Sei sulla pagina 1di 414

ding Professionalism in Project Managem

ManagementFramework
Framework
Project Management

Version 1.0

Course Objective
To familiarize participants with Project Management
Body of Knowledge Guide (Fourth Edition) by
explaining the concepts, processes, and techniques
of Project Management.

ManagementFramework
Framework
Project Management

Version 1.0

What the exam will test?


Your knowledge about PMIs processes and your ability to
apply these processes in a variety of situation.
Your understanding of the many terms that are used to
describe the process.

Your understanding of professional responsibility as it


applies to project management.

ManagementFramework
Framework
Project Management

Version 1.0

Learning Strategies
20 / 80 approach
Learn PMPism
Emphasis on learning exercise
Gaining understanding through review
exercise and class discussions
Remove friction in reading PMBOK Guide

PMBOK is a registered mark of the Project Management Institute, Inc

ManagementFramework
Framework
Project Management

Version 1.0

PROJECT MANAGEMENT FRAMEWORK

Project Management Framework

ManagementInstitute,
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Inc

Version 1.0

Course Structure
Project Management Framework
Introduction
PMBOK Guide
Define a Project
Define Project Management
Correlation among Project, Program, and Portfolio Management
Project Management Office (PMO)
Project and Operations Management
Role of a Project Manager
Enterprise Environmental Factors

Project Life Cycle and Organization


Project Life Cycle - Introduction

Projects Life Cycle - Characteristics


Product vs. Project Life Cycle Relationship
ManagementFramework
Framework
Project Management

Version 1.0

Course Structure
Projects Phases
Project Governance
Phase-to-Phase Relationship
Relationship between Stakeholders and the Project
Types of Stakeholders
Organizational Influences on Project Management

Project Management Processes for a Project


Project Process - Introduction

Common Project Management Process Interaction


Project Management Process Group - Flow

ManagementFramework
Framework
Project Management

Version 1.0

Project Management Framework Introduction

ManagementFramework
Framework
Project Management

Version 1.0

Project Management Body of Knowledge


(PMBOK) - Introduction
Sum of knowledge within the profession of Project
Management.
Practitioners & Academicians apply and advance it.
Includes proven traditional practices, as well as
innovative and advanced practices.
Is constantly evolving.

PMBOK is a registered mark of the Project Management Institute, Inc

ManagementFramework
Framework
Project Management

Version 1.0

PMBOK Guide
PMBOK Guide is a recognized standard for the project management
profession.
Project Management Institute (PMI) views these standards as a foundation
reference.
PMBOK Guide identifies (provides a general overview) the subset of Body of
Knowledge that is generally recognized as good practices and promotes a
common lexicon.

PMBOK is a registered mark of the Project Management Institute, Inc

ManagementFramework
Framework
Project Management

Version 1.0

10

Code of Ethics and Professional Conduct


PMI Code of Ethics and Professional Conduct:
Guides practitioners of the Project Management Profession
Describes expectations practitioners have of themselves and others

Code of Ethics and Professional Conduct is specific about:


Obligation of Responsibility to comply with laws, regulations and

organizational and professional policies


Respect, fairness, and honesty to deal with the stakeholders

Acceptance of the code is a requirement for the PMP


certification by PMI.

ManagementFramework
Framework
Project Management

Version 1.0

11

Project
A project is a temporary endeavor undertaken to create a unique product, service, or
result.

Every project has a definite beginning and a definite end.

A project creates unique deliverables in the form of products, services, or results.


(Repetitive elements may be present in some project deliverables, which does
not change the fundamental uniqueness of the project work.)

Uniqueness is an important characteristic of


projects deliverables.

A project ends as a result of one of the following:


Project objectives have been achieved.
It becomes clear that the project objectives
cannot be met.
The need for the project no more exists.
Continue
ManagementFramework
Framework
Project Management

Version 1.0

12

Project Continue
A project can involve:

A single person
A single Organization
Multiple Organizational Units

A project can create:

A product that can be either a component of another item or an end item in itself
A capability to perform a service
A result such as a outcome or document

ManagementFramework
Framework
Project Management

Version 1.0

13

Project Management
1.

Project Management is the application of knowledge, skills, tools, and techniques


to project activities to meet project requirements.

2.

Project Management is accomplished through the application and integration of


project management processes in 5 process groups - Initiating, Planning,
Executing, Monitoring and Controlling, and Closing.

3.

The project manager is the person responsible for


accomplishing the project objectives.

4.

Project managers often talk of Project Constraints


which includes: project scope, quality, time, cost,
resources, and risk in managing competing project
requirements.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

14

Project Management Continues


Progressive Elaboration
Progressive Elaboration means
developing and continuing by
increments.
Project objectives, scope and
deliverables are progressively
elaborated.
Progressive Elaboration should not
be confused with scope creep.

ManagementFramework
Framework
Project Management

Version 1.0

15

Project, Program, and Portfolio Management


Project management exists in a broader context that includes :
Portfolio Management
Program Management
Project Management

Project prioritization is
based on:
Risk
Funding
Organizational Strategic

Plan
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 1-1. Page 8.

ManagementFramework
Framework
Project Management

Version 1.0

16

Program Management
Program:
A group of related projects
Individual project management is not available
Includes elements of related work outside the scope

Program Management focuses on:


Project Interdependencies
Optimal approach for managing them

Projects within programs are related through common outcome or collective


capability
A project may or may not be a part of a program but a program will always
have projects.

ManagementFramework
Framework
Project Management

Version 1.0

17

Portfolio Management
Portfolio:
Collection of projects or programs
Facilitate effective management to meet business objectives
Not interdependent or directly related to projects or programs

Portfolio Management being a centralized management includes :

Identifying
Prioritizing
Authorizing
Managing and
Controlling all programs and projects

Senior managers or senior management teams typically take on the responsibility


of portfolio management for an organization.
Project, Program, and Portfolio Management on certain parameters
ManagementFramework
Framework
Project Management

Version 1.0

18

Project and Strategic Planning


Projects are:
Means of achieving an organizations strategic plan
Authorized to follow strategic considerations

Strategic Considerations:

Market Demand
Business Need
Customer Request
Technological Advance
Legal Requirement

An organizations strategic plan becomes the


primary factor guiding investments in projects.

ManagementFramework
Framework
Project Management

Version 1.0

20

Project Management Office (PMO)


PMO is an organizational unit to centralize and coordinate the management
of projects under its domain.
PMO:

Acts as an integral stakeholder


A key decision maker
Involved in selection, management, and
deployment of resources

PMO supports Project Managers in:

Identifying and developing project management standards


Coaching, mentoring, and training
Managing shared resources
Developing, managing, and monitoring project policies and procedures
Coordinating across projects

ManagementFramework
Framework
Project Management

Version 1.0

21

PMO and Project Manager


PMOs and Project Managers follow different objectives but the final aim is to
achieve the strategic needs of the organization.
Difference between the role of PMO and Project Manager:

PMO

Project Manager

Focuses on achieving potential


business objectives.

Focuses on achieving specified project


objectives.

Optimizes the use of shared resources


across all projects.

Controls the assigned project resources.

Manages methodologies, standards,


risk/opportunity, and interdependencies
among projects at enterprise level.

Manages project constraints such as


scope, schedule, cost, etc. of an
individual project.

ManagementFramework
Framework
Project Management

Version 1.0

22

Project and Operations Management


Operations are ongoing and repetitive while projects are temporary and
unique.
The purpose of a project is to attain
its objectives (and then terminate).
The objective of an ongoing operation is
to sustain the business.
Project intersect with operations during project life
cycle at various points:

Each closeout phase


Developing a new product
Upgrading a product
Improvements in operations
Divestment of the operations at the end of the product life cycle
ManagementFramework
Framework
Project Management

Version 1.0

23

Role of a Project Manager


A Project Manager is the person assigned by an organization to
achieve
objectives of the project.

Characteristics a Project Manager :

Knowledge What the project manager knows


Performance How the project manager applies

the knowledge
Personal How the project manager behaves
while performing the project

ManagementFramework
Framework
Project Management

Version 1.0

24

Project Life Cycle and Organization

ManagementFramework
Framework
Project Management

Version 1.0

25

Project Life Cycle Introduction

A project life cycle is a collection of generally sequential and


sometime overlapping project phases.

Project managers or the organization can divide projects into


phases to provide better management control with appropriate
links to the ongoing operations of the performing organization and
these phases are known as the Project Life Cycle.

Many organizations identify a specific set of life cycles for use on


all their projects.

ManagementFramework
Framework
Project Management

Version 1.0

26

Project Life Cycle - Characteristics


Most Project Life Cycles share a number of common characteristics:
1. Phases are generally sequential.

2. Cost and staffing levels are low at the start, peak during the intermediate phases,
and drop rapidly as the project draws to a conclusion.

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 2-1. Page 16.

ManagementFramework
Framework
Project Management

Continue

Version 1.0

27

Project Life Cycle - Characteristics


3.

The ability of stakeholders to


influence the project outcome
and cost is highest at the start
and gets progressively lower
as the project continues.

4.

Risk is greatest at the start of


the project and gets
progressively lower as the
project continues.

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 2-2. Page 17.

ManagementFramework
Framework
Project Management

Version 1.0

28

Product vs. Project Life Cycle Relationships


(As per PMBOK Guide)

PMBOK is a registered mark of the Project Management Institute, Inc

ManagementFramework
Framework
Project Management

Version 1.0

29

Project Phases
Project Phases are:
Divisions within a project for extra control to manage the completion of a deliverable effectively
Typically sequential but can overlap in some projects
Elements of the project life cycle
Segmented into logical subsets for easy management

Characteristics of Phases:
The close of a phase ends with some form of

transfer, usually when phases are sequential


Primary objective of the phase requires an

extra degree of control to be successful

No single way to define the ideal structure for a

project
Continue
ManagementFramework
Framework
Project Management

Version 1.0

30

Project Phases

Single Phase

Multiple Phases

Projects having only one phase


Sequential

Overlapping

Phase starts once


the earlier phase
is complete

Phase starts prior


to the completion
of the previous
phase
ManagementFramework
Framework
Project Management

Iterative
Planning of the next
phase depends on
the planning of the
current phase

Version 1.0

31

Project Governance
Project Governance:
A comprehensive, consistent method of controlling the project
Should be included in the project management plan
Must fit within the larger context of the program

Project Governance is facilitated by:


Phase structure which provides a formal basis for control
Review of the deliverables to determine completeness and

acceptance
A natural point to reassess the effort underway to change or
terminate the project
Formal phase completion which does not include authorizing the
subsequent phase

ManagementFramework
Framework
Project Management

Version 1.0

32

Project Stakeholders
1.

Project stakeholders are individuals and organizations that are :


actively involved in the project or
whose interests may be affected as a result of project execution or
completion or
may exert influence over the projects objectives and outcomes.

2.

The project management team must identify the stakeholders and manage their
influence in relation to the requirements to ensure a successful project.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

33

The Relationship Between Stakeholders and


the Project

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 2-6. Page 24.

ManagementFramework
Framework
Project Management

Continue
Version 1.0

34

Organizational Influences
Organizational Influences on Project Management:
Culture, Style, and Structure
Degree of project management maturity
Involvement of external entitles as a part of a joint venture

Continue
ManagementFramework
Framework
Project Management

Version 1.0

35

Organizational Culture and Style


Organizational cultures and styles may have a strong influence on a
projects ability to meet its objectives.

The cultures are reflected in numerous factors including:


1.
2.
3.
4.

Shared values, norms, beliefs, and expectations


Policies and procedures
View of authority relationships
Work ethics and work hours

Continue
ManagementFramework
Framework
Project Management

Version 1.0

36

Organizational Structure
The structure of the performing organization often constraints the availability of
resources in a spectrum from functional to projectized, with a variety of matrix
structures in between.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

37

Organizational Process Assets

Processes & Procedures

Corporate Knowledge Base

For conducting organizations work, which


includes but not limited to:
Organizational standard processes

Standardized guidelines, work


instructions, etc.
Guidelines and criteria for tailoring set
of standard processes
Organization communication
requirement
Project closure requirements
Financial, Change, and risk control
procedures

For storing and retrieving organizational


information, which includes but not
limited to:
Process measurement databases
Project files
Historical information and lessons
learned knowledge base
Issue and defect management
databases
Configuration management
knowledge databases
Financial databases

ManagementFramework
Framework
Project Management

Version 1.0

38

Enterprise Environment
Factors:

ManagementFramework
Framework
Project Management

Version 1.0

39

Project Management Processes


For a Project

ManagementFramework
Framework
Project Management

Version 1.0

40

Project Process - Introduction


A Process is a set of interrelated actions and activities that are performed to
achieve a pre-specified set of products, results, or services.
Project processes are performed by Project Team.

Ensure effective flow throughout the project

Specify and create the project products

Includes tools and techniques in applying skills


and capabilities

Defined by the project life cycle


Vary by application area

ManagementFramework
Framework
Project Management

Version 1.0

41

Project Management Process Groups


Project management processes are grouped into five categories known
as project management process groups or process groups.
These process groups are:

1.

Initiating Process Group:

To define a new project or a new phase of an existing project

Obtains authorization

2.

Planning Process Group:

To establish the scope of the project

Refine the objectives

Define the course of action


Continue
ManagementFramework
Framework
Project Management

Version 1.0

42

Project Management Process Groups


3.

Executing Process Group:

To complete the defined work in the project

Satisfy the project specifications in the project management plan

4.

Monitoring and Controlling Process Group:

To track, review, and regulate projects progress and performance

Identifies the areas where changes are required

Initiates the required changes

5.

Closing Process Group:

To finalize all activities to formally close the project or phase

ManagementFramework
Framework
Project Management

Version 1.0

43

Common Project Management Process


Interactions
Following figure shows the integrative nature of project management that requires
the Monitoring and Controlling Process Group to interact with the other process
groups.

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 3-1. Page 40.

ManagementFramework
Framework
Project Management

Continue
Version 1.0

44

Common Project Management Process


Interactions

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 3-2. Page 41.

ManagementFramework
Framework
Project Management

Version 1.0

45

Definitions
(As per PMBOK Guide)
Input: Any item, whether internal or external to the project that is
required by a process before that process proceeds. May be an output
from a predecessor process.
Tool: Something tangible, such as a template or software program,
used in performing an activity to produce a product or result.
Technique: A defined systematic procedure employed by a human
resource to perform an activity to produce a product or result or
deliver a service, and that may employ one or more tools.
Output: A product, result, or service generated by a process.
May be an input to a successor process.

PMBOK is a registered mark of the Project Management Institute, Inc

ManagementFramework
Framework
Project Management

Version 1.0

46

Project Management Framework

ManagementInstitute,
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Inc

Version 1.0

47

Before we begin

ManagementFramework
Framework
Project Management

Version 1.0

48

Everyone respects your time, do


you?

Come on time, Promptly return from the brea


49
ManagementFramework
Framework
Project Management

Version 1.0

Age and experience maketh a good manager

sometimes...not always

ManagementFramework
Framework
Project Management

Version 1.0

50

Your phone looks better

when switched off or silent


ManagementFramework
Framework
Project Management

Version 1.0

51

Involvement is the key

not mere

ManagementFramework
Framework
Project Management

Version 1.0

52

Be here

and only here

ManagementFramework
Framework
Project Management

Version 1.0

53

Listen to others

before you start correcting


ManagementFramework
Framework
Project Management

Version 1.0

54

Thank you!!!
ManagementFramework
Framework
Project Management

Version 1.0

55

PROJECT INTEGRATION MANAGEMENT

The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Institute,
Inc
Management
Framework
Management
Framework

Version 1.0

56

Course Structure
Project Integration Management
Introduction
Integration Management Introduction

Develop Project Charter


Develop Project Charter : Inputs, Tools, and Outputs

Develop Project Management Plan


Develop Project Management Plan : Inputs, Tools, and Outputs

Direct and Manage Project Execution


Develop and Manage Project Execution : Inputs, Tools, and Outputs

Monitor and Control Project Work


Monitor and Control Project Work : Inputs, Tools, and Outputs

Perform Integrated Change Control


Perform Integrated Change Control : Inputs, Tools, and Outputs

Close Project
Close Project : Inputs, Tools, and Outputs
ManagementFramework
Framework
Project Management

Version 1.0

57

Introduction

ManagementFramework
Framework
Project Management

Version 1.0

58

Project Integration Management Introduction


What is Integration?
It is the processes required to ensure that the various elements (people,
product, etc.) of the project are appropriately coordinated with each
other.

