Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
The Port of Redwood City plays a key role in Bay area Port infrastructure
system
Wharves 3 and 4
SIMS Metal
HS&G/CEMEX Yard
Wharves 1 and 2
Wharves 1 and 2 are critical to present and future cargo activity at the Port
Berth conflicts between Wharves 1 and 2 and the cement berth demand
attention. Need to partially accommodate two ships simultaneously to
increase efficiency and berth capacity.
Demolition Plan
Recommend complete removal of existing timber wharf system
Cost Estimates
Environmental Document Preparation:
Historic Evaluation of Warehouse #1:
$85,000
EA/ND:
$190,000
EIS/EIR:
$10,000 to $12,000
Cost Estimates
Site Redevelopment Plan:
Landside infrastructure improvements: $996,000
Cost includes:
Cost excludes:
Project Schedule
DESIGN-BID-BUILD vs. DESIGN-BUILD:
Port advertises for and selects an A/E Firm to design the project
Second advertisement and selection for a contractor to build the project using
A/E Firms plans and specifications
Traditional contracting method
A/E Firm works for Port and Port has more input into details of design
Design-Build:
Port advertises for and selects an A/E-Contractor team to design and construct
the project
Generally results in an overall reduction in project cost and shorter schedule to
delivery
Disputes between A/E Firm and Contractor eliminated
Has recently become the contracting method of choice for many owners
RECOMMENDATION:
Project Schedule
OVERALL PROJECT SCHEDULE:
Time-line from the start of Environmental Documents to
completion:
Design-Bid-Build contract: 30 to 33 months (EA/ND or
EIS/EIR)
Design-Build contract: 24 to 27 months
ENVIRONMENTAL DOCUMENTS and PERMITTING:
Project Schedule