Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
(CASE STUDY OF DISPUTE BETWEEN ATHENS GENERATING COMPANY AND BECHTEL POWER CORPORATION )
CONTRACT DETAILS
CONTRACTORS PERSPECTIVE
Reason for delay :
i) Modification in the products by the client ( as per clause 20.1 )
ii) Tornado (as per clause 19.1 V )
iii) Regional power outage
iv) client suspended the use of fuel gas for 35 days due to hike in price ( as per
clause 8.5 b & c )
Contractor also argued that daily rate of $ 49000 / day / turbine constituted an
impermissible penalty
CLIENTS PERSPECTIVE
Product modification are within the scope of contractors contract (as per clause 13.1).
Contractor was aware that Siemens technology for gas turbine is immature.( as per clause
4.4 )
Some of the modification are not needed for the substantial completion of contract and are
made for the convenience of both contractor and sub contractor.(as per clause 5.8)
In any point of time the activities are not on the critical path of work.
Because of tornado , Contractor was entitled to one day of extension on two of three
turbines ( as per clause 19.1 V ).
Contractor was entitled two days of extension on all the three turbines because of
temporary power shutdown at site.
RULING
The panel of arbitrators found that the product modification and project
betterments alleged by the contractor were within the scope of contractors
contract because it is an EPC contract, the time delays and cost caused by the
implementation of product modifications should be borne by the contractor.
Contractors Expert
Witness
FINAL VERDICT
The arbitrators found clients testimony credible and ruled that
the liquidated damages clause in the contract is enforceable
Hence, the contractor was awarded remaining contract price
DEDUCTING the liquidated damages.(as per clause 2.5)
Contract balance = $ 28,303,747
Liquidated damages = $ 26,950,000
Price awarded = $ 1,353,747
THANK YOU