ManagementFramework
Framework
Project Management

Version 1.0

59

Project Integration Management Introduction

It is a unique knowledge area and it is the core of project management.

It includes processes and activities needed to identify, define,


combine, unify, and coordinate between the various processes and
project management activities within the project management process
group.
It involves putting the pieces of the project together into a cohesive
whole, while managing trade offs among the different project
objectives and alternatives to meet or exceed stakeholders needs and
expectations.
It involves selection about:
Resource Allocation
Balancing among competing objectives
and alternatives
Managing interdependencies among
project management knowledge areas

ManagementFramework
Framework
Project Management

Version 1.0

60

Project Integration Management Processes


(As per PMBOK Guide)
Develop Project Charter (Initiating) process of developing a document that
formally authorizes a project or a phase and documenting initial
requirements that satisfy the stakeholder's needs and expectations.
Develop Project Management Plan (Planning) process of documenting the
actions necessary to define, prepare, integrate, and coordinate all subsidiary
plans.
Direct and Manage Project Execution (Executing) process of performing the
work defined in the project management plan to achieve the projects
objectives.
Monitor and Control Project Work (Monitoring & Controlling) process of
tracking, reviewing, and regulating the progress to meet the performance
objectives defined in the project management plan.
Continue

PMBOK is a registered mark of the Project Management Institute, Inc

ManagementFramework
Framework
Project Management

Version 1.0

61

Project Integration Management Processes


(As per PMBOK Guide)
Perform Integrated Change Control (Monitoring & Controlling) process of
reviewing all change requests, approving changes, and managing changes to
the deliverables, organizational process assets, project documents, and the
project management plan.
Close Project or Phase (Closing) process of finalizing all activities across all
of the project management process groups to formally complete the project
or phase.
These processes:
Interact with each other and with the processes in the other Knowledge
Areas
Occur at least once in every project or project phases
Continue

PMBOK is a registered mark of the Project Management Institute, Inc

ManagementFramework
Framework
Project Management

Version 1.0

62

Project Integration Management Processes

Project Management
Plan

Planning

Executing
Changes

Planning process group provides the Executing process group with a


documented project management plan during the early stage of the
project.
Later, it facilitates updates to the project management plan if changes
occur during the progress of the project.
ManagementFramework
Framework
Project Management

Version 1.0

63

Develop Project Charter


Who can authorize Projects?
Projects are authorized by someone external to the
project:
A sponsor
PMO
Portfolio steering committee
Project charter is the process of developing a document that:
Formally authorizes a project or a phase.
Jot downs initial requirements.
Establishes a partnership between the
performing organization and the requesting organization
(Internal Project) and performing organization and Customer
(External Project).
Continue
ManagementFramework
Framework
Project Management

Version 1.0

65

Process - Develop Project Charter


The Project Manager is identified and assigned to the project as early as
possible,
but always prior to the start of planning, and preferably while Project Charter
is
being developed.
Project charter provides the project manager with the authority to apply
resources
to initiator or sponsor should be at a level
The project
project
that
is activities.
appropriate to funding the project.
Chartering a project links the project to the strategy and ongoing
work of the organization. (Internal)

ManagementFramework
Framework
Project Management

Version 1.0

66

Develop Project Charter Inputs, Tools, and Outputs

Project statement of work


Expert judgment
- Business need
- Product scope description
- Strategic plan
Business case
Contracts
Enterprise environmental factors
Organizational process assets

ManagementFramework
Framework
Project Management

Project charter

Version 1.0

67

Develop Project Charter Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-3 Page 74.

ManagementFramework
Framework
Project Management

Version 1.0

68

Develop Project Charter: Outputs


Project Charter
Project charter documents:
Business needs

Current understanding of customers needs


New product, service, or result
Project purpose
Measurable project objectives and related success criteria
High-level requirements
High-level project description
High-level risks
Summary milestone schedule
Summary budget
Project approval requirements
Responsibility and authority level of project manager, sponsor, or other

persons

ManagementFramework
Framework
Project Management

Version 1.0

69

Process - Develop Project Management Plan

It defines how the project is executed, monitored and controlled, and


closed.

Its content will differ depending upon the application area and
complexity of the project.
Project management processes selected by the project
management team
Level of implementation of each selected process
Description of the tools and techniques to be used
How the selected processes will manage the
dependencies, interactions, inputs, and outputs
among processes

It is updated, controlled, and approved through the


Perform Integrated Change Control process.
ManagementFramework
Framework
Project Management

Version 1.0

71

Develop Project Management Plan Inputs, Tools,


and Outputs

Project charter
Outputs from planning
processes
Enterprise environmental f
actors
Organizational process as
sets

Expert judgment

ManagementFramework
Framework
Project Management

Project management plan

Version 1.0

72

Develop Project Management Plan

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-5 Page 79.

ManagementFramework
Framework
Project Management

Version 1.0

73

Develop Project Management Plan: Outputs


Project Management Plan
Integrates and consolidates all of the subsidiary management plans
and baselines from the planning processes.
It includes:
Project Life cycle
Project management

processes
tailored to that project
Subsidiary Plans
Other baselines

Continue
ManagementFramework
Framework
Project Management

Version 1.0

74

Develop Project Management Plan: Outputs


What is performance measurement baseline?
A performance measurement baseline is the combination of:
Schedule baseline
Cost performance baselines
Scope baseline
These baselines are used as an overall project baseline against which
integrated performance can be measured.
The performance measurement baseline is used for earned
value measurement.

Can you think of other baselines?


Quality

ManagementFramework
Framework
Project Management

Version 1.0

75

Process - Direct and Manage Project Execution


The process of performing the work defined in the project management plan
to achieve the projects objectives.
What type of different activities could be included?
Perform activities to accomplish project requirements
Create project deliverables
Staff, train, and manage the team members
Obtain, manage, and use resources (material, tools, etc.)
Implement the planned methods and standards
Establish and manage project communication channels (Internal and External)
Generate project data (Cost, schedule, technical and quality progress, status to facilitate
forecasting)
Issue change request and adapt approved changes
Manage risk and implement risk response activities
Manage sellers and suppliers
Collect and document lessons learned, and implement approved process improvement

activities

ManagementFramework
Framework
Project Management

Version 1.0

77

Direct and Manage Project Execution


It is directly affected by the project application area.
It requires implementation of approved changes covering:
Corrective actions that will bring anticipated project

performance into compliance with Project


Management Plan.
Preventive actions to reduce the probability of
potential negative consequences.
Defect repair request to correct product defects
found by quality process with a recommendation to
repair or replace the component.

ManagementFramework
Framework
Project Management

Version 1.0

78

Direct and Manage Project Execution Inputs,


Tools, and Outputs

Project management plan Expert judgment


Approved change requests Project management
The documented,
information system
authorized changes to
expand or reduce project
scope which may require
implementation of preventive
or corrective actions.
Enterprise environmental fact
ors
Organizational process asset
s

ManagementFramework
Framework
Project Management

Deliverables
Work performance
information
Change requests
Project management plan
updates
Project document update
s

Version 1.0

79

Direct and Manage Project Execution

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-7 Page 84.

ManagementFramework
Framework
Project Management

Version 1.0

80

Direct and Manage Project Execution:


Tools and Techniques
Who can be the experts?
Consultants, Stakeholders, Professional and technical associations and other
units within the organization.
Project management information system is a part of
the enterprise environmental factors.
It provides access to an automated tools, such as:
A scheduling software tool
A configuration management system
An information collection and distribution
system
Web interfaces to other online automated
systems
ManagementFramework
Framework
Project Management

Version 1.0

81

Direct and Manage Project Execution: Outputs


Deliverables: An approved deliverable is any unique and verifiable product to
perform a service to complete a process, phase, or project.
Work Performance Information: Collective information as the project
progresses. This includes:
Deliverables status
Schedule progress
Costs incurred
Change Requests: Issues found during the project work. These issues may
modify Project's: Policies or procedures, scope, cost, schedule or quality.
Requests for a change can
include:
Corrective action
Preventive action
Defect repair

Continue
ManagementFramework
Framework
Project Management

Version 1.0

82

Direct and Manage Project Execution: Outputs


Project management plan that may be updated include:
Requirement, Schedule, Cost, Quality, Human, Communications,

Risk, Procurement Management Plans


Project Baselines
Project documents that may be updated include:

Requirement documents
Project logs (issue, assumption, etc.)
Risk register
Stakeholder register

ManagementFramework
Framework
Project Management

Version 1.0

83

Process - Monitor and Control Project Work


The process of tracking, reviewing, and regulating the progress to meet
the performance objectives defined in the project management plan.

Monitoring includes:

Collecting
Measuring
Distributing performance information, and
Assessing measurements and trends to improve processes

Controlling includes:

Determining corrective or preventive actions


Replanning and following up on action plans
Continue
ManagementFramework
Framework
Project Management

Version 1.0

85

Monitor and Control Project Work


What type of different activities could be included?
Comparing actual project performance against the project
management plan.
Assessing performance to determine whether any corrective or
preventive actions are indicated, and recommending those actions as
necessary.
Identifying new risks and analyzing, tracking, and monitoring existing
project risks.
Maintaining an accurate, timely information base concerning the
project's product(s) and their associated documentation through
project completion.
Providing information to support status reporting, progress
measurement, and forecasting.
Providing forecasts to update current cost and current schedule
information.
ManagementFramework
Framework
Project Management

Version 1.0

86

Monitor and Control Project Work Inputs, Tools,


and Outputs

Project management plan


Performance reports
Enterprise environmental
factors
Organizational process as
sets

Expert judgment

ManagementFramework
Framework
Project Management

Change requests
Project management
plan
Project document u
pdates

Version 1.0

87

Monitor and Control Project Work

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-9 Page 90.

ManagementFramework
Framework
Project Management

Version 1.0

88

Monitor and Control Project Work Outputs


Change requests
Project management plan
Project document updates

Project Management Plan


Project Document

ManagementFramework
Framework
Project Management

Version 1.0

89

Process - Perform Integrated Change Control


It is performed from project inception through
completion.
The project management plan, scope statement, and other deliverables must
be maintained by carefully and continuously managing changes by:

Rejecting changes OR
Approving changes

Incorporate approved
changes
into revised baseline.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

91

Perform Integrated Change Control


What type of different activities could be included?
Influencing the factors that circumvent change control so

that only approved changes are implemented.


Reviewing, analyzing, and approving change requests promptly

(slow decision may negatively affect time, cost, or the feasibility


of a change)

Managing approved changes.


Releasing approved changes for incorporation into the project

management plan and project documents.


Reviewing, approving, or denying all recommended corrective

and preventive actions.


Coordinating changes across the entire project.
Documenting the complete impact ofProject
change
requests.
Management
Framework
Management
Framework

Continue
Version 1.0

92

Perform Integrated Change Control


Every (documented) change must be either accepted or rejected by
some authority.

Within the project management team OR

External organization
Many times, change control system includes a
change control board (CCB) responsible for
approving o rejecting change requests.
If the project is being provided under a contract,
then some proposed changes need to be
approved by the customer.

ManagementFramework
Framework
Project Management

Version 1.0

93

Note
Do not consider yourself an opponent of changes by
default, but you do need to manage changes and make
sure each change goes through the change control
system and that changes do not make their way through
the backdoor. So, when it comes to changes, the
keyword is control, not oppose.

ManagementFramework
Framework
Project Management

Version 1.0

94

Configuration Management System


A configuration management system with integrated change control
provides, a standardized, effective, and efficient way to manage approved
changes and baselines within a project.
Specifications of deliverables
and processes

Configuration control focuses


on
While

Change control focuses on

Identifying, documenting and


controlling changes to the
project and the product
baselines

Continue
ManagementFramework
Framework
Project Management

Version 1.0

95

Configuration Management System


Configuration management system, including change control
processes, accomplishes three objectives:
Establish an evolutionary method to consistently identify and
request changes to established baselines, and assess the value
and effectiveness of those changes.
Provides opportunities to continuously validate and improve the
project by considering the impact of each change.
Provides mechanism for the project management team to
consistently communicate all approved and rejected changes to
the stakeholders.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

96

Configuration Management System


Configuration management activities included in the integrated change
control processes are:
Configuration
Identification
Configuration status
accounting
Configuration verification and
audit

ManagementFramework
Framework
Project Management

Version 1.0

97

Perform Integrated Change Control Inputs, Tools,


and Outputs

Project management
plan
Work performance
information
Change requests
Enterprise environmenta
l factors
Organizational process
assets

Expert judgment
Change control
meetings

ManagementFramework
Framework
Project Management

Change request status


updates
Project management plan
updates
Project document updates

Version 1.0

98

Perform Integrated Change Control

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-11. Page 96.

ManagementFramework
Framework
Project Management

Version 1.0

99

Perform Integrated Change Control Outputs


Change request status updates
Project management plan updates
Project document updates

ManagementFramework
Framework
Project Management

Version 1.0

100

Process - Close Project or Phase

The process of finalizing all activities across all the Project Management
Process Groups to formally complete the project or phase.
Includes activities to investigate and document the reasons if a project
is terminated before completion.
Activities for administrative closure of the project or
phase:
Satisfy completion or exit criteria for the phase or
project
Transfer the projects products, services, or results
to the next phase or production or operations
Collect project or phase records, audit project
success or failure, gather lessons learned and
archive project information for future use.

ManagementFramework
Framework
Project Management

Version 1.0

102

Close Project or phase Inputs, Tools, and


Outputs

Project management
plan
Accepted deliverables
Organizational process
assets

Expert judgment

ManagementFramework
Framework
Project Management

Final product, service,


or result transition
Organizational
process assets
updates

Version 1.0

103

Close Project or Phase

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 4-13. Page 100.

ManagementFramework
Framework
Project Management

Version 1.0

104

Close Project or Phase - Outputs

Final product, service, or result transition:


- refers to the transition of the final product, service, or result
that the project was authorized to produce. (based on
transition criteria)

Organizational Process Assets Updates:


- includes project files, project or phase closure documents, and
historical information, etc.

ManagementFramework
Framework
Project Management

Version 1.0

105

Project Management Framework

ManagementInstitute,
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Inc

Version 1.0

106

PROJECT SCOPE MANAGEMENT

Management
Framework
Management
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Institute,
Inc

Version 1.0

107

Course Structure
Project Scope Management
Introduction
Project Scope Management - Introduction
Collect Requirements
Collect Requirements: Inputs, Tools, and Outputs
Define Scope
Define Scope: Inputs, Tools, and Outputs
Create WBS
Create WBS: Inputs, Tools, and Outputs
Verify Scope
Verify Scope: Inputs, Tools, and Outputs
Control Scope
Control Scope: Inputs, Tools, and Outputs

ManagementFramework
Framework
Project Management

Version 1.0

108

Introduction

ManagementFramework
Framework
Project Management

Version 1.0

109

Project Scope Management


The processes required to ensure that the
project includes all the work required, and only
the work required to complete the project
successfully.

It is primarily concerned with defining and


controlling what is and what is not included
in the project.

ManagementFramework
Framework
Project Management

Version 1.0

110

Project Scope Management - Processes


Collect Requirements: process of defining and documenting stakeholders needs to
meet the project objectives.
Define Scope: process of developing a detailed description of the project and
product.
Create WBS: process of subdividing
project deliverables and project work
into smaller, more manageable
components.
Verify Scope: process of formalizing
acceptance of the completed project
deliverables.
Control Scope: process of monitoring the status of the project and product scope
and managing changes to the scope baseline.

ManagementFramework
Framework
Project Management

Version 1.0

111

Product Scope vs. Project Scope


Product Scope:
The features and functions that characterize a product, service, or result.
Completion of the product scope is measured against the product requirements.
Project Scope:
The work that needs to be accomplished to deliver a product, service, or result with the
specified features and functions.
Completion of the project scope is measured against the project management plan.

