Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Carbon
equivalent
Recommended
procedure
Up to 0.55%
Abov 0.55%
C eq% = C%
+
[C]e - 0.25
HEAT TREATMENT
Symbol
(Carbon Steel)
C-1/2 Mo Steel )
C (3.5 Ni)
PREHEAT
THK(mm)
Temp (0C)
< 25
10
> 25
80
<12
10
> 12
100
ALL
95
1 1/4 Cr 1/2Mo)
ALL
150
ALL
175
F ( Austenitic )
ALL
10
PWHT
THK(mm)
Temp (0C)
<19
None
> 19
595 -650
< 19
None
>19
595 -720
< 19
None
>19
595 -685
< 12
None
>12
705-745
All
705-760
Duration
1 Hr / 25 Min
min 1 Hr
1/2Hr/25 mm
Min,Min of 1Hr
1Hr /25mm
,Min of 2Hrs
1Hr /25mm
,Min of 2Hrs
-
Contd.
Contd.
PWHT SPECIFICATION
Unrestricted heating from ambient upto 300 0C
and restricted heating from 3000C at 500C/Hr
with a temperature differential of not more
than 750C between thermocouples.
Soak temperature 5800C.
Soak period of 1 Hour (Minimum)
Restricted cooling from Soaking temperature
at 500 C /Hr
Unrestricted cooling rate from 3000 C
downwards under insulation.
FCCU Reactor
Detail of Revamp
Segment of shell replacement (Two segments & 3 circumferential
Seams)
Nozzle replacement ( 10 Nos )
Tray replacement
FEATURES of PWHT
Thermo couple welding with capacitor
discharge method.
Temperature difference between any two
thermo couple restricted to max of 30
deg C
Simulation heat treatment conducted on
existing material to decide on cycle
parameters
Reactor was held by Crane during PWHT
: 22-08-2003
Variables for each process
Actual Value
Range
Qualified
I . OPERATOR
1. Nozzle used for Grit blasting
6mm
NA
6-8mm
5-7 kg / cm2
300 mm minimum
30 deg
0.6mm - 1.6mm
G.C 100 ( 1.00mm) ( As per IS 4683 )
NA
Actual Value
Range
Qualified
II. PROCESS
1. Rust Grade of Material used
2. Product form used for blasting
Dry covered shed with exhaust fan and halogen lights for proper
illumination
Sa 21/ 2
Sa 21/ 2
No black spots observed
We certify that the data recorded in this format are correct and that the test has been carried out
as per the requirement of approved work procedure L'&T/WP/03 Rev. 0
L&T QA
CLIENT
Rev.No: 0
: 22-08-2003
Variables for each process
Actual Value
Range
Qualified
I . OPERATOR
1. Surface used for painting
2. Nozzle used for painting / no
3 to 4 kg/cm2
100mm
100 micron
65 to 70 microns
65 to 75 microns
0.38 to 0.43mm
Actual Value
Range Qualified
II. PROCESS
1. Paint specification / Brand used for
application
2. Mixing ratio of paints
5% - 10% ( depending on
temerature conditions various )
5.Pump ratio
80
Dry covered shed with exhaust fan and halogen lights for proper
illumination
III. INSPECTION
1. Visual Inspection during painting
2. Visual Inspection after 24 hrs of drying
B.SUNDAR ( QA)
We certify that the data recorded in this format are correct and that the test has been carried out
as per the requirement of approved work procedure L&T/WP/04 Rev. 0 & Paint Manufacturers recommendations.
L&T QA
CLIENT