Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Chapter 2
Project Management
Project:
An interrelated set of activities with a definite starting
and ending point, which results in a unique outcome
for a specific allocation of resources.
Project Management:
A systemized, phased approach to defining,
organizing, planning, monitoring, and controlling
projects.
Program:
Interdependent set of projects with a common
strategic purpose.
M. VERMA @ 2015
Planning Projects
1. Defining the Work Breakdown
Structure.
2. Diagramming the Network.
3. Developing the Schedule.
4. Analyzing cost-time trade-offs.
5. Assessing risks.
M. VERMA @ 2015
M. VERMA @ 2015
M. VERMA @ 2015
M. VERMA @ 2015
Critical Path:
The sequence of activities between a start and finish that
takes the longest time to complete.
Project Schedule:
Project Costs:
Direct Costs: labor; materials; etc.
Indirect Costs: administration; depreciation;
financial; etc.
Penalty Costs: incurred if project extends
beyond some specific date.
M. VERMA @ 2015
10
M. VERMA @ 2015
11
Normal
Time (NT)
(weeks)
Normal
Cost (NC)
($)
12
$12,000
11
$13,000
1,000
50,000
64,000
7,000
10
4,000
7,000
600
10
16,000
20,000
2,000
24
120,000
14
200,000
10
8,000
10
10,000
16,000
1,500
35
500,000
25
530,000
10
3,000
40
1,200,000
35
1,260,000
12,000
15
40,000
10
52,500
2,500
10,000
13,000
1,000
30,000
34,000
4,000
Totals $1,992,000
Maximum Cost of
Time
Crashing per
Reduction Week ($)
(week)
$2,209,500
M. VERMA @ 2015
12
5. Assessing Risks
Risk:
A measure of the probability and consequence of not
reaching a defined project goal.
Involves the notion of uncertainty.
Strategic Fit.
Service/ Product Attributes.
Project Team Capability.
Operations.
M. VERMA @ 2015
13
2. Statistical Analysis:
a
Most likely time =
2 =
6
Variance for each activity =
e
M. VERMA @ 2015
14
M. VERMA @ 2015
15
Other Activities
Time Estimates (week)
Activity Statistics
Activity
Optimistic
(a)
Most Likely
(m)
Pessimistic
(b)
Expected Time
(te)
Variance
(2)
11
12
13
12
0.11
15
10
15
10
2.78
16
10
1.78
14
25
30
24
7.11
18
10
4.00
25
36
41
35
7.11
35
40
45
40
2.78
10
13
28
15
9.00
15
5.44
0.11
M. VERMA @ 2015
16
Analyzing Probabilities
17
M. VERMA @ 2015
18
Additional Example
Three recent university graduates have formed a partnership and
have opened an advertising firm. Their first project consists of
activities listed in the following table.
a) Draw the precedence diagram (activity-on-node).
b) What is the probability that the project can be completed in 21 days or
less?
c) Suppose it is now the end of the seventh day and that activities a and b
have been completed while activity d is 50 percent completed. Time
estimates for the completion of activity d are 5, 6 and 7. Activities c
and h are ready to begin. Determine the probability of finishing the
project by day 21.
M. VERMA @ 2015
19
Practice Problems
5, 13, 21 and 23.
Active Model Exercise (in MyOMLab).
M. VERMA @ 2015
20