ManagementFramework
Framework
Project Management

Version 1.0

112

Project Scope Management


The work involved in performing the five processes of Project Scope Management is
preceded by a planning effort by the project management team.
This planning effort is part of the Develop Project Management Plan process, This
includes:

Time,
Cost, and
Scope management
Scope Management Plan process provides
guidance on how project scope will be:

Defined
Documented
Verified
Managed, and
Controlled
ManagementFramework
Framework
Project Management

Version 1.0

113

Collect Requirements

ManagementFramework
Framework
Project Management

Version 1.0

114

Collect Requirements
The process of defining and documenting stakeholders needs to meet the project
objectives.
Categories of Requirements

Project Requirements

Product Requirements

Business Requirements

Technical Requirements

Project management Requirements

Security Requirements

Delivery Requirements

Performance Requirements

Continue
ManagementFramework
Framework
Project Management

Version 1.0

115

Collect Requirements
Requirements become the foundation of Scope definition.
Cost, schedule, and quality planning are built on these
requirements.
The development of requirements begins with an analysis
of the information contained in:

The project charter


The stakeholder register

ManagementFramework
Framework
Project Management

Version 1.0

116

Collect Requirements Inputs, Tools, and Outputs

Project Charter
Stakeholder register

Requirements documentation
Interviews
Requirements management
Focus groups
plan
Facilitated workshops
Group creativity techniques Requirements traceability
matrix
Group decision making techniques
Questionnaires and surveys
Observations
Prototypes

ManagementFramework
Framework
Project Management

Version 1.0

117

Collect Requirements Tools and Techniques


Technique Key Characteristics

Limitations

Interview

A formal or informal method to find


out information by talking to the
stakeholders directly
Often conducted one-on one

Analysis of the data


becomes difficult
Expensive and time
consuming
Interviewer can be biased

Focus groups

Bring stakeholders and subject


matter experts together to learn
about their expectations and
attitudes towards a proposed
product, service, or result
Trained moderator guides through
an interactive discussion
More conversational than a
one-on-one interview

Cost of finding a
moderator with good
facilitative skills and venue
May be dominated by one
or two participants only
Analysis of the data
becomes difficult and time
consuming

ManagementFramework
Framework
Project Management

Continue
Version 1.0

118

Collect Requirements Tools and Techniques


Technique Key Characteristics
Facilitated
Workshops

Group
Creativity
Technique

Sessions to bring key crossfunctional stakeholders together to


define product requirements
A primary technique for quickly
defining cross-functional
requirements and reconciling
stakeholder differences
Issues can be discovered and
resolved more quickly than in
individual sessions

Brainstorming
Nominal group technique
The Delphi technique
Idea/mind mapping
Affinity diagram
ManagementFramework
Framework
Project Management

Limitations
Difficult to keep focused,
clear purpose and desired
outcome
May be dominated by
powerful individuals

Analysis of the data


becomes difficult and time
consuming
May loose the focus of the
discussion
Continue
Version 1.0

119

Collect Requirements Tools and Techniques


Technique

Key
Characteristics

Group Decision

An assessment process of
multiple alternatives with an
expected outcome for future
actions
Used to generate, classify, and
prioritize product requirements
Multiple methods such as,
Unanimity, Majority, Plurality, and
Dictatorship

Time consuming
May be dominated by
powerful people
Problems and conflicts
occur due to non
acceptance of some
decisions

Written sets of questions


designed to quickly gather
information from wide number of
audiences
Statistical analysis is appropriate

No response for selective


items
Time consuming

Making
Techniques

Questionnaires
and Surveys

Limitations

Continue
ManagementFramework
Framework
Project Management

Version 1.0

120

Collect Requirements Tools and Techniques


Technique Key Characteristics

Limitations

Observations

A direct way of viewing individuals


in their environment and how they
perform their jobs or tasks
Can also be done by a participant
observer who actually performs a
process or procedure to experience
how it is done

May land up collecting


unimportant material
Unable to observe large
population
Data analysis can be time
consuming

Prototypes

A method of providing a working


model of the expected product
before actually building it
Allows stakeholders to experiment
with a model rather than only
discussing abstract representations

Too slow process


Time consuming and
expensive

ManagementFramework
Framework
Project Management

Version 1.0

121

Collect Requirements Outputs


Requirements Documentation: describes how individual
requirements meet the business need for the project.
Format of a requirements documents may be,

A simple document
listing all the
requirements
categorized by
stakeholder and priority

Elaborate forms containing


executive summary,
detailed descriptions, and
attachments

Continue
ManagementFramework
Framework
Project Management

Version 1.0

122

Collect Requirements Outputs


Requirements documentation include:
Business need or opportunity to be seized, describing the limitations of the
current situation and what the project has been undertaken
Business and project objectives for traceability
Functional requirements, describing business processes, information,
and interaction with the product, as appropriate which can be documented
textually in a requirements list, in models, or both
Non-functional requirements, such as level of service, performance, safety,
security, compliance, supportability, retention/purge, etc
Quality requirements
Acceptance criteria
Business rules stating the guiding principles of the organization
Impacts to other organizational areas, such as the call center, sales force,
technology groups
Impacts to other entities inside or outside the performing organization
Support and training requirements
Requirements assumptions and constraints
Continue
ManagementFramework
Framework
Project Management

Version 1.0

123

Collect Requirements Outputs


Requirements Management Plan: documents how requirements will
be analyzed, documented, and managed throughout the project.
Requirements Management Plan includes:
How requirements activities will be planned, tracked, and reported

Configuration management activities such as:


how changes to the product, service, or result requirements will be
initiated,
how impacts will be analyzed,
how they will be traced, tracked, and reported, as well as the authorization
levels
required to approve these changes
Requirements prioritization process
Product metrics that will be used and the rationale for using them
Traceability structure, that is, which requirements attributes will be captured on
the traceability matrix and to which other project documents requirements will be
traced.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

124

Collect Requirements Outputs


Requirements Traceability Matrix:
Is a table that links requirements to their origin and
traces them throughout the project life cycle.
Ensures that each requirement adds business value
by linking it to the business and project objectives.
Provides a structure for managing changes to the
product scope.

This process includes tracing requirements to:

Sample RTM

Business needs, opportunities, goals, and objectives

Project objectives
Project scope/WBS deliverables
Product design and development
Test strategy and test scenarios, and
More detailed requirements from high-level
requirements
ManagementFramework
Framework
Project Management

Version 1.0

125

Collect Requirements

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 5-3. Page 106.

ManagementFramework
Framework
Project Management

Version 1.0

126

Define Scope

ManagementFramework
Framework
Project Management

Version 1.0

127

Define Scope
The process of developing a detailed
description of the project and product.
A detailed project scope statement is critical
to project success and builds upon the major
deliverables, assumptions, and constraints
that are documented during project initiation.
During planning, the project scope is defined
and described with greater specificity as
more information about the project is known.

ManagementFramework
Framework
Project Management

Version 1.0

128

Define Scope Inputs, Tools, and Outputs

Project Charter
- If in the performing
organization, project charter
is not used then comparable
information needs to be
acquired and used as a
basis for the detailed
project scope statement.
Requirements
documentation
Organizational process asse
ts

Expert judgment
Product analysis
Alternatives
identification
Facilitated workshops

ManagementFramework
Framework
Project Management

Project scope
statement
Project document upd
ates

Version 1.0

129

Define Scope Outputs


The detailed project scope statement includes:

Product scope description


Product acceptance criteria

Project deliverables
Project exclusions
Project constraints
Project assumptions

Project Document Updates:


Stakeholder register
Requirements documentation, and
Requirements traceability matrix

ManagementFramework
Framework
Project Management

Version 1.0

130

Define Scope Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 5-5. Page 113.

ManagementFramework
Framework
Project Management

Version 1.0

131

Create WBS

ManagementFramework
Framework
Project Management

Version 1.0

132

Create WBS

Create Work Breakdown Structure (WBS) is the process of subdividing project


deliverables and project wok into smaller, more manageable components.

Requirements become the foundation of WBS.

The WBS is a deliverable-oriented hierarchical decomposition of the work to be


executed by the project team, to:
Accomplish project objectives and
Create required deliverables

The lowest level of WBS component are called


work packages and it can be:
Scheduled
Cost Estimated
Monitored
Controlled
ManagementFramework
Framework
Project Management

Version 1.0

133

Create WBS Inputs, Tools, and Outputs

Project scope statement


Requirements
documentation
Organizational process a
ssets

Decompositio
n

ManagementFramework
Framework
Project Management

WBS
WBS dictionary
Scope baseline
Project document upd
ates

Version 1.0

134

Create WBS Outputs


WBS
WBS dictionary

A document generated by the Create


WBS process that supports the
WBS.

Scope baseline

Project Scope
Statement

Project scope statement


WBS
WBS dictionary

Project document updates

ManagementFramework
Framework
Project Management

Version 1.0

135

Work Breakdown Structure

ManagementFramework
Framework
Project Management

Version 1.0

136

Work Breakdown Structure - Example

RSD Requirement Specification


Design
RTM Requirement Traceability Matrix

ManagementFramework
Framework
Project Management

Version 1.0

137

Create WBS Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 5-7. Page 117.

ManagementFramework
Framework
Project Management

Version 1.0

138

Verify Scope

ManagementFramework
Framework
Project Management

Version 1.0

139

Verify Scope

The process of formalizing acceptance of the completed project deliverables.

Verify Scope includes:

Reviewing deliverables to ensure


satisfactory completion
Obtaining formal acceptance
of deliverables

ManagementFramework
Framework
Project Management

Version 1.0

140

Scope Verification vs. Quality Control

Scope verification is primarily concerned with the acceptance of deliverables,


while quality control is primarily concerned with meeting quality requirements
specified for the deliverables.

If the project is terminated early, the project scope verification process should
establish and document the extent of completion.

ManagementFramework
Framework
Project Management

Version 1.0

141

Verify Scope Inputs, Tools, and Outputs

Project management plan


Requirements documentation
Requirements traceability
matrix
Validated deliverables
- Completed and checked for
correctness by the Perform
Quality Control process.

Inspection

ManagementFramework
Framework
Project Management

Accepted deliverables
Change requests
Project document updates

Version 1.0

142

Verify Scope Outputs

Accepted deliverables: Formal documentation received from the customer or


sponsor acknowledging stakeholder acceptance
of the projects deliverables is forwarded to the Close project or Phase
process.

Project Document Updates: Include any documents that define the product or
report status on product completion.

Change requests

ManagementFramework
Framework
Project Management

Version 1.0

143

Verify Scope Outputs


Deliverable

Integrated
Change
Control
Accepted

Not Accepted

Close

Documented for
Non-acceptance

Defect Repair

Change Request

Yes

ManagementFramework
Framework
Project Management

No

Version 1.0

144

Verify Scope Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 5-12. Page 123.

ManagementFramework
Framework
Project Management

Version 1.0

145

Control Scope

ManagementFramework
Framework
Project Management

Version 1.0

146

Control Scope

The process of:


Monitoring the status of the project and product scope
Managing changes to the scope baseline

It ensures that all requested changes and recommended corrective actions are
processed through the Perform Integrated Change Control process.

It is also used to manage the actual changes when


they occur and integrated with other control processes.

Uncontrolled changes are often referred to


as project scope creep.

ManagementFramework
Framework
Project Management

Version 1.0

147

Control Scope Inputs, Tools, and Outputs

Project management plan


- Contains: Scope baseline,
Scope management plan,
Change management plan,
Configuration management
plan, and Requirements
management plan.
Work performance
information
Requirements
documentation
Requirements traceability
matrix
Organizational process asse
ts

Variance analysis
- Determining the
cause and
degree of
variance relative
to the scope
baseline
- Deciding
whether
corrective or
preventive action
is required.

ManagementFramework
Framework
Project Management

Work performance
measurement
Organizational process
assets updates
Change requests
Project management plan
updates
Project document updates

Version 1.0

148

Control Scope Outputs


Work performance measurement
Organizational process assets updates
Change requests
Project management plan updates

Scope Baseline Updates


Other Baseline Updates

Project document updates

ManagementFramework
Framework
Project Management

Version 1.0

149

Control Scope Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 5-14. Page 126.

ManagementFramework
Framework
Project Management

Version 1.0

150

Management
Framework
Management
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Institute,
Inc

Version 1.0

151

PROJECT TIME MANAGEMENT

Management
Framework
Management
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Institute,
Inc

Version 1.0

152

Course Structure
Project Time Management
Introduction
Project Time Management Introduction
Define Activities
Define Activities : Inputs, Tools, and Outputs
Sequence Activities
Sequence Activities : Inputs, Tools, and Outputs
Estimate Activity Resources
Estimate Activity Resources : Inputs, Tools, and Outputs
Estimate Activity Duration
Estimate Activity Duration : Inputs, Tools, and Outputs
Develop Schedule
Develop Schedule : Inputs, Tools, and Outputs
Control Schedule
Control Schedule : Inputs, Tools, and Outputs
ManagementFramework
Framework
Project Management

Version 1.0

153

Project Time Management Introduction

ManagementFramework
Framework
Project Management

Version 1.0

154

Project Time Management Introduction


The processes required to manage timely completion of the project.
They include the following:
Define Activities - process of identifying the specific actions to be

performed to produce the project deliverables.


Sequence Activities - process of identifying and documenting

relationships among the project activities.


Estimate Activity Resources - process of estimating the type and quantities

of material, people, equipment, or supplies required to perform each activity.


Estimate Activity Durations - process of approximating the number
of work periods needed to complete individual activities with estimated
resources.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

155

Project Time Management Introduction


Develop Schedule - process of analyzing activity sequences, durations,
resource requirements, and schedule constraints to create the project
schedule.

Control Schedule - process of monitoring the status


of the project to update project progress and managing
changes to the schedule baseline.
*Note: Majority of effort in the Project Time Management
is incurred in the Control Schedule process
to ensure completion of project work on time.

ManagementFramework
Framework
Project Management

Version 1.0

156

Project Time Management Introduction

ManagementFramework
Framework
Project Management

Version 1.0

157

Scheduling Overview

ManagementFramework
Framework
Project Management

Version 1.0

158

Define Activities

ManagementFramework
Framework
Project Management

Version 1.0

159

Define Activities

The process of identifying the specific actions to be performed to produce the


project deliverables.

Project work packages that are decomposed into smaller components


called activities to provide basis for:
Estimating

Scheduling

Executing

Monitoring and Controlling the project work


ManagementFramework
Framework
Project Management

Version 1.0

160

Define Activities Inputs, Tools, and Outputs

Scope baseline

Enterprise environmental fa
ctors

Organizational process ass


ets

Decomposition
- Involving team
members in the
decomposition can
lead to better and
more accurate results.

Rolling wave planning

Templates

Expert judgment

ManagementFramework
Framework
Project Management

Activity list

Activity
attributes

Milestone list

Version 1.0

161

Rolling Wave Planning

A form of progressive elaboration planning where,


- the work to be accomplished in the near term is planned in detail and
- future work is planned at a higher level of the WBS.

Work can exist at various levels of detail depending on where it is in the project life
cycle.

ManagementFramework
Framework
Project Management

Version 1.0

162

Define Activities Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-4. Page 133.

ManagementFramework
Framework
Project Management

Version 1.0

163

Define Activities Outputs


Activity list
- It is a comprehensive list including all schedule activities
required on the project.

Activity attributes
- Extend the description of the activity by identifying the multiple
components associated with each activity.

Milestone list
- A milestone is a significant point or event in the project.
Mandatory (Such as those required by contract)
- Milestone List

Optional (Such as those based upon historical information

ManagementFramework
Framework
Project Management

Version 1.0

164

Sequence Activities

ManagementFramework
Framework
Project Management

Version 1.0

165

Sequence Activities

The process of identifying and documenting relationships among project


activities. Activities are sequences using logical relationships.

Every activity and milestone except the first and last are connected to at least one
predecessor and one successor.

It may be necessary to use lead and lag time between activities to support a
realistic and achievable project schedule.

Sequencing can be performed by using:


- project management software or
- manual or automated techniques

ManagementFramework
Framework
Project Management

Version 1.0

166

Sequence Activities Inputs, Tools, and Outputs

Activity list
Activity attributes
Milestone list
Project scope
statement
Organizational proc
ess assets

Precedence Diagramming
Method (PDM)
Dependency determination
Applying leads and lags
Schedule network templates

ManagementFramework
Framework
Project Management

Project schedule
network diagrams
Project document upda
tes

Version 1.0

167

Sequence Activities Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-6. Page 137.

