Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Finance
Anil Raawal
21st May 2015
Contents
Lots of Work in Pipeline
Lots of Positives The Trends
Lots of Positives Transmission as Infra
Business
The reality check
The Lag despite Enabling Framework
The Power and the Prayer
The Concerns
Key Risks
The Way Forward
Transmission Scenario
Source CARE
Research
Source -Metis
Transmission Scenario
transformation
transformationcapacity
capacityaddition
addition
th
12
12thPlan
Plan Capex
Capexestimates
estimates
Central
CentralSector
Sector
State
Sector
State Sector
Total
Total
125,000
125,000Cr
Cr
55,000
Cr
55,000 Cr
1,80,000
1,80,000Cr
Cr
(Source: NEP for 12th Plan, CEA and Prospective plan, GoI )
o Sector is Maturing QRs were amended, No of players have settled to a reasonable number
with major players in keen contest.
o Trend line of Est IRR @ 12% indicates upward trending
o Section 68
o Powers now with CEA Chairperson, shall save time.
o Selection of projects
o Powers now shifted to MoP as required under Gazette
Notification
o Section 14 Amendment
The Appropriate Commission may, on an application made to it under section 15, grant a
licence to any person-(a) to transmit electricity as a transmission licensee; or
(b) to distribute electricity as a distribution licensee; or
---------------------------(c) to undertake trading in electricity as an electricity trader, or
(d) to supply electricity as a supply licensee.
PoC Mechanism
o National Electricity Policy mandates that the national tariff framework implemented should be
sensitive to distance, direction and related to quantum of power flow.
o Billing, Collection and Disbursement Agreement ensure a clearing mechanism for all licensees
Effective management of Collection Risk through power regulation.
Media Focus
o Honble Ministers statement of Rs 1 lac crores, transmission has come high on Media agenda
To invite private sector investment in the power transmission sector, the government is
likely to adopt reverse bidding for awarding projects. The new bid document, officials said,
would set a benchmark price below which the companies would need to bid. The move
comes in wake of the government's intention of awarding transmission projects worth Rs 1
lakh crore during the year. Power Finance Corporation (PFC) is in the process to award
around eight new transmission lines.
7
o In recent times transmission has worked as major bottleneck, some facts o Millions of DG sets working, cumulative capacity of 90,000 MW, nearly equal to what was Indias total installed power
generation capacity just over a decade ago (March 2002) and about 36 per cent of the current installed generation capacity.
o DG capacity is growing at a rate of 5,000 MW to 8,000 MW every year. That is higher than the cumulative nuclear and solar
capacities being added year-on-year in the country.
o In 2012-13, domestic power exchanges Indian Energy Exchange and Power Exchange of India failed to consummate salespurchase deals worth Rs.1,350 Crores , amounting to 15% of total traded volume of power, due to transmission constraints.
o Resource rich states like Chhattisgarh are also unable to evacuate the excess power. With an expected power
generation capacity in excess of 30,000 MW by end of 12th plan, against the state's peak demand requirement of about
3,300 MW, currently there is only 7000 MW of transmission capacity available to evacuate power from the state. (ET)
o Despite more than 250 GW installed power, peak demand of 141 Gw, peak deficit exists of
about 9%, impacting 0.4% of GDP
o Transmission Constraint because of a Pocket of High Demand SR, N2, N3
o Transmission Constraint because of a Pocket of High Generation W3, NER
o CERC Congestion Report - June 2015o There are examples that power could be reached through National Grid into the State, but such transmission would be
handicapped because the State level transmission and/or sub-transmission system may not be able to absorb.
o NR import -average Short Term requirement - 1000 MW to 3500 MW, Power import 1000 to 2000 MW, No WR NR corridor
margin, ER NR margin 500 to 1500 MW thus perpetual shortage
o WR import - ER WR (W3) corridor on Short term is 0 MW around the year, no power flow from ER to WR, NR route already
under pressure.
o no corridor available in WR-SR and ER - SR route in advance basis on short term. Further, there is no corridor available under
MTOA till FY 2016 for import of power from NEW grid.
22%
23%
55%
Private
Central
19%
14%
68%
Source - APP
State
State
Private
10
"I dont know how I am going to decide this case, but it appears from the paperwork, we have a bar owner who
believes in the power of prayer and we have an entire church and its devotees that does not."
11
The Concerns
Project Selection
Before
Member CERC
Member (PS) CEA
Member (E&C) CEA
Joint Sec (MoP)
Director (Proj) PGCIL
After
Member (PS) CEA
Member (E&C) CEA
Joint Sec (MoP)
Director (Proj) PGCIL
Advisor (Energy), NITI Ayog
Ex-Member(PS), CEA
Secretary, CERC
The Concerns
Enabling Framework
o Tariff Policy Exemptions proposed Leaves practically nothing which necessarily has to be
put under TBCB Policy without ends.
Before
First two Experimental works for 1200
kV HVDC
Works required to be done cater to an
urgent situration required under
compressed time schedule.
Intrastate transmission projects up to 6 th
Jan 2013
After
First two 1200 kV AC substation
Up-gradations of existing lines of
CTU/STU/PGCIL
Some more up-gradations of lines
Augmentation of existing/under
construction substations of
CTU/STU/PGCIL
Evacuation from Nuclear Power Plants
Projects under compressed time
schedule.
Projects where no bidders comes
forward.
State Sector
o Not opening, exemption period elapsed, Inner ring being too weak for evacuation
o No TSA Post PoC, no TSA for pre-commissioning period, current TSA is not valid
o TSA provisions the penal payment of additional CPG in case the developer fails to obtain
Transmission License or get the tariff adopted within stipulated time frame.
o No recognition of delays caused by the reasons beyond control of the developer including the
clearances like forest, wild life, section 164 approval etc.
o No incentive for early commissioning, the change now under consideration is also half hearted
as it does not spell out any incentive and only recognizes early commissioning, which means
early start of 35 years earning stream.
o Very Steep LDs can eat up to first year tariff
o Variable component of bid pricing can not handle the steep variation of commodities
o No long term instruments of hedging on steel and aluminium available in India
o As many as 120 transmission projects have faced delays because of the developer's inability to
acquire land and get timely clearances from all stakeholders
o Forest, Wild life clearances
15
16
17
Acknowledgements
i.
ii.
iii.
iv.
v.
vi.
vii.
Thank You
Anil.rawal@relianceada.com,anilraawal@gmail.com
18