Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Session 5
Risk, Force Majeure &
Termination
Contractor must take full responsibility for the care of the Works
and Goods from the Commencement Date until the TOC is
issued (or deemed issued).
If any loss or damage occurs to the Works during this period
other than a matter listed as an Employers Risk, the Contractor
shall rectify the loss or damage at his own risk and cost.
Contractor will be liable for any damage caused by his actions
after the issue of the TOC.
1.
1.
War, hostilities, invasion, act of foreign enemies
2.
Rebellion, terrorism, sabotage by persons other than the Contractors Personnel,
revolution, civil war, etc.
3.
Riot, commotion or disorder within the Country
4.
Munitions of war, explosives, radiation, radio-activity within the Country
5.
Pressure waves caused by aircraft,
6.
Use or occupation by the Employer of any part of the Permanent Works, except as
specified in the Contract.
2.
Liability & Insurance (Clause 18)
FIDIC contracts require the following to be insured:
Works & Contractors Equipment
Injury to Persons & Damage to Property
Contractor's Personnel
The insurances are to be taken out by the Insuring Party who is the Contractor unless
otherwise stated in the Particular Conditions.
Evidence of insurance & copies of policies are to be provided - within period stated in
Contract Data.
If the Insuring Party fails to take out or maintain the insurances, the
other Party may do so and claim reimbursement of the cost from the
Insuring Party.
If neither Party takes out the insurances, in the event of loss or damage,
the Insuring Party shall pay the amount that should have been
reimbursed under the insurances.
If, more than a year after the Base Date, the Contractor can no longer
obtain insurance for the Works on commercially reasonable terms, he
must inform the Employer who will then be entitled to claim payment
from the Contractor of an amount equivalent to commercially
reasonable terms but he will be deemed to have accepted the lack of
insurance cover.
3.
1.
fails to maintain an acceptable Performance Security;
abandons the Works or plainly demonstrates an intention not to comply with any of
his obligations under the Contract;
3.
fails to expedite progress of the Works or to comply with instructions to rectify
defects within 28 days of receipt;
4.
subcontracts the whole of the Works;
5.
becomes bankrupt or insolvent, enters into liquidation or dissolution;
6.
gives or offers any bribe, gift, gratuity or commission;
7.
fails to comply with a notice of remedial action.
3.
Employer is entitled to terminate the Contract at any time for his own
convenience by giving notice to the Contractor (Clause 15.5).
Termination takes effect 28 days after the later of the dates on which the
Contractor receives the notice or the Employer returns the
Contractors Performance Security.
3.
3.
The Contractor is entitled, subject to giving 21 days notice, to reduce his rate
of work or to suspend work:
if the Engineer fails to issue the IPC within 28 days;
Employer fails to pay the Contractor within the times prescribed;
Employer fails to provide proof of his financial arrangements within 28 days.
Full amount certified by the Engineer must be paid, subject, to any deductions
the Employer is entitled to make.
Employers partial payment:
does not affect the Contractors entitlement;
Engineer should immediately advise the Employer in writing of the
risk of suspension and/or termination.
4.
4.
4.
5.
5.
Force Majeure
If a Party is or will be prevented from performing its substantial obligations
under the Contract by Force Majeure, it must give notice to the other Party
of the event and specifying the obligations, the performance of which is
prevented. The notice must be given within 14 days of becoming aware or
when the Party should have become aware of the event.
Having given notice, the Party is excused from performance for so long as
the Force Majeure prevents performance except with respect to
obligations to pay the other Party under the Contract.
5.
Force Majeure
If the Contractor is prevented from performing its substantial obligations by
Force Majeure and has given notice to the Employer, he shall be entitled to:
an extension of time with respect to delay incurred, and
reimbursement of his Costs unless the Force Majeure event was:
a natural catastrophe, or
5.
Force Majeure
Contract may be terminated if a Party is or will be prevented by Force
Majeure from performing its obligations for a continuous period of 84
days or for multiple periods totalling more than 140 days due to the
same Force Majeure event.
In such circumstances, the Party seeking to terminate must give notice
to the other Party and the notice shall take effect 7 days after being
given.
5.
Force Majeure
After notice of termination:
Contractor ceases all further work, except as may be instructed for the
safety of life, property and the Works;
Contractor hands over to the Employer any documents, etc. for which he
has received payment;
Contractor removes from Site all his Equipment and facilities, and leaves
the Site;
Employer returns the Contractors Performance Security.
Engineer shall determine and Employer must pay to the Contractor (less
any deductions to which the Employer is entitled under the Contract) as for
termination by the Contractor, except loss of profit.
End of Session 5
Sarwono Hardjomuljadi
Dr, Ir, MSc (Civ), MSBA (Bus), MH (Law), MDBF, ACIArb, ACPE