ManagementFramework
Framework
Project Management

Version 1.0

168

Precedence Diagramming Method (PDM)


PDM is a method used in Critical Path Method (CPM) for constructing a project
schedule network diagram.
It uses boxes or rectangles, referred to as nodes, to represent activities, and
connects them with arrows that show the logical relationships that exist between
them. Also known as Activity On Node (AON)

Four types of
dependences
included in PDM:

Finish-to-start (FS)

Finish-to-finish (FF)

Start-to-start (SS)

Start-to-finish (SF)
ManagementFramework
Framework
Project Management

Version 1.0

169

Types of Dependencies
FINISH

START

Completion of successor Initiation of the successor


depends on completion of depends on completion of the
predecessor
predecessor
Completion of the
successor depends upon Initiation of the successor
the initiation of
activity depends on the
predecessor
initiation of predecessor

ManagementFramework
Framework
Project Management

Version 1.0

170

Types of Dependencies

Finish to start
Finish to Finish
Start to Start

ManagementFramework
Framework
Project Management

Version 1.0

171

Dependency Determination
Following types of dependencies are used to define the sequence among the activities:

Mandatory dependencies Those that are contractually required or inherent in the


nature of the work being done (referred to as Hard logic).
Discretionary dependencies Established based on - knowledge of best practices
and unusual aspect of the project. (referred to as preferred logic, preferential logic, or
soft logic)
Discretionary dependencies should be fully documented since they can create
arbitrary total float values and can limit later scheduling options.
When fast tracking techniques are employed, these discretionary dependencies
should be reviewed and considered for modification of removal.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

172

Dependency Determination

External dependencies The project management team determines which


dependencies are external dung the process of sequencing the activities.
Involves relationship between project activities and non-project activities (sub
contractors).
These dependencies are usually outside the project teams control.

ManagementFramework
Framework
Project Management

Version 1.0

173

Estimate Activity Resources

ManagementFramework
Framework
Project Management

Version 1.0

174

Estimate Activity Resources


The process of estimating the type and quantities of:
Material
People
Equipment
Supplies required to perform each activity.

It is closely coordinated with the Estimate


Costs process.

ManagementFramework
Framework
Project Management

Version 1.0

175

Estimate Activity Resources Inputs, Tools, and


Outputs

Activity list
Activity attributes
Resource calendars
Enterprise environmenta
l factors
Organizational process
assets

Expert judgment
Alternatives analysis
Published estimating
data
Bottom-up estimating
- When an activity cannot
be estimated with a
reasonable degree of
confidence, the work
within the activity is
decomposed into more
detail

Project management
software
ManagementFramework
Framework
Project Management

Activity resource
requirements
Resource breakdown
structure
Project document update
s

Version 1.0

176

Estimate Activity Resources Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-89 Page 142.

ManagementFramework
Framework
Project Management

Version 1.0

177

Estimate Activity Resources Outputs


Resource breakdown structure
- It is a hierarchical structure of the identified resources
by resource category and resource type.
- Examples of resource categories include:
Labour
Material
Equipment
Supplies
- Resource types can include:
Skill level
Grade level
Other information as appropriate to the project.
- It is useful for organizing and reporting project schedule data
with recourse utilization information.
ManagementFramework
Framework
Project Management

Version 1.0

178

Estimate Activity Durations

ManagementFramework
Framework
Project Management

Version 1.0

179

Estimate Activity Durations

The process of approximating the number of


work period needed to complete individual
activities with estimated resources.

The duration estimate is progressively


elaborated, based on quality and availability of
the input data and results in better and accurate
estimates.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

180

Estimate Activity Durations


Using Project Calendar
&
Resource Calendar

Amount of work effort required


&
Resources to be applied

Number of Work Periods


needed (Activity Duration)

ManagementFramework
Framework
Project Management

Version 1.0

181

Estimate Activity Duration Inputs, Tools, and


Outputs

Activity list
Expert judgment
Activity attributes
Analogous estimating
Activity resource
Parametric estimating
requirements
Three-point estimates
Resource calendar
Reserve analysis
Project scope statement
Enterprise environmental factors
Organizational process assets

ManagementFramework
Framework
Project Management

Activity duration
estimates
Project document update
s

Version 1.0

182

Estimate Activity Duration Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-13. Page 153.

ManagementFramework
Framework
Project Management

Version 1.0

183

Estimation Methods
1. Analogous Estimating:

Analogous duration estimating is frequently used to estimate project duration


when there is a limited information
Uses parameters such as duration, budgets, size, weight, and complexity,
from a previous, similar project, as the basis for estimation
Uses historical information and expert judgment.
Is generally less costly and time consuming but also less accurate.
Is most reliable when the previous activities are similar in fact and not just in
appearance, and the project team members preparing the estimates have the
needed expertise.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

184

Estimation Methods
2. Parametric Estimating:

Uses a statistical relationship between historical data and other variables (e.g.
square feet in construction) to calculate an estimate for activity parameters, such
as: cost. budget, and duration.

It can produce higher levels of accuracy depending upon the


sophistication and underlying data built into the model.

It can be applied to a total project or to segments of project, in


conjunction with other estimating methods.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

185

Estimation Methods
3.Three-Point Estimates:

The accuracy of activity duration estimates can be improved by


considering estimation uncertainty and risk.
Program Evaluation and Review Technique (PERT) uses three estimates
to define an approximate range for an activity's duration:
Most likely (tM) - Realistic expectation

Optimistic (tO) - Best-case

Pessimistic (tP) - Worst-case

PERT analysis calculates an Expected (tE) activity duration using a weighed


average of these estimates
tE = (tO + 4tM + tP )
______________

6
Standard Deviation (SD) = (tP tO ) / 6
Variance = ( SD ) 2 = [(tP tO ) / 6 ] 2
ManagementFramework
Framework
Project Management

Version 1.0

186

Example using PERT


For example, take a network with the following dependent tasks, with
each successor task having a finish-to-start relationship with the
predecessor task:

The standard deviation of the total path is given by taking the square root of the
sum of the squares of each task standard deviation.

ManagementFramework
Framework
Project Management

Version 1.0

187

Sigma calculations

ManagementFramework
Framework
Project Management

Version 1.0

188

Develop Schedule

ManagementFramework
Framework
Project Management

Version 1.0

189

Develop Schedule
The process of analyzing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule.
Developing an acceptable project schedule is often an iterative process.
It determines the planned start and finish dates for project activities and
milestones (dates).
Revising and maintaining a realistic schedule continues throughout the project as
work progresses, the project management plan changes, and the nature of risk
events evolves.

ManagementFramework
Framework
Project Management

Version 1.0

190

Develop Schedule Inputs, Tools, and Outputs

Activity list
Activity attributes
Project schedule network

diagrams

Activity resource

requirements

Resource calendars
Activity duration estimates
Project scope statement
Enterprise environmental
factors
Organizational process
assets

Schedule network
analysis
Critical path method
Critical chain method
Resource levelling
What-If scenario analysis
Applying leads and lags
Schedule compression
Schedule tool

ManagementFramework
Framework
Project Management

Project schedule
Schedule baseline
Schedule data
Project document
updates

Version 1.0

191

Develop Schedule Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-13. Page 153.

ManagementFramework
Framework
Project Management

Version 1.0

192

Develop Schedule Tools and Techniques


Schedule Network Analysis
It is a technique to generate the project schedule.
It employs various analytical techniques, to calculate the early and
late start and finish dates for the uncompleted portions of project
activities.
These techniques are:
Critical Path Method
Critical Chain Method
What-if Analysis
Resource leveling

ManagementFramework
Framework
Project Management

Version 1.0

193

Develop Schedule Tools and Techniques


Critical Path Method (CPM)
This method calculates the theoretical early start and finish dates, and the late start
and finish dates, for all activities without regard for any resource limitations.
This is done by performing a forward and backward pass analysis through the
schedule network.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

194

Critical Path Method

Continue
ManagementFramework
Framework
Project Management

Version 1.0

195

Critical Path Method

Demo-Float

Float = Late Start Early Start (or) Late Finish Early Finish

Continue
ManagementFramework
Framework
Project Management

Version 1.0

196

Critical Path Method


Early start and finish dates and late start and finish dates Affected by
activity total float

Critical paths A zero or negative total float

Critical Activities Schedule activities on a critical path

Networks can have multiple near critical paths

Positive difference between early and late dates Total Float

ManagementFramework
Framework
Project Management

Version 1.0

197

Develop Schedule Tools and Techniques


Critical Chain Method
The resource-constrained critical path is known as the critical chain.
After the critical path is identified, resource availability is entered and the
resource-limited schedule result is determined.
Determining schedule status by comparing

amount of buffer remaining


amount of buffer needed to
protect the delivery date

Difference between the buffer needed and


the buffer remaining, determine if
corrective action is appropriate.

ManagementFramework
Framework
Project Management

Version 1.0

198

Develop Schedule Tools and Techniques


Resource leveling
A schedule network analysis technique applied to a schedule that has
already been analyzed by the critical path method.
Used when shared or critical required resources are only available at certain
time, in limited quantities, or to keep resource usage at a constant level.
Often cause the original critical path to change.

ManagementFramework
Framework
Project Management

Version 1.0

199

Develop Schedule Tools and Techniques


What-If Scenario Analysis (Monte Carlo Analysis)
An analysis of the question What if the situation represented by scenario X
happens?

Applying Leads and Lags


Refinements applied during network analysis to develop a viable
schedule.

ManagementFramework
Framework
Project Management

Version 1.0

200

Develop Schedule Tools and Techniques


Schedule Compression
Shortens the project schedule without changing the project scope.
Crashing
Fast Tracking

Scheduling Tool
Expedite the scheduling process by generating start and finish dates based
on:
the inputs of activities
network diagrams
resources and
activity durations

ManagementFramework
Framework
Project Management

Version 1.0

201

Develop Schedule Outputs


Project Schedule
Includes a planned start date and planned finish date for each activity.
Can be presented in summary form, sometimes referred to as the master schedule or
milestone schedule or presented in details
Project schedule can be presented in any of the following forms:

ManagementFramework
Framework
Project Management

Version 1.0

202

Control Schedule

ManagementFramework
Framework
Project Management

Version 1.0

206

Control Schedule
The process of monitoring the status of the project to update project progress and
manage changes to the schedule baseline.
It is concerned with:

Determining the current status of the project schedule

Influencing the factors that create schedule changes

Determining that the project schedule has changed

Managing the actual changes as they occurs


It is a component of the Perform Integrated Change Control process.

ManagementFramework
Framework
Project Management

Version 1.0

207

Control Schedule Inputs, Tools, and Outputs

Project management
plan
Project schedule
Work performance
information
Organizational
process assets

Performance review
Variance analysis
Project management
software
Resource leveling
What-if scenario
analysis
Adjusting leads and
lags
Schedule compression
Scheduling tool

ManagementFramework
Framework
Project Management

Work performance
measurement
Organizational process assets
updates
Change requests
Project management plan
Project document updates

Version 1.0

208

Control Schedule Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 6-16. Page 161.

ManagementFramework
Framework
Project Management

Version 1.0

209

Control Schedule - Outputs


Work performance measurement
- The work packages and control accounts, are documented
and
communicated to stakeholders.

Organizational process assets updates


- Causes of variances
- Corrective action chosen and the reasons
- Other types of lessons learned from project schedule control

Change requests
Project management plan
- Schedule baseline
- Schedule management plan
- Cost baseline

Project document updates


- Schedule Data
- Project Schedule
ManagementFramework
Framework
Project Management

Version 1.0

210

Management
Framework
Management
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Institute,
Inc

Version 1.0

211

PROJECT COST MANAGEMENT

Management
Framework
Management
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Institute,
Inc

Version 1.0

212

Course Structure
Project Cost Management
Introduction
Project Cost Management Introduction
Estimate Costs
Estimate Costs : Inputs, Tools, and Outputs
Determine Budget
Determine Budget : Inputs, Tools, and Outputs
Control Costs
Control Costs : Inputs, Tools, and Outputs

ManagementFramework
Framework
Project Management

Version 1.0

213

Introduction

ManagementFramework
Framework
Project Management

Version 1.0

214

Project Cost Management - Introduction


It includes the processes involved in estimating, budgeting and controlling costs so that
the project can be completed within the approved budget.
Project Cost Management includes:

Estimate Costs process of developing an approximation of the monetary


resources needed to complete project activities.
Determine Budget process of
aggregating the estimated costs of
individual activities or work packages
to establish an authorized cost
baseline.
Control Costs process of monitoring
the status of the project to update the
project budget and managing changes
to the cost baseline.

ManagementFramework
Framework
Project Management

Version 1.0

215

Project Cost Management - Introduction

On the smaller scope projects, cost estimating and cost budgeting are tightly linked
and they are viewed as a single process.

The work involved in performing the Project Cost Management processes is


preceded by a planning effort

This planning effort is part of the Develop Project Management Plan process, which
produces a Cost Management Plan.

As example, the Cost Management Plan can


establish:

Level of accuracy

Unit of measure

Organizational procedure links

Control thresholds

Rules of performance measurement

Reporting formats

Process descriptions
ManagementFramework
Framework
Project Management

Version 1.0

216

Project Cost Management - Introduction

It is primarily concerned with the cost of resources needed to


complete schedule activities.

This broader view of Project Cost Management is called Life Cycle


Costing, it should also consider the effect of project decisions on the
cost of Using
Maintaining and
Supporting

the product, service, or result of the project.

Value Engineering

ManagementFramework
Framework
Project Management

Version 1.0

217

Estimate Costs

ManagementFramework
Framework
Project Management

Version 1.0

218

Estimate Costs
It is the process of developing an approximation of the monetary resources needed to
complete the project activities.
It includes identification and consideration of costing alternatives such as make
versus buy, buy versus lease, and the sharing of resources in order to achieve optimal
costs.
The accuracy of an estimate will increase as the project progresses through the
project life cycle and thus, cost estimating is an iterative process from phase to phase.

Accu
racy

10% Definitive Estimate

50% Rough Order of Magnitude (ROM)


ManagementFramework
Framework
Project Management

Version 1.0

219

Estimate Costs Inputs, Tools, and Outputs

Scope baseline
Scope statement
- Work breakdown structure
- WBS dictionary

Project schedule
Human resource plan
Risk register
Enterprise environmental
factors
Organizational process
assets

Expert judgement
Analogous estimating
Parametric estimating
Bottom-up estimating
Three-point estimates
Reserve analysis
Cost of quality
Project management
estimating software
Vendor bid analysis

ManagementFramework
Framework
Project Management

Activity cost estimates


Basis of estimates
Project document
updates

Version 1.0

220

Estimate Costs Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 7-3. Page 169.

ManagementFramework
Framework
Project Management

Version 1.0

221

Estimate Costs Tools and Techniques


Expert Judgment
Guided by historical information
Determine use of combined methods of estimating
Reconcile differences between these methods
Top-down Estimating
Analogous Estimating

Parametric Estimating

Relies on the actual cost of previous similar


projects
Uses historical information and expert
judgment
Used when limited amount of detailed
information about the project is available
Less costly, time consuming, and less
accurate
Applies to a total project or to segments of
a project

Uses a statistical relationship between


historical data and other variables
Produces higher levels of accuracy
Applies to a total project or to segments
of a project

ManagementFramework
Framework
Project Management

Version 1.0

222

Estimate Costs Tools and Techniques


Bottom-Up Estimating
A method of estimating a component of
work
Detailed estimation on cost of
individual work packages or activities
Summarizing detailed cost for
subsequent reporting and tracking
purposes
Cost and accuracy depends on the size
and complexity of individual activity or
work package

ManagementFramework
Framework
Project Management

Version 1.0

223

Estimate Costs Tools and Techniques


Three-Point Estimates
Accuracy of single-point activity cost
estimates can be improved by considering
estimation uncertainty and risk
Three estimates to define an approximate
range for an activity cost:
Most likely (CM)
Optimistic (CO)
Pessimistic (CP)

PERT analysis calculated an expected


(CE) activity cost using a weighted average
of these three estimates.

CE = CO +4CM +CP

Add-on techniques

Reserve Analysis
Cost of Quality (COQ)
Project Management Estimating
Software
Vendor Bid Analysis

ManagementFramework
Framework
Project Management

Version 1.0

224

Estimate Costs - Outputs


Activity Cost Estimates
Cost can be either Variable or Fixed
Variable Cost: Cost changes with the
amount of work (e.g. Material Cost)
Fixed Cost: Cost does not change with the
amount of work (e.g. Rentals)
Cost can be either Direct or Indirect
Direct Cost: Costs that are directly
attributable to work on the project. (Team
Wages)
Indirect Cost: Overheads or costs incurred
for the benefit of more than one project.
(h/w, s/w purchased)

ManagementFramework
Framework
Project Management

Version 1.0

225

Estimate Costs Outputs


Basis of estimates
- The amount and type of additional details supporting the cost
estimate vary by application area.
- Supporting details for activity cost estimates provide a clear and complete
understanding of how the cost estimate was derived.

