MAIN ENGINE
and AUXILIARY ENGINE
INSTALLATION
FLOWCHART ON SUPERVISION
OWNER
DESIGNER
ENG. MAKER
YARD
FABRICATION &
INSTALLATION
VERIFICATION
& TESTS
CLASS
(ENGINEERING OFFICE)
CLASS
(SURVEYOR)
CLASS
CERTIFICATE
INSPECTION ITEMS
1.
2.
3.
4.
5.
6.
7.
8.
Pre-delivery preparation
On ME arrival
Onboard Installation
Supporting Systems Installation
Start-up test
Safety Devices Test
Bay-test for ME Control Systems
Yard Trial and Official Sea Trial
1. PRE-DELIVERY PREPARATION
1. Validation of required documents:
a. Class Certificates:
b. Makers Documents
2. ON ARRIVAL OF ME
1.
2.
3.
4.
Checks on Engine
arrival
3. ONBOARD INSTALLATION OF ME
1. Preparation for
onboard installation
Crane capacity
ER works schedule
Maker attendance if
necessary
2. ME foundation
welding check
Ultrasonic test witnessed
by Yard and Owner reps,
Class
Record of UT test and
Class Surveyor approval
3. Onboard installation
ME lifting into ER space
Inspection for any
deficiencies
4. Shafting Alignment
FO, LO, Cooling, and Air starting pipes flushing by using chemical
to remove any debris and welding slag to ensure the cleanliness
After Flushing is done, circulating the FO, LO, cooling water to
remove the chemical by means of external pumps and filters.
All supporting systems are to be functionally tested prior to
installation
After all pipes are flushed and cleaned supporting systems pipes
(FO, LO, Cooling, air start, exhaust gas) are installed onto ME.
Check the alignment of pipes onto ME, particularly for Exhaust
gas pipe.
5. START UP TESTS
1.
2.
3.
6. BAY TEST
Carried out in Yards bay
For testing the control system of main engine
and remotely operated from the wheelhouse.
To revise and to re-setup any non working
control system of main engine.
To be done for yard trial preparation.
Besides the main engine, some internal test
are also done (e.g. lifeboat test, fire fighting,
functional test)