Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
On
ANTA GAS POWER STATION, NTPC Ltd
SESSION (2013-2014)
SUBMITTED TO:
Mr. Vaibhav Jain ( HOD)
4th year
SUBMITTED BY:
Praveen Kumar Gocher
(Deptt. Of Electrical Engg. )
10EPCEE091,
Content
Introduction of NTPC
Profile of NTPC anta
Electricity generation process
Major parts
Generator
Cooling tower
Transformer
Switchyard
DG Set
Conclusion
Introduction
NTPC, the largest power Company in India, was setup
in 1975 to accelerate power development in the country.
NTPC has installed capacity of 29,394 MW.
It has 15 coal based power stations (23,395 MW)
7 gas based power stations (3,955 MW).
4 power stations in Joint Ventures (1,794 MW).
The company has power generating facilities in all
major regions of the country.
It plans to be a 75,000 MW company by 2017.
Station
Approved capacity
419.3MW
Gas source
Water source
Units commissioned
Beneficiary states
Approved Investment
International Assistance
Generator
Cooling tower
Transformer
Switchyard
Controal room
IEC 60034
Generator Type
WY18L-095LL
Apparent Power
135 MVA
Terminal Voltage
10.5 kV
Rated Current
7423 A
Frequency
50 Hz
Speed
3000 RPM
Type of Cooling
Air Cooled
No. of Phases
3 Phases
Excitation System
Weight of Stator
131 T
Weight of Rotor
31 T
Applicable Standard
IEC 60034
Generator Type
WX21L-100LL
Apparent Power
191.6 MVA
Terminal Voltage
15.75 kV
Rated Current
7024 A
Frequency
50 Hz
Speed
3000 RPM
Type of Cooling
Air Cooled
No. of Phases
3 Phases
Excitation System
Weight of Stator
170 T
Weight of Rotor
42 T
Type
- Induced Draft
Make
- Paharpur
No. Of cells
- 11
Water capacity
- 31320 m3/hr
Air flow dry
- 31280 m3/hr
Gearbox ratio
- 12.98 : 1
No. Of blades/ fan - 8
Fan diameter
- 10 m
Fan rpm
- 114
Motor rating
- 115 kw
SWITCH YARD
No. of bays
Generator bays
Spare bay
Rated Current
1250 Amp
Fault Current
31.5 KA
Minimum clearance
Phase to Phase Clearance
2700 mm
2300 mm
Ground clearance
2580 mm
Section clearance
4500 mm
EMERGENCY DG SET
NUMBER OF CYLINDER
CYLINDER CONFIGURATION
OPERATING PROCESS
12
- Vee -Form
Four Stroke
COMBUTION PROCESS
CYLINDER SIZE
- Dia240*280mm
STROKE/BORE RATIO
OUT PUT
- Direct Injection
- 1.167
- 2.4 MW
RATED SPEED
- 1000 RPM
COMPRESSION RATIO
FUEL CONSUPTION
AIR REQUIRED
- 11.59
- 210g/Kwh
- 17100 m3/hr
CONCLUSION
Generation of electricity process using using Gas.
NTPC ANTA plant has created a benchmark in
technology utilization, efficiency and effective
utilization of resources.
Working of gas and stream generator.
CTs ,PTs , gas and stream transformer, cooling
tower , isolator, corona ring working.
CT and CW motor use.