Project document updates


- For example, Risk register

ManagementFramework
Framework
Project Management

Version 1.0

226

Determine Budget

ManagementFramework
Framework
Project Management

Version 1.0

227

Determine Budget
The process of aggregating the estimated costs of individual
activities or work packages to establish an authorized cost
baseline.
This baseline includes all authorized
budgets, but excludes management reserves.
Project budgets constitute the
funds
authorized to execute the project.
Project cost performance will be
measured against the authorized budget.

Cash Flow, Cost Baseline and Funding - Graphical Display


ManagementFramework
Framework
Project Management

Version 1.0

228

Determine Budget Inputs, Tools, and Outputs

Activity cost estimates


Basis of estimates
Scope baseline
- Scope Statement
- Work breakdown structure
- WBS dictionary
Project schedule
Resource calendars
Contracts
Organizational process
assets

Cost aggregation
Reserve analysis
Expert judgment
Historical
relationships
Funding limit
reconciliation

ManagementFramework
Framework
Project Management

Cost performance
baseline
Project funding
requirements
Project document
updates

Version 1.0

230

Determine Budget Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 7-5. Page 175.

ManagementFramework
Framework
Project Management

Version 1.0

231

Determine Budget Tools and Techniques


Reserve Analysis
It can establish both, the contingency reserves and the
management reserves for the project.
Contingency reserves Allowances for unplanned but potentially required
changes that can result from realized risks identified in the risk register.
Management reserves Budgets reserves for unplanned changes to project
scope and cost.
Reserves are not a part of the project cost baseline, but may be included in
the total budget for the project and they are not included as a part of the
earned value measurement calculations.

ManagementFramework
Framework
Project Management

Version 1.0

232

Cost Roll Up

ManagementFramework
Framework
Project Management

Version 1.0

233

Control Costs

ManagementFramework
Framework
Project Management

Version 1.0

234

Control Costs
The process of monitoring the status of the project to update the project budget and
managing changes to the cost baseline.
Any increase to the authorized budget can only be approved through the Perform
Integrated Change Control process.
The key to effective cost control is the management of the approved cost
performance baseline and the changes to that baseline.

What type of different activities could be


included?
Influencing factors that create changes to cost baseline.

Ensuring that all change requests are acted on in a timely manner.


Managing the actual changes when and as they occur.
Ensuring that cost expenditure do not exceed the authorized funding, by period and in total
for the project.
Monitoring cost performance to isolate and understand variance from the approved cost
baseline.
Monitoring work performance against funds expended.
Preventing unapproved changes from being included in the reported cost or resource usage.
Incoming appropriate stakeholders of all approved changes and associated cost.
Acting to bring expected cost overruns within acceptable limits.
ManagementFramework
Framework
Project Management

Version 1.0

235

Control Costs Inputs, Tools, and Outputs

Project management plan


Project funding
requirements
Work performance
information
Organizational process
assets

Earned value management


Forecasting
To-complete performance
index
Performance reviews
Variance analysis
Project management software

- Analysis of project
performance can result to the
cost performance baseline or
other components of the
project management plan.

ManagementFramework
Framework
Project Management

Work performance
measurements
Budge forecasts
Organizational process
assets updates
Change requests

Project management plan


updates
Project document updates
Version 1.0

236

Control Costs Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 7-8. Page 180.

ManagementFramework
Framework
Project Management

Version 1.0

237

Control Costs Tools and Techniques


Earned Value Management (EVM) integrates project scope, cost,
and schedule measures to help the project management team
assess and measure project performance and progress.
Important Terms:
Planned Value (PV): Estimated value of the work planned to be
done.
Earned Value (EV): Estimated value of the work actually
accomplished.
Actual Cost (AC): Actual money spent for the work
accomplished.
Budget at Completion (BAC): Budget for the total project
work.

ManagementFramework
Framework
Project Management

Version 1.0

238

Earned Value, Planned Value, and Actual Costs

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 7-9. Page 183.

ManagementFramework
Framework
Project Management

Version 1.0

239

Control Costs Tools and Techniques


Forecasting
The project team can develop a forecast for the estimate at completion
(EAC) that may differ from the budget at completion (BAC) based on the project
performance.

Estimate at Completion (EAC): How much at present we expect total


project to cost.
Estimate to Complete (ETC): How much more, at present, we expect
it to cost to finish the project.
Variance at Completion (VAC): How much over or under budget, do
we expect to be at the end of project.

ManagementFramework
Framework
Project Management

Version 1.0

240

Cost Management Formulae


Item

Formula

Remark

Cost Variance (CV)

EV AC

Negative value indicates over budget and positive


value indicates under budget

Schedule Variance (SV)

EV PV

Negative value indicates behind schedule and


positive value indicates ahead of schedule

Cost Performance Index (CPI)

EV / AC

Lesser than one indicates over budget and greater


than one indicates under budget

Schedule Performance Index


(SPI)

EV / PV

Lesser than one indicates behind schedule and


greater than one indicates ahead of schedule

Estimate at Completion (EAC)

BAC / CPI

Considering that the rate of spending remains the


same

AC + ETC

Considering that the current estimate is


fundamentally flawed

AC + (BAC EV)
AC + [(BAC EV) /
CPI]
Estimate to Complete (ETC)

Considering typical variances

EAC AC

Considering that the current estimate is


fundamentally flawed

BAC EV

Considering atypical variances

(BAC EV) / CPI


Variance at Completion (VAC)

Considering atypical variances

BAC EAC

Considering typical variances


Considering the status of the budget expected at
the end of the project

ManagementFramework
Framework
Project Management

Version 1.0

241

Control Costs Tools and Techniques


To-Complete Performance Index (TCPI)
Work Remaining (BAC EV)
= TCPI
Funds Remaining (BAC AC) or (EAC AC)

The calculated projection of cost performance that must be achieved


on the remaining work to meet a specified management goal, such as
the BAC or the EAC.
If it becomes obvious that the BAC is no longer viable, then the project manager
develops a forecasted estimate at completion (EAC).
Once approved, the EAC effectively supersedes the BAC as the cost
performance goal.
ManagementFramework
Framework
Project Management

Version 1.0

242

Important Financial Terms


Financial Term

Definition

Benefit Cost
Ratio (BCR)

Compares the benefits (revenues) to the costs of different options

Chart of
Accounts

Any numbering system used to monitor project costs by category (for example, labor,
supplies, and materials)

Depreciation

Reduced price of an asset over time attributable to deterioration, obsolescence, and


impending retirement
Applies particularly to physical assets such as equipment and structures
Straight Line depreciation: Standard amount depreciating every year
Accelerated depreciation: Value depreciating at a faster rate, for example, Double
Declining method and Sum of the Years Digits

Internal Rate of
Return (IRR)

Rate at which the project inflows and project outflows are equal
Project with greatest IRR is generally selected

Net Present
Value (NPV)

Present value of the total benefits minus costs over many time periods
Investment is profitable for positive NPV
Project with greatest NPV is selected

Opportunity Cost

Opportunity given up by selecting one project over another

Payback Period

Time period it takes to recover the investment made in the project before the profits start
accumulating

Present Value

The current value of future cash flows.

Sunk Cost

Expended costs, to be avoided when deciding whether to continue with a troubled project
ManagementFramework
Framework
Project Management

Version 1.0

243

Management
Framework
Management
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Institute,
Inc

Version 1.0

244

PROJECT HUMAN RESOURCE MANAGEMENT

Project Management Framework

ManagementInstitute,
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Inc

Version 1.0

245

Course Structure
Project Human Resource Management
Introduction
Project Human Resource Management Skills
Project Human Resource Management Processes
Develop Human Resource Plan
Develop Human Resource Plan : Inputs, Tools, and Outputs
Human Resource Theories
Acquire Project Team
Acquire Project Team : Inputs, Tools, and Outputs
Develop Project Team
Develop Project Team : Inputs, Tools, and Outputs
Manage Project Team
Manage Project Team : Inputs, Tools, and Outputs

ManagementFramework
Framework
Project Management

Version 1.0

246

Project Human Resource Management Skills


Project Human Resource Management relies on the substantial body of literature
about dealing with people.

ManagementFramework
Framework
Project Management

Version 1.0

247

Project Human Resource Management - Introduction

Project Human Resource Management includes the processes that organize,


manage, and lead the project team.

The project team is comprised of the people who have been assigned roles and
responsibilities for completing the project.

Involvement and participation of team members in project planning and decision


making can be beneficial and early involvement adds their expertise and
strengthens their commitment to the project.

The project management team (referred as the


core, executive, or leadership team) is a subset
of the project team and is responsible for the
project management and leadership activities.

ManagementFramework
Framework
Project Management

Version 1.0

248

Project Human Resource Management - Introduction

Managing and leading the project team includes:

Influencing the project team

Professional and ethical behavior


Human Resource factors that may impact the

project:
Team environment
Geographical locations of team members
Communications among stakeholders
Internal and external politics
Cultural issues
Organizational uniqueness

ManagementFramework
Framework
Project Management

Version 1.0

249

ManagementFramework
Framework
Project Management

Version 1.0

250

Develop Human Resource Plan


It is the process of identifying and documenting:

Project roles, responsibilities, and required skills

Reporting relationships and

Creating a staffing management plan

ManagementFramework
Framework
Project Management

Version 1.0

251

Develop Human Resource Plan


It also documents:

Timetable for staff acquisition and release


Identification of training needs
Team-building strategies
Plans for recognition and rewards programs
Compliance considerations
Safety issues
Impact of the staffing management
plan on the organization

The availability of, or competition for, scarce or limited human


resources should be considered.
ManagementFramework
Framework
Project Management

Version 1.0

252

Develop Human Resource Plan Inputs, Tools,


and Outputs

Activity resource requirements


Enterprise environmental factors
Organizational process assets

Organization charts and


position descriptions
Networking
Organizational theory

ManagementFramework
Framework
Project Management

Human resource
plan

Version 1.0

253

Develop Human Resource Plan Tools and Techniques


Organization Charts

Hierarchical

Matrix-based

Position Descriptions

Text-oriented
formats

- A responsibility assignment
matrix (RAM) is used to
illustrate the connections
between work packages or
activities and project team
members.
- One example of RAM is
RACI (responsible,
accountable, consult, and
inform)

ManagementFramework
Framework
Project Management

Other sections
of the Project
Management Plan
- Responsibilities related
to managing the project
are listed and explained in
other sections of the
project management plan.
- For example, risk register
lists risk owners,
communication plan lists
team members responsible
for communication
activities.
Version 1.0

254

Develop Human Resource Plan Tools and


Techniques

Networking Formal and informal interaction with others in an


organisation, industry, or professional environment.
Organizational Theory Provides information regarding the way in which
people, teams, and organizational units behave.

ManagementFramework
Framework
Project Management

Version 1.0

255

Human Resource Theories


1. Maslows Hierarchy of Needs:

ManagementFramework
Framework
Project Management

Version 1.0

256

Human Resource Theories


2. Hezbergs Theory of Motivation:

Presence of hygiene factors will not motivate people to perform as these are
expected, however, their absence will demotivate performance.
ManagementFramework
Framework
Project Management

Version 1.0

257

Human Resource Theories


3.

McGregors Theory of X and Y:


X (Micro Management)
Y (Self Motivated)

4.

Expectancy Theory:
People will behave based on what they expect as a result of their
behavior.

ManagementFramework
Framework
Project Management

Version 1.0

258

Develop Human Resource Plan Outputs


Human Resource Plan include:
Roles and responsibilities

Role
Authority
Responsibility
Competency

Project organization chart

Staffing Management Plan includes:

Staff Acquisition
Resource calendars (Resource Histogram)
Staff release plan
Training Needs
Recognition and Rewards
Compliance
Safety
ManagementFramework
Framework
Project Management

Version 1.0

259

Acquire Project Team


It is the process of confirming human resource availability and obtaining the team
necessary to complete project assignments.
The project management team have limited control over selecting the team
members due to:

Collective bargaining agreements,

Use of subcontractor personnel,

Matrix project environment,

Internal or external reporting relationships


and other various reasons

Continue
ManagementFramework
Framework
Project Management

Version 1.0

261

Acquire Project Team


Impact of unavailability of the required human resources get reflected in:

Project schedules
Project budgets
Customer satisfaction
Project quality
Project risks
Training plans and the other project
management plan as required

ManagementFramework
Framework
Project Management

Version 1.0

262

Acquire Project Team Inputs, Tools, and Outputs

Project management plan


Enterprise environmental
factors
Organizational process
assets

Pre-assignment
Negotiation
Acquisition
Virtual teams

ManagementFramework
Framework
Project Management

Project staff
assignments
Resource
availability
Staffing
management plan
updates

Version 1.0

263

Acquire Project Team Tools and Techniques


Virtual Teams
Groups of people with a shared goal who fulfill their roles with little
or no time meeting face to face.
The availability of electronic communication such as
e-mail, audio conferencing, web-based meetings
and video conferencing has made such teams
feasible.
Communications planning becomes increasingly
important in a Virtual Team Environment.

ManagementFramework
Framework
Project Management

Version 1.0

264

Develop Project Team


Competencies

It is the process of improving

Interactions
Overall environment

To achieve high performance and to meet the projects


objectives, project managers should have skills to:
Identify
Build
Maintain
Motivate, Lead, and Inspire project teams

Continue
ManagementFramework
Framework
Project Management

Version 1.0

265

Develop Project Team

Project managers should motivate their team by:


Providing challenges and opportunities
Providing timely feedback and support as needed
Recognizing and rewarding good performance

High team performance can be achieved by:


Using open and effective communication
Developing trust among team members
Managing conflicts in a constructive manner
Encouraging collaborative problem-solving
and decision-making

Teamwork is critical for project success, and developing effective project teams is
one of the primary responsibilities of the project manager.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

266

Develop Project Team Inputs, Tools, and Outputs

Project staff
assignments
Project management
plan
Resource calendars

Interpersonal skills
Training
Team-building
Activities
Ground rules
Co-location
Recognition and
rewards

ManagementFramework
Framework
Project Management

Team performance assessments


Enterprise environmental factors
updates

Version 1.0

267

Develop Project Team Tools and Techniques


Team-Building Activities
Forming

Storming
Norming
Performing
Adjourning

Co-location

- Involves placing of the most active project team members in the same
physical location to enhance their ability to perform as a team.
- This may require,
a team meeting room
places to post schedules
other conveniences that enhance communication and a sense of community.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

268

Develop Project Team Tools and Techniques


Recognition and Rewards
Recognition and Rewards should be given - willingness to
work overtime to meet an aggressive schedule objective
Recognition and rewards should not be given - need to work
overtime due to poor planning by the team member
Avoid win-lose (zero sum) rewards
People are motivated

When they feel they are


valued in the organization

Recognition and rewards should


be given to make them feel that
they are valued

ManagementFramework
Framework
Project Management

Version 1.0

269

Develop Project Team Outputs


Team Performance Assessments
The project management team makes formal or informal assessments
of the project teams effectiveness and as a result, the project management
team can identify the specific:
- training
- coaching
- mentoring
- assistance
of changes required to improve the teams performance.

The evaluation of a teams effectiveness include:


Improvements in skills and competencies
Reduced staff turnover rate
Increased team cohesiveness

ManagementFramework
Framework
Project Management

Version 1.0

270

Manage Project Team


It is the process of:

Tracking team member performance


Providing feedback
Resolving issues
Managing conflict
Managing changes to optimize project performance
Appraising team member performance

Continue
ManagementFramework
Framework
Project Management

Version 1.0

271

Manage Project Team


As a result of managing project team:

Change requests are submitted.

Human resource plan is updated.

Issues are resolved.

Input is provided for performance appraisal.

Lesson learned are added to the organization database.

ManagementFramework
Framework
Project Management

Version 1.0

272

Manage Project Team Inputs, Tools, and Outputs

Project staff assignments


Project management plan
Staffing management plan
Team performance
assessment
Performance reports
Organizational process
assets

Observation and
conversation
Project performance
appraisals
Conflict management
Issue log
Interpersonal skills

- Staffing changes, whether by


choice or by uncontrollable
events, can affect the rest of
the project management plan.

