Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Basics of PM
Introduction of MS Project
Difference between Standard and professional
edition
Entering Task in task table
Setting start date/Finish date
Basic calendar types
Setting up WBS to task table
Attaching documents
Hyper linking documents
Scheduling Tasks
Team knowledge
Expert judgment
Project files
Industry standards
Project Management Practices:
Building in a Buffer
Enter Duration
To enter a duration, follow these steps:
1 Display the Gantt chart.
2 In the Duration field for each task, type the
duration; for example, 1w or 4d.
3 If a duration is an estimate, add a question
mark after it; for example, 1w? or 4d?.
4 Press Enter.
Elapsed Duration
Duration
Duration
PERT Analysis
When you run a PERT analysis
the resulting calculated values in the
Optimistic Duration - Duration 1
Expected Duration Duration 2
Pessimistic Duration Duration 3
In addition, the resulting
optimistic start and finish dates -Start1 and Finish1.
expected start and finish dates -Start2 and Finish2.
pessimistic start and finish dates - Start3 and Finish3.
PERT Analysis
To set up a PERT
analysis,
follow these
steps:
1 Click View,
Toolbars,
PERT Analysis.
2 On the PERT
Analysis
toolbar, click
PERT Entry
Sheet.
3 For each task,
enter the
optimistic,
expected, and
pessimistic
durations in
the appropriate
fields.
PERT Analysis
4. On the PERT Analysis toolbar, click Calculate PERT.
5.The estimated durations are calculated, and the results change the value
in the Duration field
Dependency Types
Constraint Types
Flexible
Constraint Types
Moderately Flexible Constraints
SNET :For projects scheduled from a start date, this
constraint is automatically applied when you enter a
start date for a task.
FNET :For projects scheduled from a start date, this constraint is
automatically applied when you enter a finish date for a task.
SNLT : For projects scheduled from a finish date, this constraint is
automatically applied when you enter a start date for a task.
FNLT : For projects scheduled from a finish date, this constraint is
automatically applied when you enter a finish date for a task.
Constraint Types
Inflexible Constraints
MSO An inflexible constraint that specifies the exact date
when a task must begin. Other scheduling controls
such as task dependencies become secondary to
this requirement.
MFO An inflexible constraint that specifies the exact date on
which a date must be completed. Other scheduling
controls such as task dependencies become secondary
to this requirement.
Creating Milestones
Comment
Attaching a document
Hyper linking document
Thank you!!