
ofthe
theproject
project
ES=4 and
andgo
gobackward
backwardin
inthe
the
EF=6 network
networkfrom
fromGGto
toA.
A.
D(2)
LS=7
LF=9
ES=4
EF=9
E(5)
ES=9
EF=14
ES=14
EF=15
F(5)
G(1)
LS=9
LF=14
LS=14
LF=15
LS=4
LF=9
The McGraw-Hill Companies,
24
ES=2
EF=3
ES=3
EF=4
A(2)
B(1)
C(1)
LS=0
LF=2
LS=2
LF=3
LS=3
LF=4
D(2)
LS=7
LF=9
ES=4
EF=9
E(5)
LS=4
LF=9
Slack=(7-4)=(9-6)= 3 Wks
ES=9
EF=14
ES=14
EF=15
F(5)
G(1)
LS=9
LF=14
LS=14
LF=15
Duration = 15 weeks
The McGraw-Hill Companies,
25
26
Immediate Expected
Predecesors
Time
None
7
None
5.333
A
14
A
5
C
11
D
7
B
11
E,F
4
G,H
18
66
ET(A)=42/6=7
ET(A)=42/6=7
Immediate
Task Predecesors Optimistic Most Likely Pessimistic
A
None
3
6
15
B
None
2
4
14
C
A
6
12
30
D
A
2
5
8
E
C
5
11
17
F
D
3
6
15
G
B
3
9
27
H
E,F
1
4
7
I
G,H
4
19
28
Opt.
Time
++ 4(Most
Likely
Time)
++ Pess.
Time
Opt.
Time
4(Most
Likely
Time)
Pess.
Time
Expected
ExpectedTime
Time ==
66
The McGraw-Hill Companies,
27
Immediate Expected
Predecesors
Time
None
7
None
5.333
A
14
A
5
C
11
D
7
B
11
E,F
4
G,H
18
ET(B)=
ET(B)=2+4(4)+14
2+4(4)+14
66
ET(B)=32/6=5.333
ET(B)=32/6=5.333
Immediate
Task Predecesors Optimistic Most Likely Pessimistic
A
None
3
6
15
B
None
2
4
14
C
A
6
12
30
D
A
2
5
8
E
C
5
11
17
F
D
3
6
15
G
B
3
9
27
H
E,F
1
4
7
I
G,H
4
19
28
Opt.
Time
++ 4(Most
Likely
Time)
++ Pess.
Time
Opt.
Time
4(Most
Likely
Time)
Pess.
Time
Expected
ExpectedTime
Time ==
66
The McGraw-Hill Companies,
28
Immediate Expected
Predecesors
Time
None
7
None
5.333
A
14
A
5
C
11
D
7
B
11
E,F
4
G,H
18
ET(C)=
ET(C)=6+4(12)+30
6+4(12)+30
66
ET(C)=84/6=14
ET(C)=84/6=14
Immediate
Task Predecesors Optimistic Most Likely Pessimistic
A
None
3
6
15
B
None
2
4
14
C
A
6
12
30
D
A
2
5
8
E
C
5
11
17
F
D
3
6
15
G
B
3
9
27
H
E,F
1
4
7
I
G,H
4
19
28
Opt.
Time
++ 4(Most
Likely
Time)
++ Pess.
Time
Opt.
Time
4(Most
Likely
Time)
Pess.
Time
Expected
ExpectedTime
Time ==
66
The McGraw-Hill Companies,
29
Example 2. Network
Duration = 54 Days
C(14)
E(11)
H(4)
A(7)
D(5)
F(7)
I(18)
B
(5.333)
G(11)
The McGraw-Hill Companies,
30
p(t < D)
D=53
TE = 54
t
DD -- TTEE
ZZ ==
22
cpcp
The McGraw-Hill Companies,
31
Pessim.
-- Optim.
Pessim.
Optim.)22
Activity
variance,
=
(
Activity variance, = (
)
66
22
Task
A
B
C
D
E
F
G
H
I
22
41
== 41
The McGraw-Hill Companies,
32
p(t < D)
t
TE = 54
D=53
D
D -- TTEE 5353-54
54
ZZ ==
==
== -.156
-.156
22
41
41
cpcp
p(Z
p(Z <<-.156)
-.156) ==.438,
.438, or
or 43.8
43.8 %
% (NORMSDIST(-.156)
(NORMSDIST(-.156)
There
There isis aa 43.8%
43.8% probability
probability that
that this
this project
project will
will be
be
completed
completed in
in less
less than
than 53
53 weeks.
weeks.
The McGraw-Hill Companies,
33
What
What isis the
the probability
probability that
that the
the project
project
duration
duration will
will exceed
exceed 56
56 weeks?
weeks?
34
TE = 54
t
D=56
D
-- TTEE 56
--54
D
56
54
ZZ ==
=
== .312
.312
22 =
41
41
cp
cp
p(Z
p(Z>>.312)
.312) == .378,
.378, or
or 37.8
37.8 %
%(1-NORMSDIST(.312))
(1-NORMSDIST(.312))
The McGraw-Hill Companies,
35
Time-Cost Models
Basic Assumption: Relationship between
activity completion time and project cost
Time Cost Models: Determine the
optimum point in time-cost tradeoffs
36
CPM Assumptions/Limitations
Project activities can be identified as entities (There
is a clear beginning and ending point for each
activity.)
37
End of Chapter 3