ManagementFramework
Framework
Project Management

Enterprise environmental
factors updates
Organizational process
assets updates
Change requests

Project management plan


updates

Version 1.0

273

Leadership Styles
Directing : Telling others what to do.
Facilitating : Coordinating the inputs of others.
Coaching : Instructing others.
Supporting : Providing assistance along the way.
Autocratic : Making decisions without gathering information from
other team members.
Consultative : Inviting ideas and suggestions from team members.
Consensus : Problem solving in a group with decision making
based on group agreement.

ManagementFramework
Framework
Project Management

Version 1.0

274

Various Powers of a Project Manager

Formal (Legitimate)

Reward

Penalty (Coercive)

Expert

Referent
(Best forms of power are EXPERT and REWARD)

ManagementFramework
Framework
Project Management

Version 1.0

275

Conflict Management
Characteristics of conflict and the conflict management process:
Conflict is natural and forces a search for alternatives
Conflict is a team issue
Openness resolves conflict
Conflict resolution should focus on issues, not personalities
Conflict resolution should focus on the present, not the past
Six general techniques for resolving conflict:
Withdrawal / Avoidance
Smoothing / Accommodating
Compromise
Forcing
Collaborating
Confronting / Problem Solving
ManagementFramework
Framework
Project Management

Version 1.0

276

Interpersonal Skills
Project managers use a combination of,
Technical
Human
Conceptual skills
To analyze situations and interact appropriately with team members

Using appropriate interpersonal skills aids project managers in


capitalizing on the strengths of all team members.

ManagementFramework
Framework
Project Management

Version 1.0

277

The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Institute,
Inc
Management
Framework
Management
Framework

Version 1.0

278

PROJECT COMMUNICATIONS MANAGEMENT

ManagementFramework
Framework
Project Management

Version 1.0

279

Course Structure
Project Communications Management
Introduction
Basic Communication Model
Project Communications Management Processes
Identify Stakeholders
Identify Stakeholders : Inputs, Tools, and Outputs
Plan Communications
Plan Communications : Inputs, Tools, and Outputs
Distribute Information
Distribute Information : Inputs, Tools, and Outputs
General Communication Dimensions
Manage Stakeholder Expectation
Manage Stakeholder Expectation : Inputs, Tools, and Outputs
Report Performance
Report Performance : Inputs, Tools, and Outputs
ManagementFramework
Framework
Project Management

Version 1.0

280

Project Communications Management


It includes the processes required to ensure timely and appropriate:
Generation
Collection
Distribution
Storage
Retrieval and
Ultimate disposition of
project information

Project Managers majority of time (90%) is spent in communicating with the project
team and other stakeholders (internal or external to the organization).

Continue
ManagementFramework
Framework
Project Management

Version 1.0

281

Project Communications Management


Effective communication creates a bridge between diverse stakeholders involved
in a project by:
Connecting various cultural and organizational backgrounds
Different levels of expertise
Various perspectives and interests in the project execution or outcome

Continue
ManagementFramework
Framework
Project Management

Version 1.0

282

Project Communications Management

Communication activity has many potential dimensions, including:

Internal (within the project) and external (customer, other projects, the media, the
public)
Formal (reports, memos, briefings) and informal (emails, ad-hoc discussions)
Vertical (up and down the organization) and horizontal (with peers)
Official (newsletters, annual report) and unofficial (off the record communications)
Verbal and non-verbal (voice inflections, body language)
Written and oral

Continue
ManagementFramework
Framework
Project Management

Version 1.0

283

Project Communications Management

Communication skills common for general and project management:

Listening actively and effectively


Questioning, probing ideas and situations
Educating to increase teams knowledge
Fact-finding to identify or confirm information
Setting and managing expectations
Persuading a person or organization
Negotiating to achieve mutually
acceptable agreements between parties
Resolving conflict to prevent disruptive
impacts
Summarizing, recapping, and
identifying the next steps

ManagementFramework
Framework
Project Management

Version 1.0

284

Project Communications Management - Processes

ManagementFramework
Framework
Project Management

Version 1.0

285

Identify Stakeholders
It is critical to identify stakeholders early in the project, and to analyze their levels of
interests, expectations, importance, and influence.
A strategy can be developed for approaching each stakeholder and determining the
level and timing of their involvement to maximize positive influences and mitigate
potential negative impacts.
Stakeholders should be classified according to their interest, influence and
involvement as this enables the project manager to focus on the relationships
necessary to ensure the success of the project due to limited time.

ManagementFramework
Framework
Project Management

Version 1.0

286

Identify Stakeholders Inputs, Tools, and Outputs

Project charter
Procurement documents
Enterprise environmental
factors
Organizational process
assets

Stakeholder analysis
Expert Judgement

Stakeholder register
Stakeholder management
strategy

ManagementFramework
Framework
Project Management

Version 1.0

287

Identify Stakeholders Tools and Techniques


Stakeholder analysis Generally follows three steps
Step 1: Identify all potential project stakeholders and relevant information

Step 2: Identify the potential impact each


stakeholder could generate, and classify them
so as
to define an approach strategy.
Stakeholders classification models:
Example

Power/interest grid

Power/influence grid

Influence/impact grid

Salience model

Continue
ManagementFramework
Framework
Project Management

Version 1.0

288

Identify Stakeholders Tools and Techniques


Step 3: Assess how key stakeholders are likely to react or respond in
various
situations, in order to plan:
How to influence them to enhance their support and
Mitigate potential negative impacts

ManagementFramework
Framework
Project Management

Version 1.0

289

Plan Communications
It determines information and communication needs of the project stakeholders. For
example:
Who needs what information
When they will need it
How it will be given to them, and
By whom
This process is tightly linked with enterprise environmental
factors, because the organizations structure will have a
major effect on the project's communications requirements.

ManagementFramework
Framework
Project Management

Version 1.0

290

Plan Communications Inputs, Tools, and Outputs

Stakeholder register
Stakeholder management
strategy
Enterprise environmental
factors
Organizational process
assets

Communication
requirements analysis
Communications
technology
Communication models
Communication methods

ManagementFramework
Framework
Project Management

Communication
management plan
Project documents
updates

Version 1.0

291

Communications Requirements Analysis

Number of communication channels : [ n ( n -1) ]


2
where n = Number of stakeholders

Continue
ManagementFramework
Framework
Project Management

Version 1.0

292

Communications Requirements Analysis

Number of communication
channels = [ n ( n -1) ]
2
= [ 5 ( 5 -1) ]
2
=10

ManagementFramework
Framework
Project Management

Version 1.0

293

Communication Technology

Factors that can affect the selection of communication technology


in a project include:

Urgency of the need for information


Availability of technology
Expected project staffing
Duration of the project
Project environment

ManagementFramework
Framework
Project Management

Version 1.0

294

Basic Communication Model


The Sender is responsible for making the information
Clear
Unambiguous and
Complete
so that the Receiver receives it correctly.

The Receiver is responsible for ensuring that the information is received in its entirety,
understood correctly and acknowledged.

ManagementFramework
Framework
Project Management

Version 1.0

295

Communication Methods
Methods used to share information among project stakeholders are classified
into:

Interactive communication Between two or more parties performing


multidirectional exchange of information.
e.g. meetings, phone calls, video conferencing, etc.

Push communication Sent to specific recipients who need to


know the information. e.g. letters, memos, reports, emails, etc.

Pull communication Used for very large audiences that


requires the recipients to access the communication content
at their own discretion.
e.g. intranet sites, e-learning, etc.

ManagementFramework
Framework
Project Management

Version 1.0

296

Communications Management Plan


The Communications Management Plan provides:

Stakeholder communication requirements.


Information to be communicated. (Format, Content,
Level of detail)
Person responsible for communicating the information.
Methods or technology used to convey the information.
Escalation process.
Glossary of common terminology.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

297

Communications Management Plan


Type of
Information

Purpose of
Distribution

Document
Format

Method of
Distribution

Frequency

Requirements
gathering

To understand
customer
requirements

MS Word
document

Meeting and
written
communication

During
project
initiation

Project
manager

Project team

Weekly status

Project status
update

MS Word
document

E-mail
communication
followed by a
meeting

Weekly

Project
manager

All project
stakeholders

Executive
status

To check
progress and
discuss
corrective
actions

MS Power
Point
presentation

Meeting and
written
communication

Bi-weekly

Operations
manager

Senior
executives
and
functional
heads

Knowledge
sharing

To share
lessons
learned

MS Power
Point
presentation

Classroom
Presentation

Monthly

Team
members

Project team

ManagementFramework
Framework
Project Management

Person
Responsible

Audience

Version 1.0

298

Distribute Information
It is the process of making relevant information available to project
stakeholders as planned, this involves:
Implementing communications management plan
Responding to unexpected requests for information
Information distribution methods
include:
Sender-receiver models
Choice of media
Writing style
Meeting management techniques
Presentation techniques
Facilitation techniques
ManagementFramework
Framework
Project Management

Version 1.0

299

Distribute Information Inputs, Tools, and Outputs

Project management
plan

Performance reports
- Used to distribute project
performance and status
information,
- Should be made available
prior to project meetings,
- Should be as precise and
current as possible.
Organizational process
assets

Communication methods
Information distribution tools
- Hard-copy document
distribution
- Electronic communication
and conferencing tools
- Electronic tools for project
management

ManagementFramework
Framework
Project Management

Organizational process
assets updates
- Stakeholder notifications
- Project reports
- Project presentation
- Project records
- Feedback from
stakeholders
- Lessons learned
documentation

Version 1.0

300

Manage Stakeholder Expectations


It is the process of communicating and working with stakeholders to meet their
needs and addressing issues, such as:
Actively managing the expectations of stakeholders
Addressing concerns that have not become issues yet
Clarifying and resolving issues that have been identified

Managing expectations helps to increase the probability


of project success by ensuring that the stakeholders
understand the project benefits and risks.

ManagementFramework
Framework
Project Management

Version 1.0

301

Manage Stakeholder Expectations Inputs, Tools, and


Outputs

Stakeholder register
Stakeholder management
strategy
Project management plan
Issue log
Change log
Organizational process
assets

Communication
methods
Interpersonal skills
Management skills

ManagementFramework
Framework
Project Management

Organizational process
assets updates
Change requests
Project management
plan updates
Project document
updates

Version 1.0

302

Issue Log
Used to document and monitor the resolution of issues.
Used to facilitate communication and ensure a common
understanding of
issues.

Date Raised Person Resolution


Date
Issue # Issue
Status
Resolution
Added By Assigned Due Date
Resolved

ManagementFramework
Framework
Project Management

Version 1.0

303

Report Performance
It is the process of collecting and distributing performance
information,
including status reports, progress measurements, and forecasts.

The performance reporting process involves:


Periodic collection and analysis of baseline versus actual data
Forecasting the project results

Types of Performance Reports

Simple Reports

Elaborate Reports

- Analysis of past performance


- Performance information,
- Current status of risks and issues
such as percent complete,
or status dashboards for each area - Work completed during the period and to be completed n
- Other relevant information which must be reviewed and
(i.e., scope, schedule, cost, and quality)
discussed
ManagementFramework
Framework
Project Management

Version 1.0

304

Report Performance Inputs, Tools, and Outputs

Project management plan


Work performance

information
Work performance

measurements
Budget forecasts

Organizational process assets

Variance analysis
Forecasting
methods
Communication
methods
Reporting systems

ManagementFramework
Framework
Project Management

Performance reports
Organizational
process
assets updates
Change requests

Version 1.0

305

Communications Methods

ManagementFramework
Framework
Project Management

Version 1.0

306

Report Performance Tools and Techniques


Forecasting Methods The process of predicting future
project performance based on the actual performance to
date.
Classification of Forecasting Methods:
Time series methods Use historical data as the basis for estimating

future outcomes. Example, earned value, moving average, etc.


Casual/econometric methods Use the assumption that it is possible to
identify the underlying factors that might influence the variable that is
being forecasted. Example, sale of umbrellas associated with weather
conditions.
Judgmental methods Incorporate intuitive judgements, opinions, and
probability estimates. Example, composite forecasts, surveys, etc.
Other methods Include simulation, probabilistic forecasting, and
ensemble forecasting.

ManagementFramework
Framework
Project Management

Version 1.0

307

Tabular Performance Report Sample

ManagementFramework
Framework
Project Management

Version 1.0

308

ManagementFramework
Framework
Project Management

Version 1.0

309

PROJECT PROCUREMENT MANAGEMENT

Project Management Framework

ManagementInstitute,
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Inc

Version 1.0

310

Course Structure
Project Procurement Management
Introduction
Project Procurement Management Introduction
Plan Procurements
Plan Procurements : Inputs, Tools, and Outputs
Conduct Procurements
Conduct Procurements : Inputs, Tools, and Outputs
Administer Procurements
Administer Procurements : Inputs, Tools, and Outputs
Close Procurements
Close Procurements : Inputs, Tools, and Outputs

ManagementFramework
Framework
Project Management

Version 1.0

311

Project Procurement Management


Introduction

ManagementFramework
Framework
Project Management

Version 1.0

312

Project Procurement Management Introduction


The processes necessary to purchase or acquire products, services, or results needed

from outside the project team.

The organization can be either the buyer or seller of the products, services, or results of

a project.
It includes the contract management and change control

processes required to develop and administer contracts or


purchase orders.

ManagementFramework
Framework
Project Management

Version 1.0

313

Contract

A contract is a mutually binding agreement that obligates:


Seller to provide the specified products, services, or
results.
Buyer to provide monetary or other valuable
consideration.

It is a legal relationship subject to remedy in courts.

Legally binding nature of a contract usually means that it


will be subjected to a more extensive approval process.

The project management team may seek support early from


specialists in contracting, purchasing, law, and technical
disciplines.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

314

Contract

Depending upon the application area, the seller can also be called contractor,
subcontractor, or vendor, service provider, or supplier.

Depending on the buyers position in the project acquisition cycle, the buyer can
be called a client, customer, prime contractor, contractor, acquiring organization,
service requester, or purchaser.

ManagementFramework
Framework
Project Management

Version 1.0

315

Project Procurement Management Processes


Project Procurement Management processes includes:
Plan Procurements process of documenting project purchasing decisions,
specifying the approach, and identifying potential sellers.
Conduct Procurements process of obtaining seller responses, selecting a
seller, and awarding a contract.
Administer Procurements process of managing procurement relationships,
monitoring contract performance, and making changes and corrections as needed.
Close Procurements process of completing each project procurement.

ManagementFramework
Framework
Project Management

Version 1.0

316

Centralized vs. Decentralized Contracting


CENTRALISED CONTRACTING
Advantages
Increased expertise in
contracting.
Standardized company
practices.
Contracting professional have a
clearly defined career path.
Dept will provide its employees
training/shared knowledge for
continuous improvement.
Disadvantages
Contracting help may be difficult
to obtain as & when needed.
Contract person may be shared
by different projects

DECENTRALISED CONTRACTING
Advantages
Easier access to contracting
expertise.
Loyalty to the project.
More focused contracting
experience.
Disadvantages
No Home Department for contract
person, after project is completed.
Difficult to maintain high level of
contracting expertise.
Lack of standardization & replication
of efforts.

ManagementFramework
Framework
Project Management

Version 1.0

317

Project Managers Role in Procurement


In procurement, the Project Manager should:

Know the procurement process.


Understand contract terms and conditions.
Make sure the contract contains all Project Management Requirements
(Attendance at meeting, reporting, communication etc.)
Identify risks and incorporate mitigation and allocation of risks into the
contract.
Help tailor the contract to the unique needs of the project.
Incorporate schedule for procurement process into the schedule for the project.
Be involved during contract negotiations to protect relationship with the seller
and protect the integrity of the project.
Uphold the entire contract (Not just the contract statement of work).
Work with the Contract Manager to manage changes to the contract.

ManagementFramework
Framework
Project Management

Version 1.0

318

Plan Procurements

ManagementFramework
Framework
Project Management

Version 1.0

319

Plan Procurements
The process of documenting project purchasing decisions, specifying the
approach, and identifying potential sellers.

This process involves determining:

ManagementFramework
Framework
Project Management

Version 1.0

320

Plan Procurement Inputs, Tools, and Outputs

Scope baseline
- Scope statement, WBS, and
WBS dictionary

Requirements documentation

Teaming agreements
Risk register
Risk-related contract decisions
Activity resource requirements
Project schedule
Activity cost estimates
Cost performance baseline
Enterprise environmental factors
Organizational process assets

Make-or-buy
analysis
Expert judgment
Contract types

ManagementFramework
Framework
Project Management

Procurement
management plan
Procurement
statements of work
Make-or-buy
decisions
Procurement
documents
Source selection
criteria
Change requests

Version 1.0

321

Plan Procurements Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 12-3. Page 318.

