Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
OPERABILITY STUDY
When to Use?
Optimal from a cost viewpoint
1.when applied to new plants at the point where
the design is nearly firm and documented or
2.to existing plants where a major redesign is
planned.
It can also be used for existing facilities.
Results
Types: The results are the team findings.
Which include: (1) identification of hazards
and operating problems, (2) recommended
changes in design, procedure, etc., to
improve safety; and (3) recommendations
for follow-on studies where no conclusion
was possible due to lack of information.
Nature: Qualitative.
Requirements
Data: The HazOp requires detailed plant descriptions,
such as drawings, procedures, and flow charts. A
HazOp also requires considerable knowledge of the
process, instrumentation, and operation, and this
information is usually provided by team members who
are experts in these areas.
Staff: The HazOp team is ideally made up of 5 to 7
professionals, with support for recording and
reporting. For a small plant, a team as small as two or
three could be effective.
Existing Plant
Plant Superintendent
Process Engineer
Commissioning Manager
Maintenance Engineer
Instrument Engineer
Chemist
Technical Engineer
Principles of HAZOP
Concept
Systems work well when operating under design conditions.
Problems arise when deviations from design conditions occur.
Basis
a word model, a process flow sheet (PFD) or a piping and
instrumentation diagram (P&ID)
Method
use guide words to question every part of process to discover what deviations
from the intention of design can occur and what are their causes and
consequences may be.
PRINCIPLES OF HAZOPS
GUIDE WORDS*
NONE
MORE
OF
LESS OF
PART OF
MORE THAN
OTHER
CAUSE
difficulties
DEVIATION
(from standard
condition
or intention)
CONSEQUENCES
(trivial, important,
catastrophic)
-hazard
-operating
STUDY NODES
The locations (on P&ID or procedures) at which the process parameters are investigated
for deviations. These nodes are points where the process parameters (P, T, F etc.) have
an identified design intent.
INTENTION
The intention defines how the plant is expected to operate in the absence of deviations
at the study nodes.
DEVIATIONS
These are departures from the intension which can be discovered by systematically
applying the guide words.
Process conditions
activities
substances
time
place
GUIDE WORDS
Guide Words
Meaning
No, None
Negation of Intention
More Of
Quantitative Increase
Less Of
Quantitative Decrease
Qualitative Increase
Part Of
Qualitative Decrease
Reverse
Other Than
Complete Substitution
Deviations
No forward flow when there should be, i.e. no flow.
More of any relevant physical property than there should
be, e.g. higher flow (rate or total quantity), higher
temperature, higher pressure, higher viscosity, etc.
Less of any relevant physical property than there should be,
e.g. lower flow (rate or total quantity), lower temperature,
lower pressure, etc.
Composition of system different from what it should be,
e.g. change in ratio of components, component missing, ect.
More components present in the system than there should
be, e.g. extra phase present (vapour, solid), impurities (air.
Water, acids, corrosion products), etc.
What else can happen apart from normal operation, e.g.
start-up, shutdown, uprating, low rate running, alternative
operation mode, failure of plant services, maintenance,
catalyst change, etc.
EXAMPLE
C
The flowsheet shows that raw material streams A and B are transferred by
pump to a reactor, where they react to form product C. Assume that the
flow rate of B should not exceed that of A. Otherwise, an explosion may
occur. Lets consider the flow of A in line 1:
FB FA
NONE
MORE
LESS
AS WELL AS
PART OF
REVERSE
OTHER THAN
No flow of A
Flow of A greater than design flow
Flow of A less than design flow
Transfer of some component additional to A
Failure to transfer a component of A
Flow of A in a direction opposite to design direction
Transfer of some material other than A
Beginning
Select a vessel
Select a line
Examine consequences
Detect hazards
10
11
Repeat 6-10 for all meaningful deviations derived from first guide words
12
13
14
15
16
17
18
19
20
21
22
23
24
25
End
HAZOP DISPLAY
Guide Word Deviation Possible Causes
No
More
More
Flow
Excessive
Over-Cooled
Pump Speed
Product
(Control System) (Incomplete
Reaction)
Product
Unacceptable;
Dump
EXAMPLE
An alkene/alkane fraction containing small amounts of
suspended water is continuously pumped from a bulk
intermediate storage tank via a half-mile pipeline into a
buffer/settling tank where the residual water is settled out prior
to passing via a feed/product heat exchanger and preheater to
the reaction, is run off manually from the settling tank at
intervals. Residence time in the reaction section must be held
within closely defined limits to ensure adequate conversion of
the
alkene and to avoid excessive formation of polymer.
(1)
(2)
(3)