Sei sulla pagina 1di 53

Prepared By:

K.R.THANKI
(BE Civil)
LECTURER CIVIL ENGINEERING
DEPARTMENT
GOVERNMENT POLY TECHNIC ,
JUNAGADH,GUJARAT-INDIA.

10/18/15

Points, Crossings and


Yards of Railways

The arrangements by which


different routes, diverging from
the first track, are connected to
faciliate the diversion of trains
from one track to another track
without any obstruction are
known as points and crossings.

K.R.THANKI
(BE Civil)

Points and Crossings:

10/18/15

Points and Crossings:

K.R.THANKI
(BE Civil)

A complete set of points and


crossings provides for diverting
the trains from a main track to a
branch track is known as turn
out.

10/18/15

Turn out:

10/18/15

Right Hand Turn out:

K.R.THANKI
(BE Civil)

Turn out:

Animated diagram of a right-hand railroad


switch, rail track A divides into two track B
(the straight track) and track C (the
diverging track)

K.R.THANKI
(BE Civil)

Right Hand Turn out:

10/18/15

Turn out:

K.R.THANKI
(BE Civil)

Left Hand Turn out:

10/18/15

Turn out:

1) A pair of Points (Switches):

A switch, turnout or [set of]


points is a mechanical installation
enabling railway trains to be guided
from one track to another.

K.R.THANKI
(BE Civil)

Component parts and Functions :

10/18/15

Turn out:

10/18/15

K.R.THANKI
(BE Civil)

Turn out:

Switches
8

2) A pair of Stock rails:

Stock rails along with their respective


tongue rails from a pair of switches or
points.

facilitate
smooth working of tongue rails.
Function of stock rails is to

K.R.THANKI
(BE Civil)

Component parts and Functions :

10/18/15

Turn out:

10/18/15

K.R.THANKI
(BE Civil)

Turn out:

Stock rails
10

Component parts and Functions :


3) V Crossing:

K.R.THANKI
(BE Civil)

Turn out:

provide gaps between the rails


tobe crossed so that wheel

10/18/15

The function of V crossing is to

flanges can pass through the gaps


without any obstruction.
11

10/18/15

K.R.THANKI
(BE Civil)

Turn out:

V Crossing
12

Component parts and Functions :


4) Two check rails:

check
the tendency of wheels to
climb over the crossing.

K.R.THANKI
(BE Civil)

Turn out:

10/18/15

Function of these rails is to

13

10/18/15

K.R.THANKI
(BE Civil)

Turn out:

Two check rails


14

Component parts and Functions :


5) Four lead rails:

K.R.THANKI
(BE Civil)

Turn out:

the track from heel of switches


to the toe of crossing.

10/18/15

Function of these rails is to Lead

15

10/18/15

K.R.THANKI
(BE Civil)

Turn out:

lead rails
16

6) Switch tie plate:

Function of switch tie plate is to

maintain gauge distance


at front of switch.

K.R.THANKI
(BE Civil)

Component parts and Functions :

10/18/15

Turn out:

17

7) Stud(Stop):

A Bent plate which is jointed to stock


rail is called stop.
Function of stop is to
alignment.

maintain the

K.R.THANKI
(BE Civil)

Component parts and Functions :

10/18/15

Turn out:

18

8) Side Chairs:

Function of Side chair is to

support the tongue rails


throughout their length.

K.R.THANKI
(BE Civil)

Component parts and Functions :

10/18/15

Turn out:

19

Component parts and Functions :


9) Stretcher

bar:

connects
toes of both the tongue rails so
that each tongue rail moves
through same distance.

K.R.THANKI
(BE Civil)

Turn out:

10/18/15

Function of Stretcher bar is to

20

Component parts and Functions


:

K.R.THANKI
(BE Civil)

Turn out:

Function of Rods,Cranks,Lever
is to operate the points.

10/18/15

10) Rods,Cranks,Lever:

21

K.R.THANKI
(BE Civil)
10/18/15

Turn out:

Rods,Cranks,Lever
22

11) Locking System:

Function of Locking System is to

Maintain timing between


signal and tong rails.

K.R.THANKI
(BE Civil)

Component parts and Functions :

10/18/15

Turn out:

23

10/18/15

K.R.THANKI
(BE Civil)

Turn out:

Locking System
24

The arrangements by which


different
routes,
are
connected
without
any
obstructions
is
called

crossings.