ManagementFramework
Framework
Project Management

Version 1.0

322

Plan Procurement Inputs


Requirements documentation include:
Important information about project requirements that is considered
during planning for procurements.
Requirements with contractual and legal implications that may
include health, safety, security

Teaming agreements:

Teaming agreements are legal contractual agreements between


two or more entities to form a partnership or joint venture, or some
other arrangements as defined by the parties.

Teaming agreement ends with the ending of new business opportunity.

ManagementFramework
Framework
Project Management

Version 1.0

323

Make-or-Buy Analysis
A general management technique used to determine whether particular work can
best be accomplished by the project team or must be purchased from outside
sources.
Budget constraints may influence make-or-buy decisions.
The analysis includes both indirect as well as direct costs.

ManagementFramework
Framework
Project Management

Version 1.0

324

Contract Types
The risk shared between the buyer and seller is determined by the contract type.

Types of Contract

Fixed-price Contracts

Cost-reimbursable
Contracts

Time and Material


Contracts (T&M)

Continue
ManagementFramework
Framework
Project Management

Version 1.0

325

Fixed-price Contracts
Examples
Firm Fixed Price Contract
(FFP)

Contract = $1,100,000

Fixed Price Incentive Fee


Contract (FPIF)

Contract = $1,100,000. For every month


early the project is finished, an
additional $10,000 is paid to the seller.

Fixed Price with Economics


Price Adjustment Contract
(FP- EPA)

Contract = $1,100,000, but a price


increase will be allowed in year two
based on the U.S. Consumer Price Index
report for the year one.
Contract = the contract price is
$1,100,000 but a price increase will be
allowed in year two to account for
increases in specific material costs.
ManagementFramework
Framework
Project Management

Version 1.0

326

Cost-reimbursable
Contracts
Cost Plus Fixed Fee
Contracts (CPFF)

Cost Plus Award Fee


Contracts (CPAF)

Examples
Contract = Cost plus a fee of $1,100,000

Contract = Cost plus $5,000 for every


month production exceeds 100,000 units.
Maximum award available is $50,000.
Contract = Cost plus an award fee (to be
determined) for each deliverable
completed at least 7 days early.
X -- 10
X - Y -- 20
X + Y -- 5

Cost Plus Incentive Fee


Contracts (CPIF)
Cost Plus Percentage of
Cost Contracts (CPPC)

Continue
ManagementFramework
Framework
Project Management

Version 1.0

327

Time and Material


Contracts (T&M)

Example

Contract = $100 per hour plus expenses


or materials at cost.
Contract = $100 per hour plus materials
at $5 per linear meter of wood.

ManagementFramework
Framework
Project Management

Version 1.0

328

Risk and Contract Types

ManagementFramework
Framework
Project Management

Version 1.0

329

Plan Procurement Outputs


Procurement Management Plan
Describes how the procurement process will be managed from developing
procurement documents through contract closure. This includes:
Types of contracts to be used
Risk management issues
Whether independent estimates will be used and if they are needed as

evaluation criteria;
Managing multiple suppliers;
Coordinating procurement with other project aspects, such as scheduling
and performance reporting
Constraints and assumptions that could affect planned procurements
Establishing the form and format to be used for the procurement/contract
statements of work
Identifying prequalified sellers
Procurement metrics to manage contracts and evaluate sellers.
Handling the make-or-buy decisions and linking them into the Estimate Activity
Resource and Develop Schedule processes
Identifying requirements for performance bonds or insurance contracts to mitigate some
forms of project risk
Establishing the direction to be provided to the sellers on developing and maintaining a
work breakdown structure (WBS)
ManagementFramework
Framework
Project Management

Version 1.0

330

Plan Procurement Outputs


A Procurement Management Plan can be:
Formal or informal
Highly detailed or broadly framed
Based upon the needs of each project

Procurement Statements of work


The statement of work (SOW) for each procurement is developed from the
project scope baseline and defines only that portion of the project scope that is
to be included within the related contract.

ManagementFramework
Framework
Project Management

Version 1.0

331

Plan Procurement Outputs


Procurement Documents
Common terms for different types of procurements include:

Request for information (RFI),

Invitation for bid (IFB),

Request for proposal (RFP),

Request for quotation (RFQ),

Tender notice,

Invitation for negotiation, and

Invitation for sellers initial response

Source Selection Criteria


Selection criteria are often included as a part of the procurement documents.
Such criteria are developed and used to rate or score seller proposals, and
can be objective or subjective

ManagementFramework
Framework
Project Management

Version 1.0

332

Plan Procurement Outputs


Source Selection Criteria, examples:

Understanding of need
Overall or life-cycle cost
Technical capability
Risk
Management approach
Technical approach
Warranty
Financial capacity
Production capacity and interest
Business size and type
Past performance of sellers
References
Intellectual property rights
Proprietary

ManagementFramework
Framework
Project Management

Version 1.0

333

Conduct Procurement

ManagementFramework
Framework
Project Management

Version 1.0

334

Conduct Procurements
The process of obtaining seller responses,
selecting a seller, and awarding a Contract.
The team will receive bids or proposals and
will apply previously defined selection criteria
to select one or more sellers who are qualified
to perform the work and acceptable as a seller.

ManagementFramework
Framework
Project Management

Version 1.0

335

Conduct Procurements Inputs, Tools, and Outputs

Project management plan


Procurement documents
Source selection criteria
Qualified seller list
Seller proposals
Project documents
Make-or-buy decisions
Teaming agreement
Organizational process
assets

Bidder conferences
Proposal evaluation
techniques
Independent
estimates
Expert judgment
Advertising
Internet search
Procurement
negotiations

ManagementFramework
Framework
Project Management

Selected sellers
Procurement contract
award
Resource calendars
Change requests
Project management
plan updates
Project document
updates

Version 1.0

336

Conduct Procurements Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 12-5. Page 329.

ManagementFramework
Framework
Project Management

Version 1.0

337

Conduct Procurements Tools and Techniques


Bidder Conferences (also called as contractor, vendor, and
pre-bid conferences)
- meetings with sellers and buyers prior to submission of a bid
or proposal
- these conferences used to ensure that:
- prospective sellers have a clear and common
understanding of the procurement
(technical and contractual requirements)
- no bidders receive preferential treatment
- incorporation of responses on questions
into the procurement documents as
amendments
- sellers hear every question from each
seller and answers from the buyer

ManagementFramework
Framework
Project Management

Version 1.0

338

Administer Procurements

ManagementFramework
Framework
Project Management

Version 1.0

339

Administer Procurements

The process of managing procurement relationship, monitoring contract


performance, and making changes and corrections as needed.

Due to varying organizational structures, many


organizations treat contract administration
as an administrative function separate from the
project organization.

While a procurement administrator may be on


the project team, this individual typically reports
to a supervisor from a different department.

ManagementFramework
Framework
Project Management

Version 1.0

340

Administer Procurements
Project Management Processes that apply to Contractual
relationship include:

Direct & Manage Project Execution to authorize the sellers work at


the appropriate time
Report Performance to monitor contract scope,
cost, schedule, and technical performance
Perform Quality Control to inspect and verify
the adequacy of the sellers product
Perform Integrated Change Control to assure
that changes are approved and conveyed to all the
concern people
Monitoring and Control Risk to ensure that risks are mitigated

ManagementFramework
Framework
Project Management

Version 1.0

341

Administer Procurements Inputs, Tools, and Outputs

Procurement documents
Project management plan
Contract
Performance reports
Approved change

requests
Work performance
information

Contract change control

system
Procurement
performance
reviews
Inspections and audits
Performance reporting
Payment systems
Claims administration
Records management
system

ManagementFramework
Framework
Project Management

Procurement

documentation
Organizational process
assets updates
Change requests
Project management
plan
updates

Version 1.0

342

Administer Procurements Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 12-7. Page 336.

ManagementFramework
Framework
Project Management

Version 1.0

343

Close Procurements

ManagementFramework
Framework
Project Management

Version 1.0

344

Close Procurements

The process of completing each project procurement.

It also involves administrative activities such as:


- Finalizing open claims,
- Updating records to reflect final results and
- Archiving such information for future use

Unresolved claims may be subjected to litigation after


Contract Closure.

The contract terms and conditions can prescribe specific procedure for
Contract Closure.

ManagementFramework
Framework
Project Management

Version 1.0

345

Close Procurements Inputs, Tools, and Outputs

Project management

plan
Procurement
documentation

Procurement audits
Negotiated settlements
Records management

Closed procurements
Organizational process

assets updates

system

ManagementFramework
Framework
Project Management

Version 1.0

346

Close Procurements Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 12-9. Page 342.

ManagementFramework
Framework
Project Management

Version 1.0

347

Close Procurements Tools and Techniques

Procurement audits
Is a structured review of the procurement process originating

from the Plan Procurement process through Administer


Procurements.
Objective to identify successes and failures that warrant

recognition in the preparation or administration of other


procurement contracts on the project or other projects within
the performing organization.

ManagementFramework
Framework
Project Management

Version 1.0

348

Management
Framework
Management
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Institute,
Inc

Version 1.0

349

PROJECT RISK MANAGEMENT

ManagementFramework
Framework
Project Management

Version 1.0

350

Course Structure
Project Risk Management
Introduction
Project Risk Management Introduction
Plan Risk Management
Plan Risk Management : Inputs, Tools, and Outputs
Identify Risks
Identify Risk : Inputs, Tools, and Outputs
Perform Qualitative Risk Analysis
Perform Qualitative Risk Analysis : Inputs, Tools, and Outputs
Perform Quantitative Risk Analysis
Perform Quantitative Risk Analysis : Inputs, Tools, and Outputs
Plan Risk Responses
Plan Risk Response : Inputs, Tools, and Outputs
Monitor and Control Risks
Monitor and Control Risks : Inputs, Tools, and Outputs
ManagementFramework
Framework
Project Management

Version 1.0

351

Project Risk Management Introduction


Project Risk is an uncertain event or condition. If it occurs,
it has a positive or negative effect on at least one project
objective ( i.e. Time, Cost, Scope or Quality). Project Risk is
always in future
A risk may have
one or more causes and
if it occurs, one or more impacts.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

353

Project Risk Management Introduction


Some examples of areas of uncertainty are since we fail to:
Understand who the project is for
Appoint an executive user responsible for sponsoring the project
Appoint a fully qualified and supported project manager
Define the objectives of the project
Secure commitments from people who are needed to assist with the
project
Estimate costs accurately
Specify very precisely the end users' requirements

Continue
ManagementFramework
Framework
Project Management

Version 1.0

354

Project Risk Management


Risk conditions could include aspects of the projects or
organizations environment, such as:
Poor project management practices.
Lack of integrated management system.
Concurrent multiple projects.
Dependency on participants not under control,

etc.

Continue
ManagementFramework
Framework
Project Management

Version 1.0

355

Risk Process Overview

ManagementFramework
Framework
Project Management

Version 1.0

356

Project Risk Management - Processes

ManagementFramework
Framework
Project Management

Version 1.0

358

Process - Plan Risk Management


The process of deciding to approach and conduct risk
management activities for a project.

It ensures that level, type and visibility of risk management are


commensurate with
Risks and
Importance of the project to the organization.

It also ensures that:


Sufficient resources and time are provided to manage
risks.
There is agreed upon basis for evaluating risks.

ManagementFramework
Framework
Project Management

Version 1.0

360

Plan Risk Management Inputs, Tools, and


Outputs

Project scope
statement
Cost management plan
Schedule management
plan
Communications
management plan
Enterprise
environmental factors
Organizational process
assets

Planning meetings and analysis

ManagementFramework
Framework
Project Management

Risk management
plan

Version 1.0

361

Plan Risk Management


Plan Risk Management includes the following:

Methodology (Approach, tools & data sources)

Roles and Responsibilities

Budgeting (Cost for the risk management


processes)

Timing (How & when the Risk Management


activities will be performed throughout
the project lifecycle).

Continue
ManagementFramework
Framework
Project Management

Version 1.0

362

Plan Risk Management

Risk Categories (Risk Breakdown Structure (RBS))

Definition of Risk

Probability Levels and

Impact Levels

Probability and Impact Matrix

Stakeholder Risk Tolerances

Reporting Formats (Content & Format of Risk Register)

Risk Tracking Mechanism


ManagementFramework
Framework
Project Management

Version 1.0

363

Risk Breakdown Structure

(As per PMBOK Guide)

ManagementFramework
Framework
Project Management

Version 1.0

364

Impact Levels (As per PMBOK

ManagementFramework
Framework
Project Management

Guide)

Version 1.0

365

Probability and Impact Matrix (As per PMBOK

ManagementFramework
Framework
Project Management

Guide)

Version 1.0

366

Questions to be Addressed in a Plan Risk


Management

Why is it important to take/not take this risk in relation to the


project objectives?

What is the specific risk, and what are the risk mitigation
deliverables?

How is the risk going to be mitigated? (What risk mitigation


approach is to be used?)

Who are the individuals responsible for implementing the risk management plan?

When will the milestones associated with the mitigation approach occur?

How much is required in terms of resources to mitigate risk?

ManagementFramework
Framework
Project Management

Version 1.0

367

Plan Risk Management Data Flow Diagram

ManagementFramework
Framework
Project Management

Version 1.0

368

Process - Identify Risks


It determines which risks might effect the project and
documents their characteristics.
All project personnel should be encouraged to identify risks.
Iterative process - new risks may become known as the
project progresses through its life cycle.
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
ManagementFramework
Framework
Project Management

Methods for
prioritizing identified
risks
Version 1.0

370

Identify Risks Inputs, Tools, and Outputs

Risk management plan


Activity cost estimates
Activity duration estimates
Scope baseline
Stakeholder register
Cost management plan
Schedule management
plan
Quality management plan
Project documents
Enterprise environmental
factors
Organizational process
assets

Documentation reviews
Information gathering
techniques
Checklist analysis
Assumptions analysis
Diagramming techniques
SWOT analysis
Expert judgment

ManagementFramework
Framework
Project Management

Risk
register

Version 1.0

371

Identify Risks Tools and Techniques


Documentation reviews
Risk information gathering techniques. (Brainstorming,
Delphi, Interviewing, Root Cause Identification)
Checklist Analysis
Assumptions Analysis
Diagramming techniques (Causeand- Effect Diagram,
Process Flow Charts, System Flow Charts, Influence
Diagrams)

ManagementFramework
Framework
Project Management

Version 1.0

372

Risk Register
The primary output of risk identification and is a
component of the Project Management Plan.

Contents of Risk Register

List of

List of

identified risks

potential responses

Root causes of risk

ManagementFramework
Framework
Project Management

Updated
risk categories

Version 1.0

373

Identify Risks Data Flow Diagram

ManagementFramework
Framework
Project Management

Version 1.0

374

Process - Perform Qualitative Risk Analysis


The specific objectives of perform qualitative risk analysis are:

Subjectively evaluate the probability and impact of


each risk.

Create a starter list of risks by determining the


critical or top risks that you will quantify further.

Go / No- Go decision (having evaluated the risks,


do we still want to do this project).

ManagementFramework
Framework
Project Management

Version 1.0

376

Perform Qualitative Risk Analysis


Beginning in qualitative risk analysis, the project team
relies on the data about risk acquired in risk
identification
(Data Precision ranking : how well understood is the
risk).
It should include analysis of the following:

Extent of understanding of the risk.

Data available about the risk.

Reliability and Integrity of the data.

ManagementFramework
Framework
Project Management

Version 1.0

377

Perform Qualitative Risk Analysis Inputs,


Tools, and Outputs

Risk register
Risk management plan
Project scope statement
Organizational process
assets

Risk probability and impact

assessment
Probability and impact matrix
Risk data quality assessment
Risk data categorization
Risk urgency assessment
Expert Judgement

ManagementFramework
Framework
Project Management

Risk register updates

Version 1.0

378

Tigers - High Probability, High Impact. These are dangerous animals and must be neutralized

as soon as possible.
Alligators - Low Probability, High Impact. These are dangerous animals which can be
avoided with care.
Puppies - High Probability, Low Impact. We all know that delightful pup will grow into an
animal which can do damage, but a little training will ensure that not too much trouble
ensures.
Kittens - Low Probability, Low Impact. The largest cat is rarely the source of trouble, but on
the other hand a lot of effort can be wasted on training it!
ManagementFramework
Framework
Project Management

Version 1.0

379

Perform Qualitative Risk Analysis Data Flow Diagram

ManagementFramework
Framework
Project Management

Version 1.0

380

Process - Perform Quantitative Risk Analysis

The specific objectives of perform quantitative risk analysis include:

Numerically evaluating probability and impact of


each risk.

