Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Commissioning
Agenda
Agenda
Energy
Usage
Noise
Level
Output
Comment
s
Medium/High
Medium
32-64 Btuh/ft2
Adaptable
solution
32-64 Btuh/ft2
Very
efficient
all-air
system
Low
Low/Mediu
m
High
Medium
48-64 Btuh/ft2
Possible
high
maintenan
ce costs
Low
Low
32-125 Btuh/ft
Very low
maintenan
ce costs
Primary air
dew point
Room air dew
point
Secondary
CWT
Dehumidifica
tion
Option 1
Option 2
48F
51.5F
55F
57.8F
55F
58F
0.002 lbs/lbDA
0.002 lbs/lbDA
P2 drops rapidly
moving into the
room
P3 = at 3ft
into occupied
zone
Active Beam
Diffuser
Chart reports
acoustic values
without room
attenuation
effect
Active beams can
be very quiet!
2 x 8 D nozzle @ 1.20w.c.
Peak in the 2.5 KHz Band
Lw (dB) = 39.1
LwA (dBA) = 38.8
Upstream damper
at SMACNA
recommended
minimum distance
Drywall
Width
Length
Coanda wings
required for
proper throw
characteristics
Note protective
film at inlet of
unit mounted coil
Vacuum with or
without a
horse-hair
bristle brush
Pt = Ps + Pv
Pv = 0,5 x r x v2
Pressure
independent
butterfly type
Iris
Dampers
(682 Btuh)
Example 1
Room Temp
= 75oF
Water temp
= 61oF
Approach temp = 75oF-61oF
= 14oF
Capacity = X
Room Temp
= 68oF
Water Temp
= 61oF
Approach temp = 68oF-61oF
= 7oF
Capacity = 1/2X
Laminar
flow
Non-linear
Expensive
Maintenance issues?
Pressure independent
water control valve
(Constant Flow Rate)
Start-up
Start-up
Sample start-up sequence
1. Confirm start-up and operating sequence with the: plans,
specifications, and consulting engineer.
2. Confirm primary air ducting is free of dirt and debris to prevent
beam nozzle clogging.
3. Seal all duct leaks, and ensure all duct access ports are affixed to
the duct to achieve specified duct leakage rates.
4. Slit protective film at the active beam discharge to allow primary
air to enter the space. Do NOT remove the protective film, until
the work space is in an as-new condition.
Start-up
Sample start-up sequence (contd)
5. Do NOT operate the active beams for temporary heat without
prior written approval from the consulting engineer.
6. Close all operable windows, and ensure building exit doors are
sealed to assist in the envelope dehumidification.
7. Commission and operate the primary air handling unit for
building envelope dehumidification.
8. Balance supply air ducting to each zone.
Start-up
Sample start-up sequence (contd)
9. Ensure a clean environment within which the active beams will
operate (i.e. no gypsum dust or other construction
contamination)
10.Remove protective film from active beam units
11.Ensure piping mains have been flushed and leak-tested, prior
to being connected to the beam coils
12.DO NOT UNDER ANY CIRCUMSTANCES FLUSH THE PIPING SYSTEM
THROUGH THE BEAM MOUNTED COILS.
Start-up
Sample start-up sequence (contd)
13.Confirm that all air has been removed from the distribution
piping. Deliver excess water by increasing the pump flow, or by
closing other zones to assist in the removal of air from the
system.
14.Once the building envelope dew point has been reached, slowly
lower the secondary chilled water temperature to the scheduled
design value. Note that dehumidifying the building envelope
may require several days, or up to a week initially, to completely
dehumidify the space.
15.Confirm secondary water conditions regularly to ensure that it is
properly filtered, and appropriately inhibited.
Start-up
Shop drawings and schedules as a tool for
commissioning