K.R.THANKI
(BE Civil)

Crossing:

10/18/15

Crossings:

25

Accordin
g to
Angle

Accordin
g to

Diversio
n

K.R.THANKI
(BE Civil)

Crossin
g
Types:

10/18/15

Crossings:

26

Obtus
e
Angle
Acute
Angle

K.R.THANKI
(BE Civil)

Crossings:

10/18/15

According to
Angle

27

Spring

Crossov
er

Scissor
s

Gatherin
g Lines

Diamo
nd

K.R.THANKI
(BE Civil)

Crossings:

10/18/15

According to
Diversion

28

Acute angle

When angle of crossing rails


become acute angle then this
crossing
is
called
Acute
crossing or V crossing or
Frog.

K.R.THANKI
(BE Civil)

Crossings:

10/18/15

According to
Angle

29

10/18/15

K.R.THANKI
(BE Civil)

Crossings:

V crossing
30

10/18/15

K.R.THANKI
(BE Civil)

Crossings:

V crossing
31

When angle of crossing


rails become Obtuse angle
then this crossing is called
Obtuse crossing.

K.R.THANKI
(BE Civil)

Crossings:

10/18/15

According to
Angle
Obtuse Angle

32

10/18/15

Obtuse
crossing

K.R.THANKI
(BE Civil)

Crossings:

33

K.R.THANKI
(BE Civil)

When angle of crossing rails


become Right angle then this
crossing is called Right angle
crossing or Square crossing.

10/18/15

According to
Crossings:
Angle
Right angle or Square

34

K.R.THANKI
(BE Civil)
10/18/15

Crossings:

Right angle
crossing

35

Crossings:

Spring Crossing:
In this crossing wing rail is strongly
connected to V part by

K.R.THANKI
(BE Civil)

According to
Diversion

so thats why this


crosssing is called spring crossing.
These crossings used in USA but not in
INDIA.

10/18/15

helical spring

36

10/18/15

K.R.THANKI
(BE Civil)

Crossings:

Spring Crossing
37

Crossover Crossing
Function of this crossing
is to connect two

parallel
or
diverging tracks.

K.R.THANKI
(BE Civil)

Crossings:

10/18/15

According to
Diversion

38

10/18/15

Crossove
r

K.R.THANKI
(BE Civil)

Crossings:

39

Scissors Crossing(Double
cross):
This type of crossing consists
4 pair of switch
6 Acute crossings
2 Obtuse crossings
check rails
And this type is use at goods yard.

K.R.THANKI
(BE Civil)

Crossings:

10/18/15

According to
Diversion

40

10/18/15

K.R.THANKI
(BE Civil)

Crossings:

Double cross
41

Diamond Crossing
When two tracks crosses
each other at less than 90
angle
then
it
forms
diamond shape so it is
called Diamond Crossing

K.R.THANKI
(BE Civil)

Crossings:

10/18/15

According to
Diversion

42

10/18/15

Diamond
Crossing

K.R.THANKI
(BE Civil)

Crossings:

43

10/18/15

Diamond
Crossing

K.R.THANKI
(BE Civil)

Crossings:

44

Gathering Lines:
When there is more
than two track divert
from one line then it is
called Gathering lines.

K.R.THANKI
(BE Civil)

Crossings:

10/18/15

According to
Diversion

45

10/18/15

Gathering
Lines

K.R.THANKI
(BE Civil)

Crossings:

46

10/18/15

Gathering
Lines

K.R.THANKI
(BE Civil)

Crossings:

47

To collect ash which are


produced from steam engine.
Depth of ash pit varies from
0.76m
to1.20m
and
constructed from concrete.

K.R.THANKI
(BE Civil)

Functions of Ash pit :

10/18/15

Ash pit:

48

10/18/15

K.R.THANKI
(BE Civil)

Ash pit:

Ash pit
49

To Turn the engine.

K.R.THANKI
(BE Civil)

Function of Turn Table:

10/18/15

Turn Table:

50

10/18/15

Turn

K.R.THANKI
(BE Civil)

Turn Table:

51

10/18/15

Turn

K.R.THANKI
(BE Civil)

Turn Table:

52

K.R.THANKI
(BE Civil)
10/18/15

THANK
YOU

FOR ANY OTHER INFORMATION PLEASE CONTECT ME TO


Email : thankikrunal@yahoo.co.in

53

Potrebbero piacerti anche