Determining the level of risk the project currently


has and whether that level of risk is acceptable
for the expected gain from the product of the
project.

Determining the probability of cost or schedule


objectives for the project.

ManagementFramework
Framework
Project Management

Version 1.0

382

Perform Quantitative Risk Analysis Inputs,


Tools, and Outputs

Risk register
Risk management plan

Cost management plan


Schedule management plan

Organizational process assets

Data gathering and


representation techniques
Quantitative risk analysis
and modelling techniques
Expert judgement

ManagementFramework
Framework
Project Management

Risk register
updates

Version 1.0

383

Perform Quantitative Risk Analysis Tools and


Techniques
Data Gathering and Representation Techniques
Interviewing

Range of Project Cost Estimates Collected During the Risk Interview

ManagementFramework
Framework
Project Management

Version 1.0

384

Perform Quantitative Risk Analysis


Commonly used techniques in perform quantitative risks analysis
include:

Sensitivity Analysis

Decision Tree Analysis

Expected Monetary Value Analysis (EMV)

Modeling and Simulation

ManagementFramework
Framework
Project Management

Version 1.0

385

Sensitivity Analysis
Sensitivity analysis helps to determine which risks have the most potential impact on
the project. It examines the extent to which the uncertainty of each project element
affects the objective being examined when all other uncertain elements are held at their
baseline values. One typical display of sensitivity analysis is the tornado diagram,
which is useful for comparing relative importance and impact of variables that have a
high degree of uncertainty to those that are more stable.

R1
R2
R3
R4
R5
ManagementFramework
Framework
Project Management

Version 1.0

386

Decision Tree Analysis


Diagrams that show the sequence of interrelated decisions and the expected results
of choosing one alternative over the other.
Lets take an example of a company which is trying to decide whether an e-learning
prototyping is worthwhile on the project. The impact of whether the equipment
works or fails is shown in the diagram below. As per the information provided in the
diagram, what is the expected monetary value of your decision?
E-learning Prototype:
Setup cost $200,000

Failure: 35% probability and $120,000


impact
Pass: No impact
Failure: 70% probability and
$450,000 impact
Pass: No impact

Do not e-learning prototype:


Setup cost $0
ManagementFramework
Framework
Project Management

Version 1.0

387

Expected Monetary Value Analysis (EMV)


Calculated by multiplying the probability of the risk times its impact and then
adding them together. Positive results indicate opportunities and negative
generally indicate threat to the project.
EMV = P x I
(where, P = Probability and I = Times Impact)

Continue
ManagementFramework
Framework
Project Management

Version 1.0

388

Expected Monetary Value Analysis (EMV)

Continue
ManagementFramework
Framework
Project Management

Version 1.0

389

Expected Monetary Value Analysis (EMV)

ManagementFramework
Framework
Project Management

Version 1.0

390

Expected Monetary Value Analysis (EMV)

Continue
ManagementFramework
Framework
Project Management

Version 1.0

391

Expected Monetary Value Analysis (EMV)

Airline A

(20% * Rs. 50,000 = Rs. 10,000) + (80% * Rs. 0 = Rs. 0) + Rs. 9,000
= Rs. 19,000

Airline B

(40% * Rs. 50,000 = Rs. 20,000) + (60% * Rs. 0 = Rs. 0) + Rs. 3,000
= Rs. 23,000

ManagementFramework
Framework
Project Management

Version 1.0

392

Modeling and Simulation

A project simulation uses a model that translates the specified detailed uncertainties of the pro
into their potential impact on project objectives. Iterative simulations are typically performed u
the Monte Carlo technique. In a simulation, the project model is computed many times (iterated
with the input values (e.g., cost estimates or activity durations) chosen at random for each itera
from the probability distributions of these variables.

ManagementFramework
Framework
Project Management

Version 1.0

393

Perform Quantitative Risk Analysis Data Flow


Diagram

ManagementFramework
Framework
Project Management

Version 1.0

394

Process - Plan Risk Responses


It involves arriving at strategy or mix of strategies most likely to be
effective for each risk.
Primary and Back-up strategy may be selected.
A Fall back plan can be developed if the selected strategy does not
turn to be fully effective or if an accepted risk occurs.
Contingency plan can be developed, along with identification of
conditions that trigger their execution.

ManagementFramework
Framework
Project Management

Version 1.0

396

Plan Response Responses Inputs, Tools,


and Outputs

Risk register
Risk
management
plan

Strategies for negative risks


or threats
Strategies for positive risks
or opportunities
Contingent response strategy
Expert judgement

ManagementFramework
Framework
Project Management

Risk register updates


Risk-related
contractual
agreements
Project management
plan updates
Project document
updates

Version 1.0

397

Plan Risk Responses - Strategies

ManagementFramework
Framework
Project Management

Version 1.0

398

Plan Response Responses Data Flow Diagram

ManagementFramework
Framework
Project Management

Version 1.0

399

Process - Monitoring and Control Risks

Project work should be continuously monitored for new and changing


risks.

Monitoring and Control Risks involves:

Identifying, analyzing and planning for newly arising risks.


Keeping track of identified risks and those on the watch list.
Monitoring trigger conditions for contingency plans.
Monitoring residual risks.
Reviewing the execution of risk responses.

ManagementFramework
Framework
Project Management

Version 1.0

401

Residual Risk, Secondary Risk & Workaround


Residual Risk A risk that remains after risk responses have been implemented.
Secondary Risk A risk that arises as a direct result of implementing a risk response.
Workaround A response to a negative risk that has occurred. Distinguished from
contingency plan in that a workaround is not planned in advance of the occurrence of
the risk event.

ManagementFramework
Framework
Project Management

Version 1.0

402

Monitoring & Control Risks Inputs, Tools,


and Outputs

Risk register
Project management
plan
Work performance
information
Performance reports

Risk reassessment
Risk audits
Variance and trend
analysis
Technical performance
measurement
Reserve analysis
Status meetings

ManagementFramework
Framework
Project Management

Risk register updates


Organizational
process assets
updates
Change requests
Project management
plan updates
Project document
updates

Version 1.0

403

Risk Audits
Risk Audits examine and document effectiveness of risk
responses in dealing with:

Identified risks and their root causes and

Effectiveness of the risk management Process

ManagementFramework
Framework
Project Management

Version 1.0

404

Monitor and Control Risks Data Flow Diagram

ManagementFramework
Framework
Project Management

Version 1.0

405

ManagementFramework
Framework
Project Management

Version 1.0

406

PROJECT QUALITY MANAGEMENT

Management
Framework
Management
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Institute,
Inc

Version 1.0

407

Course Structure
Project Quality Management
Introduction
Project Quality Management Introduction
Plan Quality
Plan Quality : Inputs, Tools, and Outputs
Perform Quality Assurance
Perform Quality Assurance : Inputs, Tools, and Outputs
Perform Quality Control
Perform Quality Control : Inputs, Tools, and Outputs

ManagementFramework
Framework
Project Management

Version 1.0

408

Project Quality Management Introduction

ManagementFramework
Framework
Project Management

Version 1.0

409

Project Quality Management - Introduction

The processes and activities of the performing organization that determine


quality policies, objectives, and responsibilities to satisfy the project needs.

The Project Quality Management processes include:


Plan Quality process of identifying quality requirements and/or standards

for the project and product and documenting how the project will demonstrate
compliance.
Perform Quality Assurance process of auditing the quality requirements

and the results from quality control measurements to ensure appropriate quality
standards and operational definitions are used.

Perform Quality Control process of monitoring and recording results of

executing the quality activities to assess performance and recommend


necessary changes.
ManagementFramework
Framework
Project Management

Version 1.0

410

Product Quality vs. Project Quality


Project quality management addresses the management of project and product
of the project and applies to all projects, regardless of the nature of their
product.
Product quality measures and techniques are specific to the type of product
produced by the project.
Failure to meet product or project quality requirements can have serious
negative consequences for any or all of project stakeholders, which may lead to:
Employees attrition
Errors
Rework

ManagementFramework
Framework
Project Management

Version 1.0

412

Quality vs. Grade

Quality is the degree to which a set of inherent


characteristics fulfill requirements (Customer,
Project).

Grade is a category assigned to products or


services having the same functional use but
different technical characteristics.

Low quality is always a problem; low grade may


not be.

Project Manager and Project Management Team


are responsible for determining and delivering the
required level of both quality
and grade.
Quality and Grade are not the same

ManagementFramework
Framework
Project Management

Version 1.0

413

Precision vs. Accuracy

Precision and Accuracy are not equivalent.


Precision The values of repeated

measurements are clustered and have little


scatter. (not necessarily accurate)
Accuracy The measured value is very close
to the true value. (not necessarily precise)

The Project Management Team must determine, how much accuracy or precision or
both are required.

ManagementFramework
Framework
Project Management

Version 1.0

414

Modern Quality Management


Complements project management as both recognize the importance of:

Customer Satisfaction

Prevention over Inspection

Continuous Improvement

Management Responsibility

Process improvement models include Malcolm Baldrige, OPM3 CMMI.

ManagementFramework
Framework
Project Management

Version 1.0

415

Control Limits vs. Tolerance


Control Limits: are the limits within which the variation of the process is
permitted and are determined by the organizations quality standard.
Tolerance: The result is acceptable if it falls within the range specified by the
tolerance.

ManagementFramework
Framework
Project Management

Version 1.0

416

Process - Plan Quality

The process of identifying quality requirements and/or standards for the project and
product, and documenting how the project will demonstrate compliance.
This process should be performed in parallel with the other project planning
processes.
E.g. Proposed changes in the product to meet identified quality standards may
require cost or schedule adjustments and a detailed risk analysis.

ManagementFramework
Framework
Project Management

Version 1.0

418

Plan Quality Inputs, Tools, and Outputs

Scope baseline
Stakeholder register
Cost performance
baseline
Schedule baseline
Risk register
Enterprise environmental
factors
Organizational process
assets

Cost benefit analysis


Cost of quality

Control charts

Benchmarking

Design of experiments
Statistical sampling
Flowcharting
Proprietary quality
management
methodologies

Additional quality planning


tools
ManagementFramework
Framework
Project Management

Quality management
plan
Quality Metrics
Quality checklists
Process improvement
plan
- Process boundaries
- Process configuration
- Process metrics
- Targets for improved
performance

Project document
updates
Version 1.0

419

Plan Quality Inputs


Quality Policy
Project should have a Quality Policy.

Quality Policy
Either

By Performing
Organization

Or

By Project Management
Team

ManagementFramework
Framework
Project Management

Version 1.0

420

Plan Quality Tools and Techniques

Cost-Benefit analysis
Cost of quality
Control charts
Benchmarking
Statistical sampling
Design of experiments
Flowcharting
Proprietary quality management methodologies
Additional quality planning tools

ManagementFramework
Framework
Project Management

Version 1.0

421

Plan Quality Outputs


Quality Management Plan:
Describes how the project management team will
implement the performing organization's quality
policy.
Quality Metrics:
An operational definition that describes, in very specific
terms, a project or product attribute and how the quality
control process will measure it.
Quality Checklists:
A structured toll, usually component-specific,
used to verify that a set of required steps has been
performed.
Quality checklists are used in the quality control
process
ManagementFramework
Framework
Project Management

Continue
Version 1.0

432

Plan Quality Outputs


Process improvement Plan:
A subsidiary of the project management plan.
Details the steps for analyzing processes to
identify activities which enhance their value.
Areas to consider include:
Process boundaries
Process configuration
Process metrics
Targets for improved performance
Project Document Updates:
Stakeholder register
Responsibility Assignment Matrix
ManagementFramework
Framework
Project Management

Version 1.0

433

Plan Quality Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 8-3. Page 193.

ManagementFramework
Framework
Project Management

Version 1.0

434

Process - Perform Quality Assurance

Perform Quality Assurance


is the process of auditing

Quality requirements
Results from quality control measurements

To ensure appropriate quality standards and operational definitions are used.


Perform Quality Assurance is an execution process that uses data created during
Perform Quality Control.
Perform Quality Assurance also provides an umbrella
for continuous process improvement,
which Is an iterative means for improving the
quality of all processes.

ManagementFramework
Framework
Project Management

Version 1.0

436

Performance Quality Assurance Inputs, Tools,


and Outputs

Project management plan


- Quality management plan
- Process improvement plan

Quality metrics
Work performance information
Quality control measurements

Plan Quality and Perform


Quality Control tools and
techniques

Quality audits

Process analysis

ManagementFramework
Framework
Project Management

Organizational process
assets updates
Change requests
Project management
plan updates
Project document
updates

Version 1.0

437

Perform Quality Assurance Tools and Techniques

Quality Audits
It is a structured, independent review to determine whether project
activities comply with organizational and project policies, processes,
and procedures.

The objectives of a quality audit are:

Identify all the good/best practices being implemented and all the gaps/shortcomings
Share the good practices introduced or implemented in similar projects
Proactively offer assistance in a positive manner to improve implementation of
processes to help the team raise productivity
Highlight contributions of each audit in the lessons leaned repository of the
organization

They can confirm the implementation of approved change requests including:

Corrective actions
Defect repairs
Preventive actions
Continue
ManagementFramework
Framework
Project Management

Version 1.0

438

Perform Quality Assurance Tools and


Techniques

Process Analysis

Follows the steps outlined in the process improvement plan to


identify needed improvements

Process analysis includes root cause analysis A specific technique to identify a problem

Discover the underlying causes that lead to it

Develop preventive actions

ManagementFramework
Framework
Project Management

Version 1.0

439

Performance Quality Assurance Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 8-9. Page 202.

ManagementFramework
Framework
Project Management

Version 1.0

440

Process - Perform Quality Control


The process of monitoring and recording results of executing the quality activities to:
Assess performance
Recommend necessary changes

Quality control activities identify:


Causes of poor process or product quality
Recommend and/or take action to eliminate them

Continue
ManagementFramework
Framework
Project Management

Version 1.0

442

Perform Quality Control


Key Terminologies

Statistical Quality Control Especially sampling and


probability, to help evaluate quality control outputs

Prevention Keeping errors out of the process


Inspection Keeping errors out of hands of the customer

Attribute Sampling The results either conforms or does not conform


Variables Sampling The result is rated on a continuous scale that
measures the degree of conformity

ManagementFramework
Framework
Project Management

Version 1.0

443

Perform Quality Control Inputs, Tools, and Outputs

Project management
plan
Quality metrics
Quality checklists
Work performance
information
Approved change
requests
Deliverables
Organizational process
assets

Cause and effect


diagram

Control charts

Flowcharting

Histogram

Pareto chart
Run chart
Scatter diagram
Statistical
sampling
Inspection
Approved change
requests review

Quality control measurements


Validated changes
Validated deliverables
Organizational process assets
updates
Change requests
- if the recommended corrective or
preventive actions or a defect repair
requires a change to the project
management plan, a change request
should be initiated in accordance with the
defined Perform Integrated Change
Control

Project management plan updates


Project document updates

ManagementFramework
Framework
Project Management

Version 1.0

444

Perform Quality Control Tools and Techniques


Ishikawas seven basic tools of
quality:
Cause and Effect Diagram
Histogram
Pareto Chart
Run Chart
Scatter Diagram
Control Charts
Flowcharting
Statistical Sampling
Inspection
Approved Change Requests
Project Management Framework
Project Management Framework

Version 1.0

445

Quality Theories
Joseph Juran:
Developed the 80/20 principle.
Advocated Top Management involvement.
Defined Quality as fitness for use.
W. Edwards Deming:
Developed 14 steps to quality management
Advocated Plan - Do Check - Act cycle for quality
improvement.
Philip Crosby:
Popularized the concept of cost of poor quality.
Advocated prevention over inspection & zero
defects.
He believed quality is Conformance to requirements.
ManagementFramework
Framework
Project Management

Version 1.0

452

Perform Quality Control Data Flow Diagram

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOKGuide) Fourth Edition, Project Management Institute, Inc., 2008, Figure 8-11. Page 207.

ManagementFramework
Framework
Project Management

Version 1.0

453

Management
Framework
Management
Framework
The PMI Registered Education Provider logo and PMP are registered marks of theProject
Project Management
Institute,
Inc

Version 1.0

454

Potrebbero piacerti anche